The landfill blocking the Can Tho - Ca Mau highway is about to be relocated

Tạ Quang |

Can Tho - Construction is expected to start on November 15 to relocate the landfill blocking the Can Tho - Ca Mau highway.

Regarding the issue of landfill No. 8 (Cai Rang district) located on the Can Tho - Ca Mau expressway project under the North - South expressway construction project in the East phase 2021-2025, on November 8, the leader of the Project Management Board and Land Fund Development of Cai Rang district said that the contractor selection has been completed, and construction is expected to start on November 15.

Vi tri bai rac nam chan cao toc. Anh: Ta Quang
The location of the landfill is blocking the highway. Photo: Ta Quang

This leader also said that within 45 days, by December 31, the relocation of the garbage overlapping the highway construction site will be completed, in time to hand over the site to the investor according to the direction of the City People's Committee.

At the conference to remove difficulties and obstacles and promote the development of transport infrastructure in the Mekong Delta region held on October 16, Chairman of the People's Committee of Can Tho City Tran Viet Truong said that the People's Committee of Cai Rang District has approved the design and estimate with the area of ​​the landfill that needs to be relocated being 1.95 hectares.

Bai rac so 8 chan ngang cao toc Can Tho - Ca Mau. Anh: Ta Quang
Landfill No. 8 blocks the Can Tho - Ca Mau highway. Photo: Ta Quang

The Chairman of Can Tho City People's Committee also informed that the implementation cost is 13.08 billion VND and will complete the handover of 100% of the site before December 31.

According to a report from the Department of Natural Resources and Environment of Can Tho, landfill No. 8 has an area of ​​4.3 hectares with a total waste volume of over 162,000 tons.

The Project Management and Land Fund Development Board of Cai Rang District said that when handling the landfill, it is necessary to dig 7-8m deep and about 46m wide to serve the construction of a road about 145m long and two fish-carrying roads connecting to National Highway 1.

On the afternoon of October 29, Can Tho City People's Committee announced that the relocation of landfill No. 8 will be divided into 2 phases. In phase 1, Cai Rang District People's Committee will carry out the relocation of the garbage volume overlapping with the North-South Expressway east of landfill No. 8; In phase 2, the Department of Natural Resources and Environment will prepare a project to relocate and treat the entire landfill No. 8.

The Can Tho - Ca Mau Expressway Project, part of the North - South Eastern Expressway Project, started construction on January 1, 2023, is more than 110km long, passing through 5 provinces and cities: Can Tho, Hau Giang, Bac Lieu, Kien Giang, Ca Mau. The project has a total investment of more than VND 27,500 billion, divided into 2 component projects: Can Tho - Hau Giang (37km) and Hau Giang - Ca Mau (73km).

Tạ Quang
TIN LIÊN QUAN

Can Tho informs about the plan to relocate the landfill blocking the highway

|

Can Tho - The garbage transfer process is divided into 4 layers, garbage is moved from the clearance area to the neighboring area within the existing landfill.

Where to spend 13 billion to relocate the garbage dump blocking the Can Tho-Ca Mau highway?

|

Spending more than 13 billion VND to relocate the landfill blocking the Can Tho - Ca Mau expressway, completing the handover of 100% of the site before December 31.

More than 13 billion VND to relocate the landfill blocking the Can Tho - Ca Mau highway

|

Can Tho - The cost of relocating the landfill blocking the Can Tho - Ca Mau expressway is 13.08 billion VND and will complete handover of 100% of the site before December 31.

Gold ring price drops, buyers increase, stores limit sales

|

Today (November 13), the price of plain round gold rings continues to be adjusted down, many people come to stores to buy.

Children continuously hospitalized due to dengue shock

|

HCMC - Compared to 1 month ago, the number of children hospitalized and treated for dengue fever at Children's Hospital 1 has increased. Some cases were hospitalized due to dengue shock and multiple organ failure.

The case of teachers being "forgotten" in the regime: What does Son La Department of Home Affairs say?

|

Son La - Regarding the teachers in Quynh Nhai being "forgotten" of the regime, the Department of Home Affairs said it will ask the Department of Education and Training to review the subjects who have received the subsidy.

Opening of the contest "Green bank for green life"

|

The contest “Green Bank for Green Life” organized by the Vietnam Trade Union opened on November 13 at the Vietnam-Soviet Friendship Cultural Palace, Hanoi.

Missed the appointment of tourism products in Ha Long Bay and Bai Tu Long again

|

Quang Ninh - In 2023, Quang Ninh planned to have 38 new tourism products, but the products in Ha Long Bay and Bai Tu Long Bay were all delayed and this year is still the same.

Can Tho informs about the plan to relocate the landfill blocking the highway

Tạ Quang |

Can Tho - The garbage transfer process is divided into 4 layers, garbage is moved from the clearance area to the neighboring area within the existing landfill.

Where to spend 13 billion to relocate the garbage dump blocking the Can Tho-Ca Mau highway?

Lê Thanh Phong |

Spending more than 13 billion VND to relocate the landfill blocking the Can Tho - Ca Mau expressway, completing the handover of 100% of the site before December 31.

More than 13 billion VND to relocate the landfill blocking the Can Tho - Ca Mau highway

Tạ Quang |

Can Tho - The cost of relocating the landfill blocking the Can Tho - Ca Mau expressway is 13.08 billion VND and will complete handover of 100% of the site before December 31.