Speeding up construction of 571 billion VND intersection in Ho Chi Minh City Ring Road 3 project

ĐÌNH TRỌNG |

In the last months of the year, contractors are speeding up the construction progress of the Binh Chuan intersection of the Ho Chi Minh City Ring Road 3 project through Binh Duong.

On November 27, the working delegation of the Standing Committee of the Binh Duong Provincial Party Committee supervised the implementation of the Ho Chi Minh City Ring Road 3 project, the section passing through Binh Duong province. This included supervising the leadership and direction of the implementation of anti-corruption and anti-negativity work for the Party Committee of the Binh Duong Provincial People's Committee in this project.

The delegation surveyed the construction progress of Binh Chuan intersection of Ho Chi Minh City Ring Road 3 project, section through Binh Duong province. This is a very important intersection that started construction on June 29, 2023.

Doan khao sat qua trinh thi cong nut giao Binh Chuan du an Vanh dai 3 TPHCM. Anh: Dinh Trong
The delegation surveyed the construction process of Binh Chuan intersection of Ho Chi Minh City Ring Road 3 project. Photo: Dinh Trong

This intersection project is 1.3 km long, including highway, bridge, underpass... with a total investment of about 571 billion VND.

According to records at the construction site, after more than 1 year of implementation, the overpass connecting to My Phuoc Tan Van road has basically taken shape. Meanwhile, the approach road is also quite clear, some sections have been filled with crushed stone. The working atmosphere at the construction site is quite busy. Binh Duong is entering the early dry season, favorable for construction, so the units are speeding up the progress.

According to the report on the contractors' output, Dai Thien Truong Joint Stock Company has completed about 39% of the contract rate, and Thai Son Corporation has completed about 18% of the contract rate.

dsdf
Construction of the overpass has been completed by 39%. Photo: Dinh Trong

Of which, 4.5% of the road surface has been constructed, 68% of the drainage box culvert has been constructed, and 55% of the drainage longitudinal culvert has been constructed.

From now until the end of the year, the road section will strive to complete the construction of the crushed stone layer and complete 100% of the drainage culverts. The construction unit is trying to complete and hand over the access road by December 2025.

Regarding the overpass connecting to My Phuoc Tan Van road, up to now, branch bridge A has completed 46% of construction, branch bridge B has completed 46% of construction, branch tunnel C has completed 49% of construction, and branch tunnel D has completed 30%.

sfd
Workers are constructing a branch tunnel. Photo: Dinh Trong

From now until the end of the year, the structure of the T4 and T5 span beams of the bridge branches will be completed. For the tunnel branches C and D, the reinforced concrete structure of the retaining wall and closed tunnel will be completed...

The current difficulties are that the water supply lines, underground power systems, overhead power poles, and transformer stations on My Phuoc Tan Van route have not been relocated. Furthermore, there are still some points at the intersection that have not been cleared yet, and some households and units have not received compensation because they have not agreed on the compensation price...

Duong dan vao cau vuot dang duoc day nhanh tien do. Anh: Dinh Trong
The road leading to the overpass is being sped up. Photo: Dinh Trong
Mot doan da duoc do da dam. Anh: Dinh Trong
A section has been filled with crushed stone. Photo: Dinh Trong

No negative detected

On behalf of the project investor, the Binh Duong Province Traffic Construction Investment Project Management Board said that the Provincial Party Committee, Provincial People's Committee and the board regularly direct the prevention and combat of corruption, waste and negativity in project implementing units.

During the project implementation process, no negative issues have been detected in the implementation of the Ho Chi Minh City Ring Road 3 project through Binh Duong.

ĐÌNH TRỌNG
RELATED NEWS

Ho Chi Minh City Ring Road 3 through Dong Nai clears 90% of land

|

Dong Nai - Component 3 project of Ho Chi Minh City Ring Road 3, section through Nhon Trach district, has cleared more than 90% of the land.

Disbursement progress of 19,280 billion VND project through Binh Duong

|

The Ho Chi Minh City Ring Road 3 project through Binh Duong province has an investment capital of 19,280 billion VND. Currently, units are speeding up the capital disbursement and project construction progress.

Current status of a transport project worth more than 1,100 billion VND in Hue before changing investors

|

HUE will replace the investor and terminate the contract with the weak contractor, causing the key traffic project of To Huu extended road to Phu Bai airport to be delayed.

Vietnam national team wins big in first friendly match in Korea

|

The Vietnamese team had a favorable start in the training trip in Korea when they defeated Siheung FC with a score of 6-0 in the first practice match.

Phan Thiet Waste Treatment Plant has not completely overcome environmental violations

|

Lam Dong - Phan Thiet Waste Treatment Plant has not yet completely overcome environmental violations. While the act of illegal landfilling is being investigated by the police.

Strategy to register aspirations to increase chances of university admission in 2026

|

Choosing and arranging aspirations reasonably will help candidates increase their chances of being admitted to the desired university.

Ho Chi Minh City Ring Road 3 through Dong Nai clears 90% of land

HÀ ANH CHIẾN |

Dong Nai - Component 3 project of Ho Chi Minh City Ring Road 3, section through Nhon Trach district, has cleared more than 90% of the land.

Disbursement progress of 19,280 billion VND project through Binh Duong

ĐÌNH TRỌNG |

The Ho Chi Minh City Ring Road 3 project through Binh Duong province has an investment capital of 19,280 billion VND. Currently, units are speeding up the capital disbursement and project construction progress.