Dismantling barriers, opening traffic lanes for 8-lane roads in Hanoi

SÓNG HỮU |

Hanoi - People have been able to travel temporarily on Ring Road 1 after the fence at the Hoang Cau intersection was removed.

On August 29, the barrier at the entrance to the Ring Road 1 project section Hoang Cau - Voi Phuc (at the Hoang Cau intersection) was removed, opening a traffic route connecting from Xa Dan - O Cho Dua road to Cau Giay.

Accordingly, people and vehicles can temporarily travel on Ring Road 1 smoothly, reducing congestion compared to traveling on De La Thanh road as before.

s
Ring Road 1 section from Hanoi Obstetrics and Gynecology Hospital to Voi Phuc intersection. Photo: Song Huu
s
Ring Road 1 section from Hoang Cau to Lang Ha intersection. Photo: Song Huu

According to records, with the section from Hoang Cau to Lang Ha, people can travel in both directions. Similarly, the section from Hanoi Obstetrics and Gynecology Hospital to the end point of the route - Voi Phuc intersection.

The remaining sections from Lang Ha to Nguyen Chi Thanh, from Nguyen Chi Thanh to Hanoi Obstetrics and Gynecology Hospital, vehicles can circulate on the left side of the route. On the right side of the route, construction work is being completed.

It is expected that by National Day September 2nd, functional agencies will officially organize traffic diversion at the Ring Road 1 project.

Meanwhile, 2 overpasses on the route at the Lang Ha and Nguyen Chi Thanh intersections are still under construction, expected to be completed before December 31, 2026.

z
Cầu vượt nút giao Láng Hạ đang được thi công. Ảnh: Sóng Hữu
Lang Ha intersection overpass is under construction. Photo: Song Huu
s
s
Overpass construction site at Nguyen Chi Thanh intersection. Photo: Song Huu

Mr. Bui Cong Minh (34 years old, residing in Cau Giay ward) is excited that people have been able to travel temporarily on Ring Road 1, Hoang Cau - Voi Phuc section.

Although not completely completed, the temporary traffic opening has also made people's travel more convenient than before" - Mr. Minh said.

According to Mr. Minh, at the starting point of the route at the Hoang Cau intersection (O Cho Dua direction), a traffic light system has been installed but has not been officially put into operation.

This leads to many drivers being quite confused when reaching the intersection, some drivers hesitating, not daring to go straight through the intersection, but deciding to turn right into Hoang Cau street and then turn around for fear of traffic violations, causing the traffic situation at this intersection to be sometimes chaotic.

Functional agencies need to soon have guidance and regulate traffic in this area to make people's travel more convenient" - Mr. Minh said.

s
Route starting point at Hoang Cau intersection. Photo: Song Huu
s
Traffic lights here have been installed but have not been officially put into operation. Photo: Song Huu
s
Traffic at the Ring Road 1 - Hoang Cau intersection is quite chaotic as some traffic light clusters have not officially operated. Photo: Song Huu
s
The construction unit has painted the road markings on the route. Photo: Song Huu
s
The right section of the route, from Lang Ha intersection to Nguyen Chi Thanh, is under construction. Photo: Song Huu
s
Some project items are being implemented. Photo: Song Huu
s
People have to place planks to move into their houses. Photo: Song Huu
s
Sidewalk paving stones piled up in disarray at some locations on the route. Photo: Song Huu
s
A section of sidewalk is being paved with stone. Photo: Song Huu
s
Ring Road 1 section Hoang Cau - Voi Phuc when completed has a cross-section of 50m. Photo: Song Huu
s
The project is expected to be fully completed in 2026. Photo: Song Huu

The Ring Road 1 construction project, Hoang Cau - Voi Phuc section, is more than 2.2km long, with a cross-section of 50m with 8 lanes.

The starting point intersects with Cat Linh - La Thanh - Yen Lang road at Hoang Cau, the ending point is at Voi Phuc traffic junction.

The project has a total investment of more than 7,200 billion VND from the city budget.

The project was approved in December 2017, expected to be completed in 2020, but was delayed due to site clearance problems.

SÓNG HỮU
RELATED NEWS

Hanoi Ring Road 1 accelerates progress ahead of traffic opening day

|

The Ring Road 1 project, Hoang Cau - Voi Phuc section, with a total investment of nearly 7,800 billion VND, is being accelerated, aiming for the goal of technical traffic opening on National Day September 2nd.

50m wide road in Hanoi prepares for technical opening, there is a planned traffic diversion plan

|

Hanoi - Ring Road 1 project, Hoang Cau - Voi Phuc section, more than 2.2km long, is expected to be technically opened to traffic before National Day September 2nd.

Gold price at the close of the session on August 29: SJC gold bars, gold rings simultaneously decrease

|

Gold price at the close of the session on August 29: Domestic gold simultaneously decreased by about 1.5 million to 2 million VND/tael.

Fire at a row of car repair shops on Le Quang Dao street in Hanoi

|

Hanoi - The fire occurred at a row of temporary shacks and a car repair shop on Le Quang Dao street, Tu Liem ward, with a smoke column tens of meters high.

National Highway 13 section passing through old Binh Duong province is congested on the first day of the September 2nd holiday

|

Ho Chi Minh City - On August 29, the number of vehicles returning to their hometowns for holidays began to increase, National Highway 13, the section passing through Binh Duong province before, was congested for a long time.

Recreating precious historical images

|

The photo exhibition "Radiant Mountains and Rivers of Vietnam" celebrating September 2nd helps people, especially the younger generation, better understand the country's history.

Hanoi Ring Road 1 accelerates progress ahead of traffic opening day

Đặng Tiến |

The Ring Road 1 project, Hoang Cau - Voi Phuc section, with a total investment of nearly 7,800 billion VND, is being accelerated, aiming for the goal of technical traffic opening on National Day September 2nd.

Căng bạt thi công vỉa hè, đẩy nhanh tiến độ dự án đường rộng 50m ở Hà Nội

SÓNG HỮU |

Hà Nội - Do thời tiết mưa nhiều, nhà thầu đã căng bạt để công nhân thuận tiện thi công hạng mục vỉa hè, đẩy nhanh tiến độ dự án đường Vành đai 1.

Vành đai 1 Hà Nội tăng tốc, nhiều đoạn được trải nhựa, cây xanh phủ kín dải phân cách

MINH CHÂU - DƯƠNG ANH |

Hà Nội - Sau nhiều năm gặp khó khăn trong công tác giải phóng mặt bằng, tuyến đường Vành đai 1 đang dần thành hình.

50m wide road in Hanoi prepares for technical opening, there is a planned traffic diversion plan

SÓNG HỮU |

Hanoi - Ring Road 1 project, Hoang Cau - Voi Phuc section, more than 2.2km long, is expected to be technically opened to traffic before National Day September 2nd.