Removing bottlenecks at key traffic projects in Quang Tri

THƠ LUÂN |

Quang Tri - Land is the biggest bottleneck affecting the progress of key transport projects, forcing localities to continuously direct removal.

Bottlenecks at key traffic projects

The Coastal Road Project connecting the East-West Economic Corridor phase 1 is one of the key infrastructure projects of Quang Tri province with a total investment of more than 2,731 billion VND. The road, about 48km long, is expected to open up a new development space for the coastal area, strengthening the connection of economic and tourism centers with the East-West trade corridor.

Previously, the project faced the risk of delays when many sections of the route were under construction, and some contractors had not mobilized sufficient manpower and equipment as committed. However, according to the latest report of the Department of Construction, site clearance is basically completed with 99% of the route length being handed over. Contractors are simultaneously deploying construction on locations with clean ground.

Một đoạn của Dự án Đường ven biển kết nối Hành lang kinh tế Đông - Tây giai đoạn 1 thi công cầm chừng, nhiều thời điểm vắng bóng công nhân. Ảnh: Nguyễn Luân
A section of the Coastal Road Project connecting the East-West Economic Corridor phase 1 is being constructed sparingly, with many times workers absent. Photo: Nguyen Luan

To date, bridges, culverts and drainage systems have been basically completed, the value of construction contracts has reached about 70%. Accumulated disbursement reached more than 2,017 billion VND, equivalent to 81.1% of the total allocated capital.

For the Nhat Le 3 bridge and road project at both ends of the bridge, the project currently reaches about 93% of the construction volume. The main items of the bridge have been completed, and the lighting system has been put into operation. At the construction site, construction units are focusing on completing the drainage system, foundation and road surface at the expansion sections on Bao Ninh side.

Cầu Nhật Lệ 3 đã cơ bản hoàn thiện nhưng vướng mặt bằng nên chưa thể thi công đường dẫn lên cầu. Ảnh: Nguyễn Luân
Nhat Le 3 bridge has been basically completed but is facing site clearance issues, so the access road to the bridge cannot be constructed yet. Photo: Nguyen Luan

However, the project has not yet been completed due to site clearance problems in the approach road area of the bridge. Up to now, site clearance of 14.1/15.33ha has been completed. Some households have not yet agreed on compensation, support and resettlement plans, causing the final items to not be able to be implemented synchronously.

Meanwhile, the Dong Hoi City Central Railway Road and Overpass Project, with a total investment after adjustment of 193.5 billion VND, is also racing against schedule after being affected many times by site clearance problems.

Currently, the bridge part package has been basically completed, and the contractor is constructing the access road to the bridge. For the road part, the vertical and horizontal drainage systems have been completed, and construction units are focusing on treating the roadbed and foundation at the handed-over locations.

Cầu vượt đường sắt thuộc Dự án đường và cầu vượt đường sắt trung tâm TP Đồng Hới vẫn chưa thể thi công đường dẫn lên cầu do vướng mặt bằng. Ảnh: Nguyễn Luân
The overpass belonging to the Dong Hoi City Central Railway Road and Overpass Project has not yet been able to construct the access road to the bridge due to site clearance problems. Photo: Nguyen Luan

The value of construction and installation volume reached more than 67 billion VND, equivalent to 71.19% of the contract value. Accumulated disbursement reached about 158 billion VND, equal to 81.7% of the total allocated investment capital. However, some existing site locations are still factors affecting the project completion target in the third quarter of 2026.

Focus on removing difficulties

Faced with the risk of key projects being affected in progress, Quang Tri Provincial People's Committee has continuously issued many directives requesting communes, wards, investors and related units to focus on removing bottlenecks in site clearance.

Regarding the Nhat Le 3 bridge project, the Provincial People's Committee requests units to complete the compensation and resettlement support plan for households still facing difficulties; accelerate land recovery procedures and resolutely handle cases of delays. Localities are assigned to review the entire implementation process, limiting errors in dossiers leading to prolonged site clearance time.

Công nhân, máy móc đẩy nhanh tiến độ Dự án đường và cầu vượt đường sắt trung tâm TP Đồng Hới. Ảnh: Nguyễn Luân
Workers and machinery accelerate the progress of the central railway road and overpass project in Dong Hoi City. Photo: Nguyen Luan

At the central railway overpass project of Dong Hoi City, the Provincial People's Committee requested the Chairmen of the People's Committees of Dong Hoi and Dong Thuan wards, the Director of the Provincial Land Fund Development Center, and related organizations and individuals to be responsible to the Provincial People's Committee if there is a situation of slow site clearance affecting project progress and causing waste of public investment capital.

Recently, Mr. Le Hong Vinh - Chairman of the Provincial People's Committee and Mr. Phan Phong Phu - Vice Chairman of Quang Tri Provincial People's Committee, along with leaders of departments, branches and localities, directly inspected the site of key traffic projects.

Chủ tịch UBND tỉnh Lê Hồng Vinh và Phó Chủ tịch UBND tỉnh Phan Phong Phú kiểm tra tiến độ Dự án thành phần 2 - Cầu Nhật Lệ 3 và đường hai đầu cầu. Ảnh: Hưng Thơ
Chairman of the Provincial People's Committee Le Hong Vinh and Vice Chairman of the Provincial People's Committee Phan Phong Phu inspect the progress of component project 2 - Nhat Le 3 bridge and roads at both ends of the bridge, directing the removal of site obstacles. Photo: Hung Tho

Through actual inspection, the Chairman of the Provincial People's Committee acknowledged the efforts of investors, contractors and localities, and at the same time requested to continue to focus highly on site clearance work; proactively handle difficulties and obstacles on the basis of legal regulations.

Công trường thi công Dự án Đường ven biển kết nối Hành lang kinh tế Đông - Tây giai đoạn 1 đoạn qua xã Cam Hồng. Ảnh: Hưng Thơ
Construction site of the Coastal Road Project connecting the East-West Economic Corridor phase 1 section passing through Cam Hong commune. Photo: Hung Tho

The Chairman of the Provincial People's Committee also requested to strengthen propaganda and mobilization to create consensus among the people; fully implement support policies; develop plans to protect construction in areas that are still problematic. Investors and contractors must mobilize maximum human resources and equipment, take advantage of favorable weather to increase shifts, increase shifts, accelerate construction progress and disburse public investment capital, striving to complete projects according to the set plan.

THƠ LUÂN
RELATED NEWS

Lam Dong needs to remove obstacles for non-budget projects

|

Lam Dong - The working delegation of the Central Inspection Committee works with the Standing Committee of the Provincial Party Committee on removing backlog projects and implementing resolutions.

Da Nang removes procedures for 39 projects, completing social housing target

|

Da Nang - Da Nang City People's Committee has just informed about the licensing situation of 39 investment projects and the implementation of the social housing construction plan for the next phase.

220 projects waiting for land, Lang Son requests focus on removing bottlenecks

|

Lang Son - The Provincial People's Committee has just requested localities and related units to focus on removing "bottlenecks" in site clearance (GPMB) work.

Hai Phong police inform about the tourist boat collision in Lan Ha Bay that killed 1 person

|

Hai Phong - On the evening of June 14, the City Police informed about the waterway accident in Lan Ha Bay.

People excitedly record the aura around the sun in Ninh Binh

|

Ninh Binh - At noon on June 14, many people in the Vu Ban commune area expressed interest when they saw extremely clear sun halos.

People rescue goods to help drivers reduce damage after collision

|

Lam Dong - Many people in Lien Huong commune have joined hands to collect and buy goods to help drivers reduce damage after collisions.

Removing obstacles in the migration out of Hue Citadel

|

HUE - The project to relocate people out of Hue Citadel is being removed from land difficulties, as many households have not yet moved because of many reasons.

Lam Dong needs to remove obstacles for non-budget projects

Phúc Khánh |

Lam Dong - The working delegation of the Central Inspection Committee works with the Standing Committee of the Provincial Party Committee on removing backlog projects and implementing resolutions.

Da Nang removes procedures for 39 projects, completing social housing target

Nguyễn Linh |

Da Nang - Da Nang City People's Committee has just informed about the licensing situation of 39 investment projects and the implementation of the social housing construction plan for the next phase.

220 projects waiting for land, Lang Son requests focus on removing bottlenecks

Khánh Linh |

Lang Son - The Provincial People's Committee has just requested localities and related units to focus on removing "bottlenecks" in site clearance (GPMB) work.