Another trillion-dong hydropower project on the Gam River

Việt Bắc |

Tuyen Quang - The Yen Son Hydropower Project on the Gam River with a total investment of VND3,918 billion is expected to be commercially operational by the end of 2025.

The Yen Son Hydropower Project was first granted an investment certificate by the People's Committee of Tuyen Quang province on September 25, 2011, and the project started construction at the end of December 2013.

The investor is Binh Minh Construction and Tourism Group Joint Stock Company. In early 2024, the project was adjusted to increase the total investment capital to VND 3,918 billion, with a capacity of 90MW with 3 units, to be completed in 2025.

Recorded at the beginning of June 2025, at the Yen Son Hydropower Project (Tuyen Quang province), many items have been formed and are being completed such as overflow cavities, right- shoulder dams, locations for planting generators, and floodgates.

Cac hang muc cua Thuy dien Yen Son dang duoc thi cong. Anh: Viet Bac.
Items of Yen Son Hydropower Plant are under construction. Photo: Viet Bac.

According to the investor's progress report, the concrete pouring of the overflow cavities and right shoulder dams will be completed in July to install valve doors and test the operation of valve doors in October 2025.

Mr. Le Xuan Tuan - Commander of Yen Son Hydropower Project said that the spillway items are being urgently supervised by the investor, general contractor, and consultant to be constructed continuously in 3 shifts to be able to reach the flood-proof elevation before the 2025 rainy season arrives.

Up to now, the project has basically completed important items such as the construction of factories and discharge canals. Some other items such as the 220KV line and distribution station and factory are being accelerated for completion, acceptance and load testing in November 2025.

Du an voi 3 to may phat dien, cong suat 90MW. Anh: Viet Bac.
The project has 3 generators, with a capacity of 90MW. Photo: Viet Bac.

When officially put into operation, Yen Son Hydropower Plant will contribute tens of billions of VND each year to the budget and create jobs for many local workers, helping to transform the economic structure such as cage fish farming, developing eco-tourism, community tourism

According to the investor, all construction items are meeting the set schedule to ensure the installation of all 3 generators and conduct commercial power generation by the end of 2025 as approved by the investment policy.

The Yen Son Hydropower Project is located in 10 communes of Yen Son and Chiem Hoa districts, Tuyen Quang province, including 3 generators, with a total capacity of 90MW, and a total investment of VND 3,918 billion.

This is also the second largest hydropower plant in Tuyen Quang (after Tuyen Quang Hydropower Plant, with a capacity of 342 MW) and is the final steps in the hydropower system on the Gam River approved by the Ministry of Industry and Trade. The project, once completed, will provide the national grid with 356.9 million kWh per year.

Việt Bắc
TIN LIÊN QUAN

Bustling largest fishing port in Tuyen Quang hydroelectric reservoir

|

Not far from Tuyen Quang Hydropower Plant, Na Hang fishing wharf becomes bustling in the afternoon, which is also the time when shrimp and fish caught naturally throughout the lake are transferred.

Put 6 cases and incidents under the monitoring of the Steering Committee for Anti-Corruption and Wastefulness

|

The Central Steering Committee on preventing and combating corruption, waste and negativity agreed to include 6 cases and incidents under the monitoring and direction of the Steering Committee.

Launching the Standing Committee of the Vietnam Fatherland Front Committee of Hanoi City

|

Hanoi - On July 7, a ceremony was held to announce decisions on personnel work of the Vietnam Fatherland Front Committee of Hanoi City.

Provincial Road 9 in Hue is plowed, people are miserable because of dust and elephant holes

|

HUE - The road surface is peeling, with patchy rocks and soil, dusty, and trucks running around, causing serious damage to Provincial Road 9 in Hue, threatening the safety of people.

Truck in accident, 4 tons of fabric stolen by people at night in Hanoi

|

Hanoi A rare incident just happened, a truck carrying 4 tons of fabric had an accident at night, when taking the truck to repair it, all the goods were taken away by the people.

Recovering from the flood, Thai Nguyen people struggle to restore their livelihoods

|

Thai Nguyen - After the big flood, many households in Ba Xuyen ward tried to recover their livelihoods when all the barns and crops were swept away at night.

Bustling largest fishing port in Tuyen Quang hydroelectric reservoir

Việt Bắc |

Not far from Tuyen Quang Hydropower Plant, Na Hang fishing wharf becomes bustling in the afternoon, which is also the time when shrimp and fish caught naturally throughout the lake are transferred.

Thủy điện Tuyên Quang lần đầu mở hết 8 cửa xả đáy

Nguyễn Hoàn |

Thủy điện Tuyên Quang đã mở hết 8 cửa xả đáy, đây là việc chưa từng có sau gần 20 năm đi vào vận hành.

Loạt thủy điện Tuyên Quang xả lũ, xóm bè chênh vênh bên dòng nước xiết

Nguyễn Tùng |

Các thủy điện tại Tuyên Quang đồng loạt xả lũ khiến mực nước trên sông Lô, sông Gâm lên cao, nhiều năm nay người dân xóm bè mới sống cảnh chênh vênh bên dòng nước xiết.