Speeding up progress, Hoa Lien - Tuy Loan Expressway expected to open to traffic in August

Nguyễn Linh |

The 11.5km Hoa Lien - Tuy Loan expressway project in Da Nang is in the final stage, expected to open to traffic on August 30. However, some difficulties in site clearance still exist as 12 households have not yet accepted the compensation plan.

12 households stuck in land clearance

The Hoa Lien - Tuy Loan Expressway project has a total route length of about 11.5km, passing through 3 communes of Hoa Lien, Hoa Son and Hoa Nhon in Hoa Vang district, Da Nang city, including 6 lanes in the completion phase and 4 lanes in the investment phase.

The total investment of the Hoa Lien Expressway project is over VND 2,112 billion, of which the cost of compensation for site clearance including contingency is VND 951 billion. The project implementation period is from 2021 to 2025. The total land area to be recovered is about 60.7873 hectares, about 600 households are affected and the number of resettled households is about 272 households.

The representative of the Ho Chi Minh Road Project Management Board (project investor) said that the Hoa Lien - Tuy Loan Expressway project has so far completed site clearance of 11.43km, reaching 99.7%. However, in reality, there is still about 0.57km of the main route that has not been cleared, involving 12 households, along with 1.2km of service roads and crossroads that have not been compensated.

Regarding resettlement, Da Nang City is currently implementing procedures to build 3 resettlement areas to serve the project. Resettlement area No. 1 in Hoa Nhon commune is expected to start construction in the first quarter, the remaining 2 resettlement areas are carrying out planning procedures and are expected to start construction in the second quarter.

The total land clearance capital for 2025 has been allocated by the Ministry of Transport at 479.8 billion VND to complete all items of the land clearance sub-project, mainly the value to implement 3 resettlement areas.

The project management board recommends that Da Nang City continue to complete the site clearance for the remaining part of the project. Complete 3 resettlement areas to ensure the disbursement of all allocated capital for site clearance, and increase the capacity of Truong Ban quarry to meet the needs of the project.

Mr. Ta Gia Manh Hung, Director of Hoa Lien - Tuy Loan Expressway Project, said that if the site handover is completed in February, the project will be technically open to traffic by August 30 according to the Prime Minister's direction.

In early February, Secretary of the Da Nang Party Committee Nguyen Van Quang inspected the construction site and asked the units to take advantage of favorable weather to speed up the progress to complete the project soon. Secretary of the Da Nang Party Committee Nguyen Van Quang said that the Hoa Lien - Tuy Loan Expressway is very meaningful for the development of the country, as well as for the city, and at the same time requested the People's Committee of Hoa Vang district to soon complete the site clearance of the project to hand over to the construction unit in February.

“We need to take advantage of the beginning of the year, when the weather is favorable, for construction units to make efforts to speed up progress. Ensure that the main route is open by August 30 and the entire route is open by December 30,” Mr. Quang requested.

Da Nang plans to manage Tuy Loan intersection

The Government Office has just issued Official Dispatch No. 865/VPCP-CN on investment in the construction of Tuy Loan intersection under the Da Nang - Quang Ngai Expressway project. This intersection is expected to be assigned to the Da Nang City People's Committee for management.

Under the direction of the Party Central Committee member and Deputy Prime Minister Tran Hong Ha, the Ministry of Transport will adjust the Da Nang - Quang Ngai expressway project to separate the Tuy Loan intersection from the main project. This adjustment will be carried out in accordance with legal regulations and the authority of the Ministry. The Ministry of Transport will also coordinate with the Da Nang City People's Committee to submit to the Prime Minister to assign the management agency of the Tuy Loan intersection. This is expected to be completed this February.

The proposal to separate Tuy Loan intersection was made by the Ministry of Transport in Document No. 408/BGTVT-KHDT dated January 13, 2025 to create conditions for the People's Committee of Da Nang City to invest in the construction of this intersection on a complete scale. Regarding funding, the Ministry of Finance will preside over and coordinate with the Ministry of Planning and Investment to propose a source of central budget support, implementing according to the direction of the Prime Minister.

Nguyễn Linh
TIN LIÊN QUAN

Dust flies everywhere at the Hoa Lien - Tuy Loan expressway project, Da Nang

|

Many people traveling on the Hoa Lien - Tuy Loan expressway project (Da Nang City) had their vision obscured by the dust.

Russian military expands attacks in Kursk, Ukraine gradually loses position

|

Russian troops continue to attack and retake control of many places in Kursk while Ukrainian forces are in a difficult state.

Ancient ban flower forest blooms like a painting in Dien Bien

|

An ancient ban flower forest in Dien Bien is blooming in white mountains and forests, creating a beautiful scene as seen from fairy tales.

Special policewoman shows showing a knife around the neck of a car

|

One of many special performances organized by the Ministry of Public Security on the afternoon of March 9 was "attaching a spear to the neck of a car trailer" performed by a female police officer on duty.

Close-up of the 40-year-old apartment complex, degraded in the heart of Hoa Binh City

|

The shabby apartment complex is located in Group 13, Tan Thinh Ward, Hoa Binh City.

Gold prices increase but buyers only make a profit of 600,000 VND

|

Gold prices last week recorded a strong increase, however, the profits of domestic gold buyers were quite modest.

Cheap poultry eggs are everywhere in Ho Chi Minh City

|

HCMC - Recently, the price of poultry eggs in the city has decreased sharply, to only about 15,000-30,000 VND/dozen, nearly 50% lower than before Tet.

Verifying Hoang Hoa district urgently completes headquarters

|

Thanh Hoa provincial authorities requested verification and reporting on the case of the district headquarters increasing capital from 45 billion to nearly 53 billion VND.

Dust flies everywhere at the Hoa Lien - Tuy Loan expressway project, Da Nang

Nguyễn Linh |

Many people traveling on the Hoa Lien - Tuy Loan expressway project (Da Nang City) had their vision obscured by the dust.

Đà Nẵng thúc tiến độ mặt bằng cao tốc Hòa Liên - Túy Loan

Thùy Trang |

Dự án cao tốc 2.000 tỉ đồng Hòa Liên - Túy Loan có nguy cơ chậm tiến độ vì vướng giải phóng mặt bằng (GPMB). Với gần 5.000 hồ sơ nhà, đất và mộ, TP Đà Nẵng đang phải chạy đua trong 1 tháng nữa để hoàn thành việc giải tỏa, bàn giao cho mặt bằng cho đơn vị thi công.

Giải tỏa gần 5.000 hồ sơ đất, nhà ở và mộ để làm cao tốc Hòa Liên - Túy Loan

THÙY TRANG |

Đà Nẵng - UBND huyện Hòa Vang đã lập 3 tổ công tác để thực hiện công tác giải phóng mặt bằng, giải tỏa đền bù theo yêu cầu của Chính phủ, bởi có gần 5.000 hồ sơ đất, nhà ở và mộ cần được giải tỏa để thực hiện dự án cao tốc Hòa Liên – Túy Loan.