On the afternoon of November 24, Mr. Nguyen Cong Hoang - Vice Chairman of the People's Committee of Quang Ngai province - chaired a meeting with leaders of relevant departments, branches and localities to assess the implementation and disbursement of public investment capital plans for projects in the eastern part of the province.
According to the report of the Department of Finance, the total capital plan for 2025 assigned to implement tasks, programs and projects in the eastern area of Quang Ngai province is 4,648 billion VND. Of which, the capital of the National Target Program is 1,051 billion VND; the capital allocated to investors to implement public investment projects is 3,336 billion VND; other development investment capital is 58 billion VND.

As of November 20, 2025, the National Target Program capital has been disbursed VND 560 billion, reaching 53% of the plan. The capital allocated to investors to implement public investment projects has been disbursed 1,961 billion VND, reaching 59% of the plan. Of which, the provincial departments, branches and sectors disbursed VND1,797 billion, reaching 57% of the plan; the local sector disbursed VND164 billion, reaching 82% of the plan. Compared to the previous reporting week, the disbursed capital increased by 114 billion VND, an increase of 2.6% of the plan.
In the past week, investors have maintained an average disbursement rate; many projects are behind schedule due to problems in compensation and site clearance. The two specialized project management boards in the Eastern region have compiled 76 recommendations, mainly related to procedures and site clearance.
Concluding the meeting, Mr. Nguyen Cong Hoang acknowledged the efforts of departments, branches and localities in speeding up the disbursement of public investment capital; the disbursement results have improved, higher than last week. At the same time, he suggested that 21 investor units with disbursement rates lower than the province's average should urgently speed up the progress to complete the set targets.
Mr. Nguyen Cong Hoang requested departments, branches and localities to review the progress of each project, clearly assign responsibilities for each task; proactively remove difficulties in documents, procedures and site clearance; develop detailed plans, link construction progress with disbursement progress; strive to increase the disbursement rate in December 2025. In particular, localities need to prioritize the disbursement of capital for the National Target Program, develop specific implementation plans and plans, ensure progress and efficiency in capital use.
Mr. Nguyen Cong Hoang assigned the Department of Finance to synthesize weekly disbursement results to monitor, compare and promote progress among investors, units and localities, ensuring the completion of the 2025 disbursement plan.