Progress of the nearly 1,000 billion VND road project at the gateway to Hanoi

Minh Chuyên |

The road project connecting Luong Son town, now Luong Son commune, Phu Tho with Xuan Mai (Hanoi) is being constructed intermittently because many locations have not been handed over land.

According to the Hoa Binh Regional Project Management Board, the Luong Son - Xuan Mai connecting road project (phase 1) has a total investment of 999 billion VND, with a length of 7.6km.

The project started in September 2022, initially expected to be completed by the end of 2025. However, due to delays, the project's construction time was extended to the end of December 2026.

The joint venture of Long Thanh Transport Construction Joint Stock Company, Song Da Construction Investment Joint Stock Company and Hai Phong Transport Construction Joint Stock Company is the construction unit.

Máy móc đang thi công tại dự án. Ảnh: Minh Chuyên
Machinery is under construction at the project. Photo: Minh Chuyen

According to reports, currently the project has only handed over 4/7.6km of site. Contractors have constructed the roadbed, gravel foundation and drainage system along about 3.8km.

At the same time, deploying the item of bored piles for bridge No. 1. The actual value to date has reached about 160/472.61 billion VND, equivalent to 34% of the contract value.

Site clearance is identified as the biggest bottleneck of the project. The total recovered land area is about 34.75ha, affecting about 568 households, of which it is expected that 81 households will have to be resettled.

To date, functional agencies have only completed site clearance of about 16.63/34.75ha, reaching nearly 48% of the recovered area. Inventory work has been carried out with 474/477 households. The total amount of compensation and support has been paid to 279 households and 1 organization of about 110 billion VND.

Nhiều vị trí đã cơ bản hình thành. Ảnh: Minh Chuyên
Many positions have basically been formed. Photo: Minh Chuyen

According to the Project Management Board, many difficulties are directly affecting the project progress such as slow confirmation of land origin, incomplete land registration procedures for some households; obstacles to increased area compared to land use right certificates; some cases of encroachment on roads and streams.

In addition, 2 resettlement areas serving the project are still not completed. The resettlement area in Bui Tram village is under construction and is expected to be completed in May 2026, while the resettlement area in sub-zone 6 of Luong Son commune cannot be implemented due to continued site clearance problems.

The public listing of prolonged compensation plans, slow appraisal and approval, and lack of support mechanisms for adjacent garden land, residential land, and agricultural land in residential areas also cause many households not to agree to hand over land.

Tuyến đường thi công cầm chừng do thiếu mặt bằng. Ảnh: Minh Chuyên
Road construction is slow due to lack of land. Photo: Minh Chuyen

In the afternoon of May 25, Lao Dong Newspaper reporters' records at the construction site in Luong Son commune showed that at the locations where the site has been handed over, many machines and workers are urgently constructing, and some sections of the route have basically formed.

However, in locations where land has not been handed over, construction activities are slow, and many equipment have to stop operating due to lack of deployment land.

Dự án mới giải phóng mặt bằng được 48%. Ảnh: Minh Chuyên
The project has only cleared 48% of the site. Photo: Minh Chuyen

Representatives of Song Da Construction Investment Joint Stock Company said that the unit has mobilized a lot of machinery and manpower to the construction site but cannot maximize capacity due to small and fragmented handover sites. Many equipment have to wait at the construction site because there is no work to deploy continuously.

Ms. Bui Thi Van Anh (resident in Luong Son commune) said that the project was started many years ago, and is still unfinished, significantly affecting the travel of people in the area.

We hope the project will be completed soon so that traffic infrastructure is more synchronized, promoting socio-economic development in the locality," Ms. Van Anh shared.

Nhiều đoạn thi công chưa đồng bộ. Ảnh: Minh Chuyên
Many construction sections are not synchronized. Photo: Minh Chuyen

Currently, the Hoa Binh Regional Project Management Board has sent a document to the People's Committee of Luong Son commune and the Land Fund Development Center to accelerate the preparation, appraisal, and approval of compensation plans. At the same time, soon complete the support mechanism for households with adjacent garden land and residential land and agricultural land in residential areas to remove site bottlenecks and ensure project progress.

Minh Chuyên
RELATED NEWS

Peak heat, Me So bridge project workers change shifts to maintain progress

|

Hanoi - Amidst the scorching hot weather, hundreds of engineers and workers at the Me So bridge construction site are accelerating construction to bring the project to completion on schedule.

Dong Nai approves compensation plan for Ring Road 4 project, more than 46 km long

|

Dong Nai - The Ho Chi Minh City Ring Road 4 project through Dong Nai has had 10 decisions approving compensation plans with a cost of more than 837 billion VND.

Ho Chi Minh City starts construction of 53 new transportation projects in the 2026 - 2027 period

|

Ho Chi Minh City will start construction of 53 new transport projects in the period 2026 - 2027, including 7 urgent steel overpasses to be implemented immediately in 2026.

Gold ring prices fall, people take advantage of buying wedding gold to save money

|

On May 26, gold prices fell, many people in Hanoi rushed to buy in, trading faster, no longer crowded like before.

Power outage in hot weather, many households in the middle of the night find places to sleep

|

Hanoi - On the evening of May 25, some locations in the capital Hanoi experienced power outages for many hours, especially in suburban communes.

Illegal pig gathering point causes pollution in residential areas in Lam Dong

|

Lam Dong - Wastewater from a pig collection point in Quang Son commune is discharged directly into the stream, causing environmental pollution and affecting people's lives.

Peak heat, Me So bridge project workers change shifts to maintain progress

BẠCH DƯƠNG |

Hanoi - Amidst the scorching hot weather, hundreds of engineers and workers at the Me So bridge construction site are accelerating construction to bring the project to completion on schedule.

Dong Nai approves compensation plan for Ring Road 4 project, more than 46 km long

HÀ ANH CHIẾN |

Dong Nai - The Ho Chi Minh City Ring Road 4 project through Dong Nai has had 10 decisions approving compensation plans with a cost of more than 837 billion VND.

Ho Chi Minh City starts construction of 53 new transportation projects in the 2026 - 2027 period

MINH QUÂN |

Ho Chi Minh City will start construction of 53 new transport projects in the period 2026 - 2027, including 7 urgent steel overpasses to be implemented immediately in 2026.