Progress of 50m wide road project in Hanoi reaches 70%, 2 overpasses reveal their shape

SÓNG HỮU |

Hanoi - Ring Road 1 project, Hoang Cau - Voi Phuc section, has reached about 70% progress to date, expected to be completed in 2026.

In the early days of August 2026, although the weather was not favorable, with erratic sunshine and rain, the construction work at the Ring Road 1 project, Hoang Cau - Voi Phuc section, was still urgently deployed by the contractor.

Talking to Lao Dong Newspaper, Mr. Le Ba Luong - Deputy Construction Site Commander of Ring Road 1 package said that the contractor still maintains the construction pace at the project site. Bridge and road items are deployed simultaneously with 3 construction teams.

Up to now, the construction volume has reached about 70%. Despite facing certain difficulties, the contractor still mobilized maximum machinery and personnel, making efforts to ensure the set progress" - Mr. Le Ba Luong said.

sfasvas
Construction machinery for items on the project site. Photo: Song Huu
sca
Green trees and miniatures are planted on the route. Photo: Song Huu

The investment project to build Ring Road 1, Hoang Cau - Voi Phuc section, has its starting point at the intersection with Cat Linh - La Thanh - Yen Lang road at Hoang Cau; the ending point at Voi Phuc traffic junction.

The total length of the route is about 2,274km, with a cross-section scale of 50m.

Total investment of more than 7,210 billion VND. Project implementation period from 2018 to 2026.

The project is invested to complete the entire route according to the plan, with the main items including: Site clearance; foundation, road surface, intersection, drainage, technical trench system, lighting, green trees, sidewalks, traffic organization and relocation of underground and above-ground works within the investment scope.

svasv
Many overpass pillars at Lang Ha intersection have taken shape. Photo: Song Huu

According to records, in addition to the road item, the construction of 2 overpasses on the route (Lang Ha - Giang Vo intersection and Nguyen Chi Thanh intersection) has also been implemented by the contractor in the past time.

However, the construction of the overpass at Nguyen Chi Thanh intersection is still problematic, because the area between piers T3 and T4 of the overpass is the intersection with S3 station belonging to urban railway line No. 5 Van Cao - Hoa Lac.

At the meeting on July 26, the Hanoi Department of Construction requested the Hanoi Urban Railway Management Board to direct contractors to complete the fence items of S3 station within the intersection before August 5, 2026. At the same time, units urgently complete procedures to organize the transportation of materials and waste soil 24/24 hours.

For the Nguyen Chi Thanh intersection overpass project, the investor is required to review and supplement construction measures, build detailed progress weekly; strive to complete concrete pouring of the main span structure before December 15 and open the project to traffic before December 31, 2026.

SÓNG HỮU
RELATED NEWS

Investing 985 billion VND to build a road connecting the Red River dike with Van Phuc bridge

|

Phu Tho - The project to build a road connecting the left dyke of the Red River with Van Phuc bridge with a total investment of nearly 985 billion VND has begun to select a construction contractor.

Recovering more than 33ha of land in Hoai Duc to build inter-zone roads, implementing a series of projects

|

Hanoi - The city is expected to recover more than 33ha of land in Hoai Duc commune to implement 11 projects.

Information on land acquisition and site clearance to expand roads through 7 communes and wards in Hanoi

|

Hanoi - The project to expand National Highway 6, Ba La - Xuan Mai section through 7 communes and wards has basically completed site clearance after more than 3.5 years from the time of commencement.

Big fire at Bien Hoa market in Dong Nai

|

Dong Nai - On the evening of August 5, functional forces were extinguishing a fire that occurred in Tran Bien ward.

9th Hour No. 209: The Unwilling Child - Part 1

|

Hour 9 - Being absolutely trusted by his wife, the husband calmly cheated. When the third person demanded his status, how would he handle it?

Gia Lai is proposed to pilot the socialist ward model

|

Gia Lai - Head of the Central Propaganda and Training Commission Trinh Van Quyet proposed that the province study selecting Hoai Nhon Bac ward to pilot the socialist ward model.

Following the people who sell PNJ diamonds

|

Ho Chi Minh City - PNJ's regulations make "the rich also cry" because they suddenly become unwilling "creditors" for their own diamonds.

Investing 985 billion VND to build a road connecting the Red River dike with Van Phuc bridge

Tô Công |

Phu Tho - The project to build a road connecting the left dyke of the Red River with Van Phuc bridge with a total investment of nearly 985 billion VND has begun to select a construction contractor.

Recovering more than 33ha of land in Hoai Duc to build inter-zone roads, implementing a series of projects

HOÀI ANH |

Hanoi - The city is expected to recover more than 33ha of land in Hoai Duc commune to implement 11 projects.

Information on land acquisition and site clearance to expand roads through 7 communes and wards in Hanoi

SÓNG HỮU |

Hanoi - The project to expand National Highway 6, Ba La - Xuan Mai section through 7 communes and wards has basically completed site clearance after more than 3.5 years from the time of commencement.