Progress of the nearly 65 billion VND medical center upgrade project in Hai Phong

Hoàng Khôi |

Hai Phong - Vice Chairman and the field delegation inspect the project to upgrade the Tien Lang Regional Medical Center.

The project to upgrade the Tien Lang Regional Medical Center started construction in August 2025. Currently, the project has completed the rough construction and is completing items such as: fire prevention and fighting system, water supply and drainage, power lines, facade stone plating, brick plating... It is expected to be completed, handed over and put into use in August 2026.

After being put into use, Tien Lang Medical Center will be arranged as a place to organize reception and outpatient examination and treatment; arrange active resuscitation units at the examination and treatment area to receive, handle, and provide emergency care to seriously ill patients coming for examination and treatment at the Center; arrange specialized clinics, procedure rooms, administrative working areas, inpatient treatment areas and arrange meeting rooms...

Regarding the project to upgrade the Tien Lang Regional Medical Center, Vice Chairman of the City People's Committee Vu Tien Phung requested contractors and construction units to closely follow the schedule and determination to complete it before August 19.

In the context of limited facilities, officials, doctors and physicians of the Center strive to ensure good medical examination and treatment activities for people. In which, strengthen technical equipment, ensure minimum medical examination and treatment needs; effectively apply the city's support mechanisms and policies to attract, train, and improve the quality of human resources; maximize existing equipment and machinery to serve patients; proactively advise the Department of Health and the Department of Home Affairs to consolidate the organizational structure and clearly define tasks.

Along with that, the Center continues to support the Commune Health Station in professional tasks; do well in primary health care tasks, especially maternal and child health care; uphold the spirit and attitude of serving patients.

The project to invest in upgrading the Tien Lang Regional Medical Center aims to invest in central facilities with a scale of 250 beds or more (currently 190) with departments and rooms according to regulations, developing new high technology, performing the task of medical examination and treatment, care and protection of people's health. The project has a total investment of more than 64.9 billion VND from the city budget, the investment scale is to build 1 5-story building unit of the inter-specialized medical examination area, with a total construction floor area of about 4,540 m2 (at the main gate facing Pham Ngoc Da street) along with auxiliary works such as yards, sidewalks, green parks, water supply and drainage...

Hoàng Khôi
RELATED NEWS

Dialogue on site clearance for the 5-story apartment building demolition project in Hai Phong

|

Hai Phong - April 15, Do Son ward organized a dialogue with households related to the project of site clearance and demolition of a 5-story apartment building at 75 Ly Thanh Tong.

Complete site clearance for a 40-story apartment project in Hai Phong

|

Hai Phong - To date, Le Chan ward has completed the site clearance for the Urban Renovation Investment Project (Project 150 To Hieu).

Hai Phong provides timely and appropriate housing support for children of Agent Orange victims

|

Hai Phong - Hai Phong has just issued a plan to support the removal of temporary and dilapidated houses for children of resistance activists infected with chemical toxins.

92.5 trillion VND project in Hanoi: Hundreds of people come to hear information about land acquisition

|

Hanoi - The work of land acquisition and site clearance for the Olympic Sports Urban Area project, with an investment of 925 trillion VND, is being actively implemented by communes.

People excitedly attend the Buddha bathing ceremony during the Chol Chnam Thmay Tet holiday

|

Ho Chi Minh City - Chôl Chnăm Thmây Tet at Candaransi Pagoda attracts a large number of people, highlighted by the Buddha bathing ritual and imbued with the identity of the Khmer people.

Terminating the operation of the National Traffic Safety Committee from June 1, 2026

|

The Prime Minister decided to terminate operations and dissolve the National Traffic Safety Committee and the Traffic Safety Boards of localities from June 1, 2026.

Case of teacher punishing 5 students for self-injecting needles in their hands: Test results have been available

|

Ho Chi Minh City - 5 students who were punished by teachers by self-injecting needles into their hands have blood counts within normal limits and are continuing to be monitored for their health.

Government directs inspection of the arrangement and assignment of deputy-level leaders

|

The Government requests inspection and supervision of legal regulations on arranging and assigning the number of deputy-level leaders according to regulations.

Dialogue on site clearance for the 5-story apartment building demolition project in Hai Phong

Hoàng Khôi |

Hai Phong - April 15, Do Son ward organized a dialogue with households related to the project of site clearance and demolition of a 5-story apartment building at 75 Ly Thanh Tong.

Complete site clearance for a 40-story apartment project in Hai Phong

Hoàng Khôi |

Hai Phong - To date, Le Chan ward has completed the site clearance for the Urban Renovation Investment Project (Project 150 To Hieu).

Hai Phong provides timely and appropriate housing support for children of Agent Orange victims

Hoàng Khôi |

Hai Phong - Hai Phong has just issued a plan to support the removal of temporary and dilapidated houses for children of resistance activists infected with chemical toxins.