According to report No. 376 dated November 24, 2025 of the Department of Finance of Tuyen Quang province, in 2025, the total public investment capital of the province (including local and central budget capital) will be more than 17,331 billion VND. The capital disbursement progress to date has only reached 33.69% (equivalent to more than VND 5,832 billion).
Some key projects and works of Tuyen Quang - Ha Giang Expressway (phase 1), the Project to build a road from My Lam Mineral Spring Tourist Area to National Highway 2D connecting to Tuyen Quang - Phu Tho Expressway, programs, projects for population arrangement, national target programs... are also behind schedule in disbursing public investment capital.
The reason given is that in some projects, additional capital from the central budget has not been allocated, and some construction locations have not been handed over due to difficulties in site clearance. In addition, recently, heavy rain, flash floods and flash floods have affected the construction progress.

According to the assessment of the Department of Finance of Tuyen Quang province, the reasons for the delay in the disbursement of public investment capital are many reasons such as compensation and site clearance at some projects are facing difficulties. In addition, part of the reason is the arrangement and consolidation of commune-level administrative units, lacking qualified and capable staff to implement.
Mr. Tran Viet Hung, Director of the Project Management Board for Investment and Construction of Project No. 1 of Tuyen Quang province, said that the weather is currently favorable, and construction units are required to speed up the progress.
"The Project Management Board is strengthening working groups to go to the route, going to the foot of the project to urge the contractor to speed up the construction progress. The goal is to make payments as soon as possible," Mr. Hung informed.
There is not much time left in 2025, Tuyen Quang province is determined to implement solutions to speed up the disbursement of public investment capital. In which, land problems are completely resolved, site inspection is increased, contractors are urged to focus on machinery and human resources to carry out "3 shifts, 4 teams" to ensure the set progress.
Mr. Nguyen Manh Tuan - Permanent Vice Chairman of Tuyen Quang Provincial People's Committee said that in a strong and determined spirit, not retreating in disbursing public investment capital, sectors and localities urgently receive the handover of works, absolutely not being left uncompromised.
The People's Committee of Tuyen Quang province requires sectors and localities to be flexible and creative, especially with emergency projects and projects preparing for investment, preparing to urgently complete procedures to make advances in accordance with regulations, increasing the disbursement rate of capital.
"For projects using extended capital that must focus on implementing all solutions to speed up the disbursement progress, the province will consider the responsibility of collectives and individuals who slow down the disbursement of capital. Regarding capital allocated from the beginning of the year and capital allocated in the year, it must also be drastic, everything must be implemented synchronously", the Standing Vice Chairman of Tuyen Quang Provincial People's Committee emphasized.