Progress of site clearance, verification of land origin of National Highway 6 renovation and upgrade project

Anh Tuấn |

Hanoi - Xuan Mai Commune People's Committee has just organized a dialogue with leaders of organizations, agencies, and units affected by the National Highway 6 renovation and upgrade project.

The Steering Committee for site clearance of Xuan Mai commune has just organized a dialogue conference with leaders of organizations, agencies, and units in the commune affected by the National Highway 6 renovation and upgrade project, mobilizing the dismantling and handover of construction site for the project.

Deputy Head of the Economic Department of the commune Nguyen Thanh Lai said: The project to renovate and upgrade National Highway 6, Ba La - Xuan Mai section passing through the commune has a total length of 6.53 km, a total recovered land area of 38.58 ha with 1,804 land plots. Including 917 plots used by households and individuals; 17 defense land plots; 29 land plots of headquarters of agencies, units, and organizations; 1 land plot of belief; 133 land plots managed by the Commune People's Committee and 705 agricultural land plots.

To date, the site has been handed over with an area of 24.04 ha, reaching 62.3%; 872 compensation plans have been approved; 795 land acquisition decisions have been issued; compensation, support, and relocation of 1 religious land project have been completed; compensation, support for site clearance and relocation for 6 graves.

At the same time, measurement, survey, and inventory work has been completed; the origin of land has been confirmed for 1,068 land plots; and for 452 land plots, the Economic Department is continuing to review and confirm the origin of land and assets attached to land. 232 plans have been appraised and reviewed; the City Traffic Board is completing and publicizing them according to regulations; and 970 land plots have not yet been prepared or appraised.

Within the project scope, there are 23 agencies, units, and organizations using land, with a recovered area of 3.78 ha. To date, the Department of Logistics - Technology, Special Forces Corps (warehouse T342) has completed site clearance and handed over the site to the investor with an area of 2.38 ha; Xuan Mai Commune People's Committee has handed over the site and is proceeding to dismantle the headquarters of Xuan Mai town People's Committee (old) with an area of 398.7 m2.

At the same time, the remaining 21 agencies and units have minutes of measurement, investigation, survey, and inventory; of which 2 agencies and units have publicly drafted compensation and support plans.

Xuan Mai commune strives to complete site clearance work in the second quarter of 2026.

Ông Hoàng Minh Hiến - Bí thư Đảng ủy, Chủ tịch HĐND xã Xuân Mai chủ trì hội nghị đối thoại với lãnh đạo các tổ chức, cơ quan, đơn vị trên địa bàn xã bị ảnh hưởng bởi dự án cải tạo, nâng cấp Quốc lộ 6. Ảnh: Hoàng Tình
Mr. Hoang Minh Hien - Secretary of the Party Committee, Chairman of the People's Council of Xuan Mai commune chaired a dialogue conference with leaders of organizations, agencies, and units in the commune affected by the project to renovate and upgrade National Highway 6. Photo: Hoang Tinh

Secretary of the Party Committee of Xuan Mai commune Hoang Minh Hien emphasized that in the current development context, transport infrastructure plays a leading role in planning and opening up new development space.

In particular, when the elevated railway project towards Xuan Mai began to be launched, the requirement for site clearance became even more urgent and needed to be implemented drastically, synchronously, and urgently.

Mr. Hien affirmed that the sooner the project is completed, the sooner Xuan Mai will have favorable conditions to attract investment, develop socio-economy, and improve people's lives.

In that spirit, Xuan Mai commune identifies site clearance as the top priority task at the present time and must be completed in June 2026 according to the plan.

Mr. Hien hopes to continue to receive the consensus and support of agencies, units, and organizations within the project scope; and at the same time requests units to proactively coordinate and implement dismantling and handover of land soon to ensure general progress.

With the spirit of setting an example, the comrade requested the commune's agencies, together with military and police units in the area, to complete the handover of land before April 18; the remaining units to complete before April 25.

Leaders of Xuan Mai Commune People's Committee will accompany, support, and promptly remove difficulties and obstacles; and at the same time be responsible for the progress and effectiveness of site clearance work.

For the Hanoi City Traffic Construction Investment Project Management Board, it is necessary to direct contractors to focus manpower and vehicles, accelerate the construction progress for the allocated area; and at the same time complete compensation, support, and resettlement plans, ensuring the rights of relevant organizations and units.

Anh Tuấn
RELATED NEWS

National Highway 6 upgrade project: Ward proposes solutions to handle cases of not handing over land

|

Hanoi - For cases of intentionally delaying the handover of land for the National Highway 6 upgrade project, Chuong My ward will apply handling measures according to regulations.

Land acquisition to expand National Highway 6: There are still some difficulties and obstacles waiting to be resolved

|

Hanoi - Chuong My Ward has pointed out some difficulties and obstacles in site clearance for the National Highway 6 expansion project and is gradually removing them.

92.5 trillion VND project in Hanoi: Hundreds of people come to hear information about land acquisition

|

Hanoi - The work of land acquisition and site clearance for the Olympic Sports Urban Area project, with an investment of 925 trillion VND, is being actively implemented by communes.

People excitedly attend the Buddha bathing ceremony during the Chol Chnam Thmay Tet holiday

|

Ho Chi Minh City - Chôl Chnăm Thmây Tet at Candaransi Pagoda attracts a large number of people, highlighted by the Buddha bathing ritual and imbued with the identity of the Khmer people.

Terminating the operation of the National Traffic Safety Committee from June 1, 2026

|

The Prime Minister decided to terminate operations and dissolve the National Traffic Safety Committee and the Traffic Safety Boards of localities from June 1, 2026.

Case of teacher punishing 5 students for self-injecting needles in their hands: Test results have been available

|

Ho Chi Minh City - 5 students who were punished by teachers by self-injecting needles into their hands have blood counts within normal limits and are continuing to be monitored for their health.

Government directs inspection of the arrangement and assignment of deputy-level leaders

|

The Government requests inspection and supervision of legal regulations on arranging and assigning the number of deputy-level leaders according to regulations.

Trusting Lao Dong Newspaper to maintain its No. 1 position in protecting workers

|

Hanoi - At a working session with Lao Dong Newspaper on the morning of April 16, Chairman of the Vietnam General Confederation of Labor Nguyen Anh Tuan expressed his belief that Lao Dong Newspaper will continue to maintain its number 1 position in protecting workers.

National Highway 6 upgrade project: Ward proposes solutions to handle cases of not handing over land

Anh Tuấn |

Hanoi - For cases of intentionally delaying the handover of land for the National Highway 6 upgrade project, Chuong My ward will apply handling measures according to regulations.

Phải di dời 6 ngôi mộ để thực hiện dự án nâng cấp Quốc lộ 6

Anh Tuấn |

Hà Nội - Đối với dự án Cải tạo nâng cấp đường Quốc lộ 6, UBND xã Xuân Mai cho biết vẫn còn một số vướng mắc liên quan đến công tác giải phóng mặt bằng.

Land acquisition to expand National Highway 6: There are still some difficulties and obstacles waiting to be resolved

SÓNG HỮU |

Hanoi - Chuong My Ward has pointed out some difficulties and obstacles in site clearance for the National Highway 6 expansion project and is gradually removing them.