Overview of the fastest construction item of the Nguyen Trai bridge project, Hai Phong

Mai Dung |

Hai Phong - The package of approach bridges, approach roads and intersections is the fastest construction item in the entire Nguyen Trai bridge project and urban embellishment of the surrounding area.

Fastest item of Nguyen Trai bridge

The project to invest in the construction of Nguyen Trai bridge and urban embellishment in the surrounding area is a key project of the city in 2024, belonging to group A, special-grade traffic works with a total investment of more than 6,235 billion VND. The main bridge section is 550.6 m long; the length of the approach bridge on Thuy Nguyen side is 459 m, and the length of the approach bridge on Ngo Quyen side is 466.8 m.

The bidding package for the construction of approach bridges, approach roads and intersections has a contract value of 1,435 billion VND, started on December 18, 2024, and is expected to be completed in December 2026. The project contractor is the Joint Venture of Thang Long Corporation - JSC, VNCN E&C Technical Construction Investment Joint Stock Company, Thang Long Bridge 3 JSC and HJC Construction Investment Group JSC.

Toàn cảnh công trường thi công cầu dẫn dự án cầu Nguyễn Trãi. Ảnh: Hoàng Khôi
Overview of the construction site of the Nguyen Trai bridge project. Photo: Hoang Khoi

According to information from the Hai Phong Traffic Construction Investment Project Management Board (investor), regarding the approach bridge section, currently, units are simultaneously deploying 14 bored pile and bridge pier construction teams on both sides of Thuy Nguyen and Ngo Quyen. Progress by early April is to complete 322/340 bored piles, 21/29 abutments, branch bridge piers, 20/20 abutments, approach bridge piers, 21/26 shielding walls; 20 shielding wall nails, 11 hollow bridge abutment beams, 11 hollow bridge abutment beams... The approach road section has also completed the K98 soil foundation embankment construction, and is currently constructing type 2 gravel aggregate.

The total contract value to date has reached more than 80% of the contract value, which is the item with the fastest progress in the entire Nguyen Trai bridge project.

Focusing on occupational safety and health

According to Mr. Dinh Duc Duy - representative of the supervision consulting unit, the progress of the approach bridge and approach roads basically closely follows the set progress, striving to complete all approach bridges before September 2, 2026.

In addition to ensuring project progress, occupational safety and health are also focused on by units. According to representatives of supervision consultants, more than 200 workers are currently working 3 shifts/day at the construction site. Workers are fully equipped with personal protective equipment and safety checks before each shift. Construction units strictly comply with technical procedures, install warning systems, barriers and closely monitor dangerous areas.

In addition, strengthen inspection and handling of violations and develop timely incident response plans to minimize risks for workers.

Công tác bảo đảm an toàn vệ sinh lao động được chú trọng. Ảnh: Mai Dung
Work on ensuring occupational safety and health is emphasized. Photo: Mai Dung

Mr. Bui Van Khanh - a bridge construction worker - said that labor safety and hygiene work is strictly inspected by contractors and supervisory units. Thanks to that, workers also raise their awareness of compliance, voluntarily equip themselves with protective equipment and necessary knowledge and skills to prevent all risk factors.

It is known that in addition to the bidding package for the construction of approach bridges, approach roads and intersections, the cable-stayed bridge and Nguyen Trai - Le Hong Phong underpass items are also being accelerated, striving to bring the entire project to completion on September 2, 2027.

Gói thầu cầu dẫn, đường dẫn và nút giao dự kiến hoàn thành tháng 12.2026. Ảnh: Mai Dung
The approach bridge, approach road and intersection package is expected to be completed in December 2026. Photo: Mai Dung
Mai Dung
RELATED NEWS

Investigating the case of a worker dying from being caught in a construction cable in Hai Phong

|

Hai Phong - Information from the Trade Union of Sanhua Co., Ltd., functional agencies are investigating an accident caused by an electric cable that killed a worker tragically.

87 households have not handed over land, construction of Binh Thuy bridge is behind schedule

|

Can Tho - Binh Thuy bridge, belonging to the project to upgrade and expand National Highway 91 (section from Km0 - Km7), has not yet been able to be implemented because 87 households have not handed over the site.

Progress of the intersection worth more than 565 billion VND belonging to the Nguyen Trai bridge project in Hai Phong City

|

Hai Phong - By the end of March 2026, the site clearance progress of the Nguyen Trai - Le Hong Phong intersection will only reach about 60%.

Road worth over 1,300 billion VND in Hanoi completed all items in March

|

Hanoi - Ring Road 2.5 project, Dam Hong - National Highway 1A section, 1.6km long, with a total capital of over 1,300 billion VND, will complete all items in March 2026.

Mai Thu Huyen: I really hate the phrase "mobile vase

|

In "Samediday Afternoon Coffee", producer, director, actress Mai Thu Huyen shared her perspective on the development of the film industry in 2026.

Cold storage fire in Bui Xuong Trach, 6 motorbikes and cars burned down

|

Hanoi - A cold storage fire on Bui Xuong Trach street (Khuong Dinh ward) caused many properties to be burned down, including 6 motorbikes and 1 truck.

People discover a bullet and explosives in the Ba River area

|

Gia Lai - Police warn people not to move or dig up explosives and remaining bombs and bullets.

Death certificate, marriage registration "how important" without authorization

|

The delegate wondered, a deceased person needs a death certificate for burial, how to handle not authorizing the Chairman of the Commune People's Committee when this person is busy attending a meeting?

Investigating the case of a worker dying from being caught in a construction cable in Hai Phong

Hoàng Khôi |

Hai Phong - Information from the Trade Union of Sanhua Co., Ltd., functional agencies are investigating an accident caused by an electric cable that killed a worker tragically.

87 households have not handed over land, construction of Binh Thuy bridge is behind schedule

Tạ Quang |

Can Tho - Binh Thuy bridge, belonging to the project to upgrade and expand National Highway 91 (section from Km0 - Km7), has not yet been able to be implemented because 87 households have not handed over the site.

Progress of the intersection worth more than 565 billion VND belonging to the Nguyen Trai bridge project in Hai Phong City

Mai Dung |

Hai Phong - By the end of March 2026, the site clearance progress of the Nguyen Trai - Le Hong Phong intersection will only reach about 60%.

Road worth over 1,300 billion VND in Hanoi completed all items in March

SÓNG HỮU |

Hanoi - Ring Road 2.5 project, Dam Hong - National Highway 1A section, 1.6km long, with a total capital of over 1,300 billion VND, will complete all items in March 2026.