Ho Chi Minh City speeds up progress of Long Thanh airport connection projects

Huyền Trân |

HCMC - The An Phu intersection project, Ring Road 2, 3, and the expansion of the HCMC - Long Thanh - Dau Giay expressway are required to speed up progress to connect to Long Thanh airport.

According to information from the Ho Chi Minh City Department of Transport on February 5, to ensure the progress of projects connecting Ho Chi Minh City to Long Thanh International Airport under the direction of Deputy Prime Minister Tran Hong Ha, the Department of Transport proposed that the Ho Chi Minh City People's Committee direct the Management Board of Investment and Construction of Traffic Works (Transport Board) to urgently carry out a number of tasks.

In particular, focusing on mobilizing human resources, machinery, equipment, supplies and construction materials to speed up the construction progress of projects to be completed in December 2025, including: the overpass section in Thu Duc city of Component Project 1 of the Ho Chi Minh City Ring Road 3 Construction Investment Project; An Phu Intersection Construction Project (Thu Duc city).

The Transport Department is speeding up the progress of investment preparation for the Ho Chi Minh City Ring Road 2 project (section from Phu Huu Bridge to Vo Nguyen Giap Street and section from Vo Nguyen Giap Street to Pham Van Dong Street), ensuring construction starts in the second quarter of 2025; construction is completed before June 30, 2026.

The Transport Department quickly deployed the project to expand the Ho Chi Minh City - Long Thanh - Dau Giay Expressway (the section connecting An Phu intersection to Ring Road 2, about 4km long), ensuring the construction progress will start in the third quarter of 2025 and be completed in the third quarter of 2026.

Previously, on January 9, Deputy Prime Minister Tran Hong Ha inspected the site and had a working session to review the progress of the Long Thanh International Airport construction investment project and the implementation of projects connecting Ho Chi Minh City to Long Thanh International Airport.

Regarding a number of projects and works connecting Ho Chi Minh City with Long Thanh International Airport, Deputy Prime Minister Tran Hong Ha directed Ho Chi Minh City to focus on ensuring the progress of the projects (Ho Chi Minh City Ring Road 3 Project; An Phu Intersection Construction Project; Ho Chi Minh City Ring Road 2 Project, section from Phu Huu Bridge to Vo Nguyen Giap Street and section from Vo Nguyen Giap Street to Pham Van Dong Street) and the Ho Chi Minh City - Long Thanh - Dau Giay Expressway Expansion Project (section connecting An Phu Intersection to Ring Road 2, about 4km long)...

Huyền Trân
TIN LIÊN QUAN

The 41,000 billion VND road in Ho Chi Minh City has 31 problems

|

The Beltway 3 project through Ho Chi Minh City with a total capital of more than 41,000 billion VND is still stuck with 31 sites in Thu Duc City and Binh Chanh District, affecting construction progress.

No change in target to complete Long Thanh airport by 2025

|

Dong Nai - Prime Minister Pham Minh Chinh and the Central working delegation extended New Year greetings, presented gifts and inspected the progress of the Long Thanh airport project.

Ho Chi Minh City starts 4 projects worth over 42,000 billion VND in 2025

|

HCMC - Beltway 2, Nguyen Khoi bridge and road, renovation of Xuyen Tam canal and the North bank of Doi canal with a total capital of more than 42,000 billion VND will start construction in 2025.

Resort, hotel headache due to online booking fraud

|

Consecutive fraudulent booking occurred on the occasion of the Lunar New Year, causing resorts and hotels to find a way to overcome and recommend visitors.

Early retirement policy for preschool teachers

|

Allow preschool teachers to retire early compared to the age is the policy built based on the characteristics of this object's career activities.

Buffalo died in Quang Tri forest, increasing number

|

Quang Tri - There were 29 abnormal dead buffaloes discovered by people scattered in the forest area.

Vice Chairman of Ha Tinh province talked about retirement

|

Ha Tinh - In the morning of 8.2, Mr. Le Ngoc Chau - Vice Chairman of Ha Tinh People's Committee shared with the Lao Dong Newspaper reporter about his retirement before his age.

Parents' minds when teachers and schools stop teaching

|

Parents have mixed reactions when the schools announce the suspension of organizing tutoring activities in the school.

The 41,000 billion VND road in Ho Chi Minh City has 31 problems

MINH QUÂN |

The Beltway 3 project through Ho Chi Minh City with a total capital of more than 41,000 billion VND is still stuck with 31 sites in Thu Duc City and Binh Chanh District, affecting construction progress.

No change in target to complete Long Thanh airport by 2025

HÀ ANH CHIẾN |

Dong Nai - Prime Minister Pham Minh Chinh and the Central working delegation extended New Year greetings, presented gifts and inspected the progress of the Long Thanh airport project.

Ho Chi Minh City starts 4 projects worth over 42,000 billion VND in 2025

MINH QUÂN |

HCMC - Beltway 2, Nguyen Khoi bridge and road, renovation of Xuyen Tam canal and the North bank of Doi canal with a total capital of more than 42,000 billion VND will start construction in 2025.