Ho Chi Minh City rescues 10,000 billion VND tide prevention project stranded for 4 years

MINH QUÂN |

Ho Chi Minh City proposed to the Prime Minister many solutions to remove obstacles to the nearly 10,000 billion VND tide prevention project that has been "stranded" for nearly 4 years.

The Ho Chi Minh City People's Committee has just sent a document to the Prime Minister on a plan to remove difficulties for the project to solve flooding caused by tides in the Ho Chi Minh City area, taking into account climate change factors (phase 1).

This important project started in mid-2016, aiming to control flooding caused by high tides and respond to climate change over an area of ​​570 km², serving about 6.5 million people in the central area and along the Saigon River.

Although 90% of the work has been completed, the project has had to suspend construction three times, the most recent of which lasted from November 15, 2020 to present.

According to the Ho Chi Minh City People's Committee, the total investment of the project is likely to exceed VND10,000 billion - a national important project criterion. The authority and implementation procedures for the project that is in the process of being implemented have not been clearly defined. Ho Chi Minh City said it will propose an implementation plan and report to the Government during the process of adjusting the project's investment policy.

According to the HCMC People's Committee, the total disbursement value for the project is nearly VND8,300 billion, of which VND7,100 billion is from loans and more than VND1,181 billion is from the investor's own capital. The project still needs about VND1,800 billion more to complete.

The biggest difficulty is that the investor does not have the capital to continue construction. BIDV Bank - the capital sponsor - cannot sign the credit contract appendix with the investor to submit to the State Bank to extend the time for disbursing re-lending capital. The reason is that the State Bank has recovered about VND 3,560 billion of re-lending capital for BIDV. Even though the disbursement extension is granted, BIDV still cannot continue to disburse because the project has not been paid.

To resolve the difficulties, the Ho Chi Minh City People's Committee proposed that the Government Working Group consider submitting to the Government a Resolution allowing Ho Chi Minh City to entrust the city budget to the Ho Chi Minh City State Financial Investment Company (HFIC) to provide loans for investors to complete the project.

However, the Ministry of Finance believes that this option is not suitable because the 2015 State Budget Law does not stipulate the use of local budgets to entrust local development investment funds.

Therefore, HCMC currently has no basis to mobilize entrusted capital. The solution that HCMC proposed is to review and adjust the payment terms in the contract. Accordingly, payment will be made to investors using the identified land funds, creating capital to continue construction and completion of the project.

In addition, the project is also facing difficulties due to the lack of a basis for payment under the BT (build-transfer) contract. Ho Chi Minh City has negotiated and signed a contract, along with a contract appendix, under which the investor will be paid 16% of the final settlement value (about VND 1,588 billion) in land funds and the remaining 84% (about VND 8,380 billion) in cash.

To ensure the legal basis and adjust payments to suit reality, it is necessary to make overall adjustments to the project. This requires a lot of time and is complicated, because it is necessary to negotiate and agree with BIDV and investors on loan interest.

Ho Chi Minh City proposed to simultaneously adjust the project implementation time and adjust the payment terms in the contract.

After the adjustment, Ho Chi Minh City will have a legal basis to pay with land funds, helping to solve capital sources for investors and reduce costs arising from interest during the waiting period.

MINH QUÂN
TIN LIÊN QUAN

Siêu dự án ngăn triều TPHCM sắp về đích sau 6 năm trễ hẹn

MINH QUÂN |

Siêu dự án ngăn triều tại TPHCM với tổng mức đầu tư gần 10.000 tỉ đồng, sau khi trễ hẹn 6 năm, đã được đặt mục tiêu hoàn thành vào dịp 30.4.2025.

Dự án ngăn triều 10.000 tỉ ở TPHCM tăng lên 14.000 tỉ và tăng bao nhiêu nữa

Lê Thanh Phong |

Theo tính toán của nhà đầu tư, việc tạm dừng và kéo dài quá lâu khiến tổng mức đầu tư dự án ngăn triều 10.000 tỉ đồng đã tăng lên hơn 14.000 tỉ đồng.

3 vướng mắc của dự án ngăn triều 10.000 tỉ đồng ở TPHCM

MINH QUÂN |

TPHCM – Cho nhà đầu tư vay tiền để hoàn thiện dự án, điều chỉnh tổng mức đầu tư, phương thức thanh toán cho nhà đầu tư là 3 vướng mắc của dự án ngăn triều gần 10.000 tỉ đồng ở TPHCM, khiến dự án này hoàn thành hơn 90% khối lượng vẫn chưa thể về đích.

Về đâu chợ nổi miền Tây?

NHÓM PV |

Từng là nơi giao thương sầm uất trên bến dưới thuyền nhưng các chợ nổi ở miền Tây đang đứng trước nguy cơ chìm dần do vắng bóng thương hồ.

Giao nhân sự làm Phó Chủ tịch Ủy ban Giám sát tài chính

PHẠM ĐÔNG |

Ông Vũ Nhữ Thăng được giao tiếp tục giữ chức Phó Chủ tịch Ủy ban Giám sát tài chính Quốc gia.

Kẻ dương tính ma túy gây tai nạn, bé 8 tháng tuổi mồ côi cha

TẠ QUANG - YẾN PHƯƠNG |

Cần Thơ - Vụ đối tượng dương tính ma túy lái xe ô tô tải gây tai nạn liên hoàn vào trưa 26.9 đã để lại hậu quả nặng nề cho gia đình các nạn nhân.

Khủng hoảng tâm lý khi chứng kiến sạt lở ven sông Hồng

HỮU CHÁNH |

Hà Nội - Trong vòng chỉ hơn 1 tháng, hộ gia đình ở Gia Lâm chứng kiến 2 vụ sạt lở cuốn phăng công trình và nhiều diện tích đất thổ cư.

Hình ảnh Việt Nam tỏa sáng tại kinh đô điện ảnh Hollywood

Chí Long |

Chương trình xúc tiến du lịch - điện ảnh Việt Nam tại Mỹ với chủ đề “Việt Nam - Điểm đến mới của Điện ảnh thế giới” mở ra nhiều cơ hội hợp tác với các nhà làm phim Hollywood.

The super project to prevent tides in Ho Chi Minh City is about to reach the finish line after 6 years of delay.

MINH QUÂN |

The super tidal dam project in Ho Chi Minh City with a total investment of nearly 10,000 billion VND, after being delayed for 6 years, has been targeted for completion on April 30, 2025.

Dự án ngăn triều 10.000 tỉ ở TPHCM tăng lên 14.000 tỉ và tăng bao nhiêu nữa

Lê Thanh Phong |

Theo tính toán của nhà đầu tư, việc tạm dừng và kéo dài quá lâu khiến tổng mức đầu tư dự án ngăn triều 10.000 tỉ đồng đã tăng lên hơn 14.000 tỉ đồng.

3 vướng mắc của dự án ngăn triều 10.000 tỉ đồng ở TPHCM

MINH QUÂN |

TPHCM – Cho nhà đầu tư vay tiền để hoàn thiện dự án, điều chỉnh tổng mức đầu tư, phương thức thanh toán cho nhà đầu tư là 3 vướng mắc của dự án ngăn triều gần 10.000 tỉ đồng ở TPHCM, khiến dự án này hoàn thành hơn 90% khối lượng vẫn chưa thể về đích.