On April 3, contractors are speeding up the construction progress of construction package No. 3 of the Ring Road 3 project, the section passing through the old Binh Duong province.
Notably, this construction package has an important intersection with National Highway 13. This section is built with an overpass and below is an access road connecting to National Highway 13.
The overpass project is nearly 1km long from the intersection with Nguyen Thi Minh Khai street running along the One World real estate project and across National Highway 13.
According to records, after 2 years of construction, the overpass with 318 bored piles, 40 abutments, body piers and overpass girders has been installed. At the beginning of 2026, the contractor poured concrete and asphalted the bridge deck.

Currently, the asphalt paving has been completed, and the contractor is continuing construction to complete the remaining items. It is expected that this bridge can be completed in April 2026, this will be the first item in construction package No. 3 to be completed.
In addition, the contractor is focusing machinery on constructing access roads from National Highway 13 to Ring Road 3 HCMC and vice versa. Access roads are starting to build the roadbed. Road construction is expected to be completed in the second quarter of 2026.
Meanwhile, at this location, National Highway 13 is also under construction for a project to upgrade and expand from 6 to 8 lanes. Units are installing drainage culverts, relocating power grids, and leveling the roadbed. Both projects are accelerating progress to jointly complete this intersection.







It is known that the Ring Road 3 of Ho Chi Minh City passing through the Binh Duong area was previously about 26.6 km long with a total investment of 19,280 billion VND. There are 4 construction packages under construction with a total length of 11.6 km, construction package No. 3 is nearly 9 km long, of which nearly 1km is an overpass.
According to the Binh Duong Provincial Traffic Works Project Management Board, construction package No. 3 was started in February 2024, the construction time according to the contract is 960 days. It is expected that the overpass and road section will be completed in September 2026.