Ho Chi Minh City's longest canal renovation project at risk of delay in completion

MINH QUÂN |

Ho Chi Minh City - The project to renovate the Tham Luong - Ben Cat - Nuoc Len canal is at risk of being delayed for completion at the end of 2026 due to lack of materials, site clearance problems, and contractor delays.

On March 26, the Ho Chi Minh City Urban Infrastructure Construction Investment Project Management Board (the investor) said that although the goal is to complete the entire project by the end of 2026, the actual progress is currently slower than planned.

The project to renovate the Tham Luong - Ben Cat - Nuoc Len canal was started on February 23, 2023. To date, the accepted construction volume has reached about 67%.

In which, the embankment item, drainage system and connection discharge gates are completed 98%. However, the traffic road and technical infrastructure only reached about 57%.

Notably, all 10 construction packages (from XL-01 to XL-10) are being delayed.

Hiện trạng kênh Tham Lương - Bến Cát sau hơn 3 năm cải tạo.  Ảnh: Anh Tú
Current status of Tham Luong - Ben Cat canal after more than 3 years of renovation. Photo: Anh Tu

According to the investor, the reason for the slow progress comes from both objective and subjective factors.

Objectively, compensation and site clearance work still has 10 cases that have not been handed over, and there is even a situation where people obstruct construction, making some sections unable to be deployed.

In addition, the failure to approve the landfill locations has caused the process of digging the roadbed and dredging the canal bed to be stalled due to the lack of a gathering place.

The greater difficulty lies in the source of materials. Construction sand and stone continue to be scarce, and rising prices disrupt construction plans.

In particular, the source of asphalt concrete - an important material for transportation items - is seriously lacking. The total demand of the project is about 180,850 tons, but currently only about 30% is met.

From a subjective perspective, some contractors are assessed as not being proactive in organizing construction, lacking coordination in the joint venture. The lack of preparation of materials, labor, and equipment in the context of scarcity further makes progress passive.

Dự án kênh Tham Lương - Bến Cát - rạch Nước Lên thiếu vật liệu làm đường hai bên.  Ảnh: Anh Tú
Tham Luong - Ben Cat - Nuoc Len canal project lacks materials for roads on both sides. Photo: Anh Tu

Faced with the risk of delays, the Ho Chi Minh City Urban Infrastructure Board said it is implementing a series of solutions to "untie the knot".

First of all, focus on definitively handling land issues. Leaders of the Ho Chi Minh City People's Committee and the Department of Agriculture and Environment have directed the review and urging of relevant localities.

At the same time, early approval of excess soil dumps is considered a prerequisite for clearing construction, especially for excavation and dredging of canals.

Regarding materials, the investor proposed to support the designation of a quarry to serve the project, and at the same time create conditions to import sand from Cambodia to ensure supply.

TPHCM đặt mục tiêu hoàn thành kênh Tham Lương - Bến Cát - rạch Nước Lên cuối năm 2026.  Ảnh: Minh Quân
Ho Chi Minh City aims to complete the Tham Luong - Ben Cat - Nuoc Len canal by the end of 2026. Photo: Minh Quan

In the construction organization stage, the Board is tightening the management of contractors. Many measures have been applied such as strengthening construction site inspections, making detailed records of each location behind schedule, and closely monitoring the capacity to mobilize human resources, machinery and materials.

Contractors who are behind schedule are continuously reminded, warned and directly convened for meetings. If there is no improvement, they will be penalized according to the contract, even transferring the volume to another unit with better capacity in the same consortium.

The project to improve the environment and build infrastructure along the Tham Luong - Ben Cat - Rach Nuoc Len canal was started in February 2023, with a total initial investment of 8,200 billion VND, after adjusting to more than 9,000 billion VND.

The canal is nearly 32 km long, built with concrete embankments on both banks, dredging the canal bed, building a road along the canal 8 - 12 m wide, installing drainage systems, lighting, green trees; building 19 drainage culverts, 12 wharves and 3 connecting bridges.

According to the initial plan, the project was expected to be completed on April 30, 2025. However, the project was delayed and the implementation time was adjusted to 2026.

MINH QUÂN
RELATED NEWS

The most polluted canal renovation in Ho Chi Minh City is facing 1,265 households who have not yet handed over land

|

Ho Chi Minh City - The Xuyen Tam canal renovation project is currently facing site clearance issues for 1,265 households. The Chairman of the Ho Chi Minh City People's Committee requested the handover of 100% of the site in June 2026.

All 10 bidding packages for the longest canal renovation project in Ho Chi Minh City are behind schedule

|

Ho Chi Minh City - 10 main construction packages under the Tham Luong - Ben Cat - Nuoc Len canal renovation project are all behind schedule compared to the signed contract.

The longest canal renovation project in Ho Chi Minh City is deserted of workers, machinery is lying idle

|

Ho Chi Minh City - The construction site of the Tham Luong - Ben Cat - Nuoc Len canal renovation project, the longest canal in Ho Chi Minh City, is deserted of workers and machinery is lying idle.

Video of Vietnam - Bangladesh team goals (3-0)

|

Vietnam team wins 3-0 against Bangladesh. Watch the match live and exclusively on FPT Play, at: http://fptplay. vn.

Mr. Nguyen The Phuoc elected Deputy Secretary of Lao Cai Provincial Party Committee

|

Lao Cai - Mr. Nguyen The Phuoc - Standing Vice Chairman of the Provincial People's Committee was elected to hold the position of Deputy Secretary of the Provincial Party Committee.

2 Senior Colonels, 1 Lieutenant Colonel of the Army receive new assignments

|

2 Senior Lieutenant Colonels, 1 Lieutenant Colonel have just been assigned the task of Deputy Attaché of National Defense, in charge of the Border Guard field.

Ministry of Education and Training awards certificates of merit to students who rushed into a fire to save people

|

Nguyen Le Tu - a student at Hanoi University of Science and Technology, who rushed into the fire that occurred in Linh Nam (Hanoi) - to save people was awarded a certificate of merit by the Ministry of Education and Training.

The most polluted canal renovation in Ho Chi Minh City is facing 1,265 households who have not yet handed over land

MINH QUÂN |

Ho Chi Minh City - The Xuyen Tam canal renovation project is currently facing site clearance issues for 1,265 households. The Chairman of the Ho Chi Minh City People's Committee requested the handover of 100% of the site in June 2026.

All 10 bidding packages for the longest canal renovation project in Ho Chi Minh City are behind schedule

MINH QUÂN |

Ho Chi Minh City - 10 main construction packages under the Tham Luong - Ben Cat - Nuoc Len canal renovation project are all behind schedule compared to the signed contract.

The longest canal renovation project in Ho Chi Minh City is deserted of workers, machinery is lying idle

MINH QUÂN |

Ho Chi Minh City - The construction site of the Tham Luong - Ben Cat - Nuoc Len canal renovation project, the longest canal in Ho Chi Minh City, is deserted of workers and machinery is lying idle.