On the Ring Road 4 construction site at the end of the year

NHÓM PV |

Hanoi - Contractors at the Ring Road 4 project site are determined to complete the parallel road by 2025.

According to Lao Dong newspaper reporters at the construction site of the Ring Road 4 parallel road of the Capital Region through Dan Phuong district (Hanoi) at the end of December, the route has revealed its shape when viewed from above.

The closer to the end of the year, the more urgent the construction atmosphere is. The construction site has almost no time to stop the sound of machines.

Duong song hanh Vanh dai 4 doan qua huyen Dan Phuong da lo dien. Anh: Nhom PV
The parallel road of Ring Road 4 through Dan Phuong district has been revealed. Photo: Reporter Group
Nhieu doan da duoc tham lop betong nhua. Anh: Nhom PV
Many sections have been paved with asphalt concrete. Photo: PV Group

At package 9 - construction of the Ring Road 4 parallel road section through Dan Phuong and Hoai Duc (21km) constructed by contractor Vinaconex, about 100 locomotives, equipment and 200 officers, engineers and workers were mobilized to work day and night, "3 shifts, 4 teams" at the project site.

Mr. Hoang Trong Hai - Commander of construction team No. 1 - said that up to now, package No. 9 implemented by Vinaconex has reached over 43% of the contract value.

The contractor has now paved about 8km of concrete along the entire route, and the remaining sections are being paved with crushed stone. Some bridge sections across the canal are also being implemented by the contractor.

Nhau thau dang trien khai hang muc cap phoi da dam. Anh: Nhom PV
The contractor is implementing the crushed stone grading project. Photo: PV Group
Nhieu may moc, cong nhan duoc huy dong day nhanh tien do du an. Anh: Huu Chanh
Many machines and workers were mobilized to speed up the project's progress. Photo: PV Group

According to Mr. Hai, for key projects such as Ring Road 4, the closer to the end of the year, the greater the workload, so staff also have to work overtime more.

"Although it is difficult, the contractor, workers and engineers are all united and determined to speed up the project's progress," said Mr. Hai.

During the 2025 New Year, construction activities at the site will continue as usual. As for the Lunar New Year, although there is no specific plan, everyone is ready to stay at the site and work through the Tet holiday to complete the parallel road project in 2025.

Mot so doan da duoc tham nhua mat duong. Anh: Nhom PV
People travel on the parallel road through Ha Mo commune (Dan Phuong district). Photo: Reporter team
May moc duoc huy dong den cong truong de thi cong hang muc tham betong nhua. Anh: Nhom PV
Machinery gathered at the construction site to construct the asphalt concrete pavement. Photo: PV Group

At package No. 8 - construction of the parallel road of Ring Road 4 through Soc Son and Me Linh districts (13km), the representative of the contractor Truong Son Corporation said that up to this point, the package has completed about 64% of the construction volume, ensuring progress compared to the plan.

"With the sections that have cleared land, the joint venture contractor is committed to completing the construction of the Ring Road 4 parallel road project through Me Linh and Soc Son in June 2025," the contractor representative affirmed.

Cau vuot duong sat thuoc goi thau so 8 dang duoc xay dung. Anh: Nhom PV
The railway overpass under package 8 is under construction. Photo: PV Group

Similarly, package 10 through Ha Dong district and Thanh Oai district, package 11 through Thuong Tin are also being implemented by contractors in many construction phases simultaneously, ensuring the project's progress.

Regarding the site clearance work of the Ring Road 4 project through Hanoi, up to now, the Hanoi Traffic Construction Project Management Board has received 776.82/786.2 hectares of site, equivalent to 48.35km/52.73km, reaching 91.7%.

Currently, the project still has 8.3% of the land area, equivalent to more than 4.4km in length, that has not been cleared. There are still many interruptions and delays along the entire construction route.

Representatives of some districts where Ring Road 4 runs through said that most of the agricultural land has been cleared. The project site that has not been cleared yet is related to residential land, old graves and the relocation of high-voltage power line infrastructure.

Mot so nha dan xa Dai Mo (huyen Dan Phuong) chua duoc giai toa de thi cong du an. Anh: Nhom PV
Some houses in Ha Mo commune (Dan Phuong district) have not been cleared for project construction. Photo: PV Group

Hanoi strives to complete site clearance for the project before the Lunar New Year 2025.

After about 17 months since the commencement of the Ring Road 4 project, 4 construction packages in Hanoi have been simultaneously deployed on a route length of 48.35km with 32 construction points (23 road points, 9 bridge points).

The output to date is about 1,810/4,205 billion VND (reaching 43.04% of the contract value and 100% of the 2024 plan). Hanoi strives to complete the parallel road project in the fourth quarter of 2025.

NHÓM PV
TIN LIÊN QUAN

The first locality to hand over full land for Hanoi Ring Road 4 project

|

Of the 7 districts in Hanoi that Ring Road 4 passes through, only one locality has handed over enough land for the project.

Ring Road 4 - Capital Region faces the risk of "road waiting for bridge"

|

The parallel road of Ring Road 4 is being accelerated and is expected to be completed in 2025, but to date, the three bridges including Me So, Hong Ha and Hoai Thuong have not yet started construction, most likely "the road is finished but the bridge is not seen".

27-span flyover on Hanoi's Ring Road 4 to be completed in 2025

|

Hanoi - It is expected that by the second quarter of 2025, the North-South railway overpass, nearly 590m long, with 27 spans (part of the Ring Road 4 parallel road project through Me Linh) will be completed.

The moment Vietnam team lifted the ASEAN Cup trophy

|

The moment the Vietnamese team celebrated emotionally when winning the ASEAN Cup 2024 championship on the Thai field.

Hanoi gives big reward to Vietnam Team

|

On the evening of January 5, Hanoi City decided to donate 2 billion VND to the Vietnam National Team, congratulating the team on winning the 2024 ASEAN Cup championship.

Man United ranked 13th in Premier League after draw with Liverpool

|

Liverpool and Man United drew 2-2 in round 20 of the Premier League.

Nguyen Ninh green rice cake production site has animal manure

|

On January 5, the Hanoi Department of Health announced a series of food safety violations at the Nguyen Ninh green rice cake production facility that had just been suspended.

Watch Tuan Hai's opening goal for Vietnam team

|

Pham Tuan Hai scored the opening goal for Vietnam in the second leg of the 2024 ASEAN Cup final against Thailand. Watch the 2024 ASEAN Championship Mitsubishi Electric Cup live and in full on FPT Play, at: http://fptplay.vn.

The first locality to hand over full land for Hanoi Ring Road 4 project

HỮU CHÁNH |

Of the 7 districts in Hanoi that Ring Road 4 passes through, only one locality has handed over enough land for the project.

Ring Road 4 - Capital Region faces the risk of "road waiting for bridge"

HỮU CHÁNH - KHÁNH AN |

The parallel road of Ring Road 4 is being accelerated and is expected to be completed in 2025, but to date, the three bridges including Me So, Hong Ha and Hoai Thuong have not yet started construction, most likely "the road is finished but the bridge is not seen".

27-span flyover on Hanoi's Ring Road 4 to be completed in 2025

NHÓM PV |

Hanoi - It is expected that by the second quarter of 2025, the North-South railway overpass, nearly 590m long, with 27 spans (part of the Ring Road 4 parallel road project through Me Linh) will be completed.