On February 25, according to information from the Dong Nai Provincial Construction Investment Project Management Board, contractors at component project 1, Bien Hoa - Vung Tau expressway and component project 3, Ring Road 3 HCMC simultaneously resumed construction of packages after the Binh Ngo Tet holiday 2026.

Component project 1, Bien Hoa - Vung Tau expressway, with a length of 16km, has now reached about 75% of the construction volume. At this project during Tet, a contractor mobilized dozens of machines, equipment and manpower to simultaneously deploy 3 construction fronts throughout Tet to accelerate progress beyond the plan, maintain working pace, create positive momentum to help the construction site immediately catch up and return to normal construction immediately after the holiday ends, avoiding sluggishness.

As for component project 3, Ho Chi Minh City Ring Road 3, with a total length of more than 11km, the completed construction volume reached about 67%.
According to the plan, these projects will complete construction and put into synchronous operation in May 2026.
When completed and put into operation, the projects will contribute to completing the transportation network of the Southern region, creating more favorable connection conditions between Dong Nai and Ho Chi Minh City, and also play an important role in effectively supporting the operation of Long Thanh airport in the coming time.