Hanoi Ring Road 2.5 is entangled with site clearance, risk of delayed progress

Minh Hạnh |

Hanoi - Ring Road 2.5 project is facing site clearance obstacles, facing the risk of not being completed in time in 2026.

Although it is in the peak construction phase, the Ring Road 2.5 project section passing through Cau Giay ward and Yen Hoa ward, Hanoi City is still facing site clearance problems, causing the goal of completion in 2026 to face the risk of delay.

The Ring Road 2.5 project is a key project, expected to reduce traffic pressure for the western area of the Capital. After the groundbreaking ceremony on March 20, 2026, contractors simultaneously mobilized machinery and manpower to implement important items before the rainy and storm season.

Thi công lắp đặt hệ thống cống. Ảnh: Hải Lê
Construction and installation of the sewer system. Photo: Hai Le

However, in the section passing through the new urban area of Dich Vong - Duong Dinh Nghe (0.71km long), construction activities are currently only concentrated in locations with cleared ground. According to research, the construction unit has only excavated the foundation of the drainage system along about 200m and installed protective corrugated iron fences.

Notably, due to problems in site clearance, construction is falling into a "slow-moving" situation. Many sections of the route are interrupted by temporary houses and corrugated iron houses that have not been relocated, making it impossible for machinery to access to dig roads or install drainage systems.

Công nhân đưa đế bê tông vào vị trí định sẵn trước khi đặt ống cống lên trên. Ảnh: Hải Lê
Workers put the concrete base into the pre-arranged position before placing the sewer pipe on top. Photo: Hai Le

Talking to reporters, a representative of Song Hong Joint Stock Company (the construction contractor) said that although the route section is only 710m long, so far the unit has only been handed over about 400m. The remaining 300m is still entangled in the cemetery area and people's houses have not been relocated.

Talking to a reporter of Lao Dong Newspaper, Mr. Vu Trung Kien - Head of the Economic and Urban Infrastructure Department of Cau Giay ward said that the area managed by the ward has basically completed site clearance and is being handed over to the construction unit. "The ward focuses on deploying work, regardless of Saturday or Sunday. Currently, the work is being carried out in a "rolling" manner, both site clearance and handover for construction," Mr. Kien said.

Reality shows that at locations adjacent to Duong Dinh Nghe street, the ground has not been cleared, causing the project to be stalled. Meanwhile, in the opposite direction of Cau Giay street, although the ground is basically completed, the overall infrastructure connection still faces difficulties due to lack of synchronization.

If the site is handed over in early May 2026, we will mobilize maximum manpower to compensate for the progress. Conversely, if the handover continues to be delayed, the goal of completing the project of more than 8,400 billion VND in 2026 will be very difficult to achieve," said the contractor representative.

Minh Hạnh
RELATED NEWS

The appearance of the parallel road of Ring Road 4 Hanoi

|

Hanoi - Ring Road 4 parallel road has basically completed the main works of bridges, culverts and other items, the output value reached about 85%.

Urgently remove obstacles at Ring Road 2.5 project with a capital of over 1,300 billion VND

|

Hanoi - Relevant units are coordinating site clearance for investors to complete the Ring Road 2.5 project, Dam Hong - National Highway 1A section.

Ring Road 2.5, Dich Vong - Duong Dinh Nghe section is expected to open to traffic in September

|

Hanoi - Ring Road 2.5, Dich Vong - Duong Dinh Nghe section is expected to be technically opened to traffic in early September if the site is handed over on schedule.

Conflict when converting electricity contracts causes company in Tay Ninh to temporarily stop production

|

The power outage at CPF Potash Fertilizer Production Co., Ltd. (Tay Ninh province) caused production to be disrupted, and many workers had to temporarily stop working.

Discovery of a 2-year-old girl dead in a car

|

Nghe An - A girl over 2 years old was left in a car for many hours leading to death, relatives were shocked when they discovered the incident.

Registering for 10th grade in Ho Chi Minh City, choosing the wrong aspiration, high score still fails

|

From April 22, 9th grade students in Ho Chi Minh City begin registering for 10th grade aspirations. The selection needs to have a clear basis, avoiding the situation of high scores but still failing.

Stop climbing activities in Lao Cai due to extremely dangerous forest fire risk

|

Lao Cai - Bat Xat Nature Reserve Management Board warns that forest fires are extremely dangerous, absolutely prohibiting entry into the forest, mountain climbing, and sightseeing.

Overcoming the crude water pipe burst incident, re-supplying water to 38,000 households in Dak Lak

|

Dak Lak - After the DN600 raw water pipeline burst incident, functional agencies have repaired and restored clean water to tens of thousands of households.

The appearance of the parallel road of Ring Road 4 Hanoi

SÓNG HỮU |

Hanoi - Ring Road 4 parallel road has basically completed the main works of bridges, culverts and other items, the output value reached about 85%.

Urgently remove obstacles at Ring Road 2.5 project with a capital of over 1,300 billion VND

SÓNG HỮU |

Hanoi - Relevant units are coordinating site clearance for investors to complete the Ring Road 2.5 project, Dam Hong - National Highway 1A section.

Ring Road 2.5, Dich Vong - Duong Dinh Nghe section is expected to open to traffic in September

Hữu Vũ |

Hanoi - Ring Road 2.5, Dich Vong - Duong Dinh Nghe section is expected to be technically opened to traffic in early September if the site is handed over on schedule.