On December 10, Vinh Phuc Provincial People's Committee informed that Vice Chairman of the Provincial People's Committee Nguyen Khac Hieu had just inspected the construction and upgrade project of Binh Xuyen District Medical Center and Tran Phu High School Project.
According to the Provincial Construction Investment Management Board, the Tran Phu High School project has a total investment of more than 323 billion VND, with a scale of 39 classrooms, meeting the learning needs of 1,600 students.
The project started in November 2023 and the planned implementation period is 580 days. The project is built on the area of the old Tran Phu High School, in Lien Bao Ward, Vinh Yen City.
Up to now, the total completed volume has reached more than 150 billion VND, equivalent to more than 84.6% of the contract value.
According to the contractor's commitment, the project will be inaugurated and put into use before the start of the new school year 2025-2026.
For the Binh Xuyen District Medical Center Project, the project has a total investment of more than 260 billion VND, and construction started in May 2023.
Up to now, many hospital projects have been basically completed.
To date, the project has achieved approximately 114 billion VND. The project is expected to be inaugurated in May 2025.
After listening to the units' reports on the progress and some difficulties and problems in the project's construction process, Vice Chairman of Vinh Phuc Provincial People's Committee Nguyen Khac Hieu requested that relevant departments, branches and localities support the investor and construction units to perform well the tasks during the construction process.
Along with that, the project investor and construction units focused on removing difficulties during the construction process; taking advantage of favorable weather, increasing construction manpower, ensuring safety, progress and quality.