Overcoming the construction ceremony of the 282 billion VND bridge in Lao Cai border commune

Đinh Đại |

Lao Cai - These days, the construction site of the road bridge across the Red River in Bat Xat Commune connecting to China is still bustling with construction.

During the National Day holidays on September 2, present at Provincial Road 156 under the project to build a border bridge across the Red River in Bat Xat Commune, Lao Cai Province, Lao Dong Newspaper reporters recorded the bustling activities of workers and a series of machines at the construction site.

Here, workers are constructing items such as foundations and bridge piers, and transporting materials for the construction process.

Doi ngu ky su, cong nhan xay dung miet mai thi cong cau bien gioi tai Lao Cai dip Quoc khanh. Anh: Dinh Dai
A team of engineers and construction workers are working hard to construct the border bridge in Lao Cai on the occasion of National Day. Photo: Dinh Dai

Through research, the investment project to build a border bridge over the Red River in Ban Vuoc commune and connecting infrastructure includes 3 components, implemented in the period of 2021-2025.

In which, component 1: Construction of a border bridge across the Red River; upgrading Provincial Road 156 (Kim Thanh - Ngoi Phat) from the intersection with BV32 and BV28 roads to the intersection with BV190 road (3km long); upgrading and renovating the Noi Bai - Lao Cai IC 18 expressway intersection.

Cong truong cau bien gioi 282 ti dong tai xa Bat Xat, tinh Lao Cai. Anh: Dinh Dai
The 282 billion VND border bridge construction site in Bat Xat commune, Lao Cai province. Photo: Dinh Dai

Component 2 includes: Upgrading Provincial Road 156 (Kim Thanh - Ngoi Phat) from Quang Kim Bridge to the intersection with BV32 and BV28 roads (8km long) and leveling the ground on both sides of the road with a depth of 50m; component 3: Upgrading and renovating IC19 intersection.

The total investment is 1,490 billion VND, the Central budget supports 950 billion VND, the local budget matches 540 billion VND.

The construction units are Minh Duc General Construction Company Limited, Cuong Thinh Thi Construction Investment and Development Joint Stock Company and Dong Hung Development Investment Joint Stock Company.

Cac thiet bi hang nang van chuyen nguyen vat lieu va cau kien thi cong cau. Anh: Dinh Dai
Heavy equipment for transporting raw materials and components for bridge construction. Photo: Dinh Dai

For the border bridge project across the Red River connecting Bat Xat (Vietnam) - Ba Sai (China), the total investment capital is about 282 billion VND.

The joint venture of Trung Chinh Construction and Trading Company Limited and Inland Waterway Management and Maintenance Joint Stock Company is the construction unit, implemented within 18 months.

In Vietnam, the bridge construction location is at Ban Vuoc border gate, Bat Xat district, about 700 m downstream of marker 97 on the Red River.

The project will have the following scale: Extradosed main bridge over the Red River (low- tower cable-stayed bridge); girder made of prestressed reinforced concrete according to the cantilever casting method combined with fan-less cable-stayed cable-stayed, tower pillars are 20 m high from the bridge surface.

The width of the bridge is 35.3 m, of which the Vietnamese side will build half of the main bridge (115 m long).

Mot so mong tru da thi cong xong. Anh: Dinh Dai
Some pillar foundations have been completed. Photo: Dinh Dai

The bridge and approach road on the Vietnam side are 40 m long and are made of reinforced concrete box beams for force cast on fixed scaffolding. The road at the head of the bridge is 232.5 m long, the roadbed is 35 m wide, the road surface is 25 m wide.

"Taking advantage of the sunny weather, we mobilized excavators and constructed the bridge items through the ceremony so that the project could be completed on time," said the representative of the construction unit.

The contractor is speeding up construction activities to ensure the project will be completed in September 2026, after 18 months of construction.

Cong trinh du kien hoan thanh vao thang 9.2026. Anh: Dinh Dai
Workers work through the ceremony to complete it in September 2026. Photo: Dinh Dai

Mr. Pham Minh Hai - Deputy Director of the Lao Cai Province Traffic Construction Investment Project Management Board - also said: "With the goal of putting the bridge into use soon, promoting economic development and trade of goods, during the National Day holiday on September 2, the construction site on the Vietnamese side still maintains about 50 workers and many construction machinery and equipment.

According to Mr. Pham Minh Hai, the contractor has basically completed 5/5 T9 and 12/12 T8 bored piles. The implementation value to date is 39/280.25 billion VND, reaching 14%.

Đinh Đại
RELATED NEWS

Starting construction of a hundred-billion-dong bridge in Lao Cai border commune

|

Lao Cai - On the morning of August 19, the groundbreaking ceremony for the construction of Ngoi Phat bridge took place in Trinh Tuong commune.

The road connecting the hundred-billion-dong bridge in Lao Cai is cracked even though it has not been handed over yet

|

Although not yet handed over, the road connecting the bridge worth hundreds of billions of VND in Lao Cai has seen many large cracks, causing people to worry about the quality of the project.

Preparing to start construction of a hundred-billion-dong bridge connecting Lao Cai - China

|

Lao Cai - The road bridge across the Red River in the border district of Bat Xat connecting with China will start construction on Provincial Road 156.

Details of the National Day fireworks display locations on September 2 in Hanoi and other provinces and cities

|

By September 1, many localities had announced schedules and fireworks display locations to celebrate the 80th anniversary of National Day on September 2.

Germany suddenly reverses the idea of sending troops to Ukraine

|

Germany has just officially postponed the plan to consider deploying troops to Ukraine in case a ceasefire is achieved.

The streets of Ho Chi Minh City are brightly decorated with flags and flowers, celebrating the 80th anniversary of National Day on September 2

|

HCMC - These days, the streets of the city named after Uncle Ho are filled with the colorful flags and flowers of the people celebrating National Day on September 2.

Many experiences in watching the A80 parade successfully

|

The commemoration, parade, and parade to celebrate the 80th anniversary of the August Revolution and National Day on September 2 are solemn events. Tourists should prepare carefully.

Hanoi wears red flag with yellow star, brilliantly celebrating the National Day

|

Hanoi - These days, the capital is brilliant with the red flag with yellow star, wearing a heroic and atmospheric appearance to welcome the September 2 holiday.

Starting construction of a hundred-billion-dong bridge in Lao Cai border commune

Đinh Đại |

Lao Cai - On the morning of August 19, the groundbreaking ceremony for the construction of Ngoi Phat bridge took place in Trinh Tuong commune.

The road connecting the hundred-billion-dong bridge in Lao Cai is cracked even though it has not been handed over yet

Nhóm PV |

Although not yet handed over, the road connecting the bridge worth hundreds of billions of VND in Lao Cai has seen many large cracks, causing people to worry about the quality of the project.

Preparing to start construction of a hundred-billion-dong bridge connecting Lao Cai - China

Đinh Đại |

Lao Cai - The road bridge across the Red River in the border district of Bat Xat connecting with China will start construction on Provincial Road 156.