Restarting the 1,300 billion VND project after Lao Dong's reflection

NHÓM PV |

Dien Bien - After Lao Dong Newspaper published an article reflecting "Suffering because the 1,300 billion VND traffic project is behind schedule", contractors mobilized maximum machinery and human resources for construction.

On September 12, Lao Dong Newspaper published an article reflecting on the 1,300 billion VND traffic project's slow progress, affecting the lives of many people. The next day (September 13), Mr. Le Thanh Do - Chairman of Dien Bien Provincial People's Committee inspected the site and gave drastic instructions.

Ong Le Thanh Do - Chu tich UBND tinh Dien Bien (hang dau, thu 3 tu trai sang) di kiem tra thuc dia sau phan anh cua Bao Lao Dong.
Mr. Le Thanh Do - Chairman of Dien Bien Provincial People's Committee (front row, 3rd from left) went to inspect the field after Lao Dong Newspaper's reflection.

During the inspection, Mr. Le Thanh Do requested Dien Bien Phu City and Dien Bien District (localities with land belonging to the project) to focus on inventory work and promptly complete the handover of the site to the contractors.

At the same time, allow the implementation of resettlement land funds of other projects to arrange resettlement for households in need and eligible for resettlement; Implement support policies and rent temporary accommodation for people.

Cac nha thau tiep tuc thi cong tuyen chinh cua du an tu Quoc lo 12 - Quoc lo 279 co chieu dai 19,56km, doan qua dia phan xa Thanh Chan, huyen Dien Bien.
Contractors continue to construct the main route of the project from National Highway 12 - National Highway 279 with a length of 19.56km, passing through Thanh Chan commune, Dien Bien district.

The project completion time on December 31, 2024 is gradually shortening, while the remaining workload is very large. The Chairman of the People's Committee of Dien Bien province requested contractors to concentrate human resources, work in 3 shifts, and work day and night to speed up the progress.

Mr. Le Thanh Do also requested the investor (Dien Bien Province Traffic Project Management Board) to strengthen supervision to ensure the quality of construction works. "In case the contractors do not meet the requirements and construction progress, the investor needs to handle according to authority, invite other investors to ensure progress" - Mr. Do emphasized.

Cac phuong tien may moc da duoc nha thau tap ket tai hau het cac goi thau cua du an ngay tu chieu 13.9.
Machinery and equipment were gathered by contractors at most of the project's packages since the afternoon of September 13.

On September 14, according to Lao Dong Newspaper's reporter, on the 29.57km long section of the road outside the urban area, contractors mobilized vehicles and human resources to urgently "restart" the project.

Previously, as Lao Dong Newspaper reported, the traffic project connecting key economic areas in the dynamic economic zone along National Highway 279 and National Highway 12 in Dien Bien province (dynamic road) with a total investment of 1,300 billion VND in Dien Bien was behind schedule, affecting the lives of many people.

Chu tich UBND tinh Dien Bien yeu cau cac nha thau phai lam 3 ca de day nhanh tien do du an.
The Chairman of Dien Bien Provincial People's Committee requested contractors to work 3 shifts to speed up the project's progress.

The reason why most of the construction packages have been suspended for many months is said to be due to continuous rain and lack of clean ground for construction. Therefore, in the past few days, hundreds of households living along the main route of National Highway 12 and National Highway 279, which is 19.56km long, have been affected by flooding and mud.

The investor representative also said that the dynamic road project is currently facing many challenges, especially the issue of site clearance.

Some images recorded by Lao Dong Newspaper reporters on September 13-14:

NHÓM PV
TIN LIÊN QUAN

Khổ vì dự án giao thông 1.300 tỉ chậm tiến độ

NHÓM PV |

Dự án giao thông 1.300 tỉ tại Điện Biên được kỳ vọng sẽ là “cú hích” để phát triển. Tuy nhiên, do dự án chậm tiến độ đã ảnh hưởng tới cuộc sống nhiều người.

Điện Biên cưỡng chế thu hồi gần 500m² đất phi nông nghiệp

QUANG ĐẠT |

Sáng 11.9, TP Điện Biên Phủ, tỉnh Điện Biên đã tiến hành cưỡng chế thu hồi trên 475m2 đất phi nông nghiệp tại đô thị bị lấn chiếm.

Điện Biên đối diện nguy cơ đứt gãy nền đường Quốc lộ 279

NHÓM PV |

Mưa lớn kéo dài nhiều ngày qua đã khiến nhiều đoạn trên tuyến Quốc lộ 279 tại tỉnh Điện Biên bị sụt lún đối diện nguy cơ đứt gãy nền đường.

Tuyển Indonesia thua trận đầu tiên tại vòng loại 3 World Cup 2026

NHÓM PV |

Tối 15.10, đội tuyển Indonesia nhận thất bại 1-2 trên sân tuyển Trung Quốc tại vòng loại thứ 3 World Cup 2026.

Ra mắt Tủ sách điện tử Tổng Bí thư Nguyễn Phú Trọng

Vương Trần |

Tủ sách điện tử Tổng Bí thư Nguyễn Phú Trọng là cơ sở dữ liệu quý, phục vụ nghiên cứu, học tập và vận dụng trong sự nghiệp xây dựng và bảo vệ Tổ quốc.

Phá đường dây cờ bạc nghìn tỉ qua mạng, tạm giam 12 người

Thành Nhân |

Bến Tre - Lực lượng Công an vừa triệt xóa đường dây cờ bạc trên không gian mạng với tổng số tiền giao dịch hơn 1.800 tỉ đồng.

Nổ nồi hấp tinh dầu, 1 bé gái bị thương, 5 căn nhà ảnh hưởng

LÝ LINH |

TPHCM - Ngày 15.10, Công an huyện Bình Chánh đang điều tra vụ nổ nồi hấp tại một cơ sở sản xuất tinh dầu trên địa bàn xã Vĩnh Lộc A khiến một bé gái bị thương.

Nguyên chủ tịch xã ở Thái Bình bị tố lạm quyền để trục lợi

TRUNG DU |

Thái Bình - Nguyên Chủ tịch UBND xã Quỳnh Hải, huyện Quỳnh Phụ bị tố lợi dụng chức vụ quyền hạn để tư lợi, trục lợi cho bản thân, gia đình.

Khổ vì dự án giao thông 1.300 tỉ chậm tiến độ

NHÓM PV |

Dự án giao thông 1.300 tỉ tại Điện Biên được kỳ vọng sẽ là “cú hích” để phát triển. Tuy nhiên, do dự án chậm tiến độ đã ảnh hưởng tới cuộc sống nhiều người.

Điện Biên cưỡng chế thu hồi gần 500m² đất phi nông nghiệp

QUANG ĐẠT |

Sáng 11.9, TP Điện Biên Phủ, tỉnh Điện Biên đã tiến hành cưỡng chế thu hồi trên 475m2 đất phi nông nghiệp tại đô thị bị lấn chiếm.

Điện Biên đối diện nguy cơ đứt gãy nền đường Quốc lộ 279

NHÓM PV |

Mưa lớn kéo dài nhiều ngày qua đã khiến nhiều đoạn trên tuyến Quốc lộ 279 tại tỉnh Điện Biên bị sụt lún đối diện nguy cơ đứt gãy nền đường.