3 projects suspended for decades are about to be revived in Ho Chi Minh City

MINH QUÂN |

Ho Chi Minh City is making efforts to restart projects that have been "suspended" for decades, such as Binh Quoi - Thanh Da Urban Area, Phan Dinh Phung Stadium, and Saigon Safari Park.

These are 3 of 10 key projects directly monitored and directed by Chairman of Ho Chi Minh City People's Committee Phan Van Mai to remove difficulties, speed up progress and avoid wasting resources.

Phan Dinh Phung Stadium

Located on a prime land with four frontages on Pasteur, Nguyen Dinh Chieu, Nam Ky Khoi Nghia and Vo Van Tan streets (District 3), the Phan Dinh Phung stadium project was approved under the BT (build-transfer) form in 2008.

Initially, An Tao Company Limited and the Compensation and Clearance Corporation were assigned to carry out the project, but when An Tao withdrew, the project fell into a state of stagnation.

By 2018, the joint venture of Compensation and Clearance Joint Stock Corporation - Phat Dat Real Estate Development Joint Stock Company was appointed as a replacement.

However, many problems, especially related to land funds for payment for BT contracts, have caused the project to continue to be delayed.

Du an nha thi dau Phan Dinh Phung (Quan 3). Anh: Anh Tu
Phan Dinh Phung Stadium project (District 3). Photo: Anh Tu

In April 2024, the Ho Chi Minh City People's Committee decided to stop investing under the BT contract and switch to using the budget.

According to the new design, the project has a total investment of 1,850 billion VND, a campus area of ​​more than 14,400 m² with a construction density of 50%.

The stadium consists of 3 floors above ground and 3.5 basements, with a total floor area of ​​over 59,600 m², meeting the training and competition needs of 13 sports with a capacity of 4,000-5,000 spectators.

The design competition is expected to be held in 2025, with construction starting in 2026 and completion in 2028. Compared to the original plan of more than VND 1,953 billion, the project scale has been significantly reduced to reduce costs.

Binh Quoi - Thanh Da Urban Area

Binh Quoi - Thanh Da urban area (Binh Thanh district) covers 427 hectares, located on a peninsula about 6.5 km from the center of Ho Chi Minh City. It was approved in 1992 but has not been implemented due to lack of capital and difficulties in site clearance.

Currently, there are about 5,000 households with more than 16,600 people living here, suffering from serious infrastructure degradation due to the "suspended" project.

Khu do thi Binh Quoi - Thanh Da chi cach trung tam TPHCM vai km. Anh: Anh Tu
Binh Quoi - Thanh Da urban area is only a few kilometers from the center of Ho Chi Minh City. Photo: Anh Tu

To restart, Ho Chi Minh City has included the project in the list of typical projects to celebrate the 50th anniversary of the Liberation of the South and National Reunification Day (April 30, 1975 - April 30, 2025). The city aims to complete the bidding process to select investors by April 2025.

At the same time, Ho Chi Minh City organized an international competition for planning ideas, requiring at least 200 hectares for green parks and public spaces, creating a living environment in harmony with the Saigon River landscape.

Saigon Safari Park

Located in An Nhon Tay and Phu My Hung communes (Cu Chi district), Saigon Safari Park was planned in 2004 with an area of ​​over 485 hectares and a total investment of 500 million USD.

This was expected to be the largest eco-tourism park in Vietnam, of Southeast Asia scale, with the function of preserving, displaying and breeding rare animals in the world.

Du an Cong vien Sai Gon Safari bi bo hoang. Anh: Minh Quan
Abandoned Saigon Safari Park project. Photo: Minh Quan

To implement the project, in June 2004, the Ho Chi Minh City People's Committee issued a decision to reclaim the land and assigned the investor, Saigon Zoo and Botanical Garden Company Limited (investor) and the Cu Chi District People's Committee to compensate and resettle more than 700 households in 2 communes of Cu Chi District.

The project achieved 96% site clearance in 2007 but has been stalled for many years, leaving land fallow and wasting resources.

In 2021, the People's Committee of Cu Chi district proposed converting the project planning into a high-tech industrial park to attract investment and promote local economic development.

MINH QUÂN
TIN LIÊN QUAN

4 main roads in Thu Thiem remain unfinished after 10 years

|

HCMC - After 10 years of construction, 4 main roads in Thu Thiem New Urban Area (Thu Duc City) are still not completed due to land acquisition problems.

Leaders of Ho Chi Minh City People's Committee divide the work of handling a series of large backlog projects

|

Chairman of the Ho Chi Minh City People's Committee Phan Van Mai and five vice chairmen directly directed the removal of a series of stalled projects, speeding up the completion progress to avoid waste and loss.

44 km of National Highway 1 through Ho Chi Minh City changed to 3 new names

|

44 km of National Highway 1 through Ho Chi Minh City is divided into three sections named Do Muoi, Le Duc Anh, and Le Kha Phieu.

Border guards firmly protect the country's borders

|

HUE - Over 60 years of formation and development, the Thua Thien Hue Border Guard (BDBP) has been absolutely loyal to the Party, the Fatherland and the people.

Tomorrow Thanh Xuan district will forcibly reclaim land for a big project

|

Hanoi - On December 12, Thanh Xuan district will organize the compulsory land recovery of 34 households to build the new urban area project Phung Khoang according to regulations.

Wedding dress street in Ho Chi Minh City is deserted, many premises are empty

|

Many premises on Ho Van Hue Street (Phu Nhuan District) - a large wedding dress street in Ho Chi Minh City - are vacant, some are even being put up for sale because they cannot find tenants.

Ba Ria - Vung Tau will collect 10,734 billion VND from auctioning 23 land plots

|

In 2025, Ba Ria - Vung Tau aims to collect 10,734.3 billion VND from land auctions, including 14 new land plots and revenue from 9 auctioned land plots in 2024.

3,450 Ha Long households donate land to upgrade urban infrastructure

|

Quang Ninh - Urban infrastructure, especially roads in Ha Long, are increasingly spacious thanks in part to the support and land donations of thousands of households.

4 main roads in Thu Thiem remain unfinished after 10 years

MINH QUÂN |

HCMC - After 10 years of construction, 4 main roads in Thu Thiem New Urban Area (Thu Duc City) are still not completed due to land acquisition problems.

Leaders of Ho Chi Minh City People's Committee divide the work of handling a series of large backlog projects

MINH QUÂN |

Chairman of the Ho Chi Minh City People's Committee Phan Van Mai and five vice chairmen directly directed the removal of a series of stalled projects, speeding up the completion progress to avoid waste and loss.

Dự án nhà thi đấu 2.000 tỉ đồng ở TPHCM bỏ hoang, ai đi qua cũng nhức mắt

MINH QUÂN |

TPHCM - Liên quan đến dự án nhà thi đấu Phan Đình Phùng 4 mặt tiền tại trung tâm TPHCM bị bỏ hoang, Chủ tịch UBND TPHCM Phan Văn Mãi cho biết, người dân thành phố đi qua nhìn rất nhức mắt và bản thân ông cũng thấy rất khó chịu.