The Ministry of Construction answers questions about the resettlement project of a railway project

Xuyên Đông |

On the Government Portal, the Ministry of Construction answered citizens' questions about resettlement at a railway project.

Mr. L.D.P said that his Project Management Board was assigned by the Provincial People's Committee to be the investor to organize the implementation of compensation, support and resettlement for the railway construction investment project.

The project has been decided by the National Assembly on the investment policy on February 19, 2025; in which the Provincial People's Committee with the project is assigned to implement the construction of a resettlement area for the project based on the preliminary design documents in the pre-feasibility study report decided by the National Assembly on the investment policy.

During the implementation process, Mr. Phuong's unit encountered some problems.

First, regarding the authority to appraise and approve the cost estimate for the master plan (for resettlement areas with a land use scale of less than 5 hectares).

Second, regarding the selection of fire prevention and fighting design solutions for resettlement areas (due to resettlement areas in many different areas and of different scale.

Mr. P suggested that competent authorities provide specific guidance on the scale and method of determining the resettlement area to apply fire prevention and fighting design solutions according to the provisions of the Law on Fire Prevention, Fire Fighting and Rescue to have a basis for organizing project implementation, ensuring compliance with current legal regulations, meeting the requirements of progress.

The Ministry of Construction responds to this issue as follows:

The implementation of the establishment and approval of the master plan shall comply with the provisions of Article 10 of Decree No. 178/2025/ND-CP dated July 1, 2025 of the Government detailing a number of articles of the Law on Urban and Rural Planning.

In case the investor implements the construction investment to develop a master plan as a basis for project establishment, according to the provisions of Point a, Clause 1, Article 4 of Decree No. 175/2024/ND-CP dated December 30, 2024 of the Government detailing a number of articles and measures to implement the Construction Law on construction management, construction work, appraisal and approval of planning according to the law on urban and rural planning as a basis for project establishment under the project preparation phase.

The appraisal and approval of project preparation costs shall be implemented in accordance with the provisions of Article 10 of Decree No. 10/2021/ND-CP dated February 9, 2021 of the Government on management of construction investment costs.

The works must have their fire prevention and fighting designs appraised.

Clause 1, Article 6 of Decree No. 105/2025/ND-CP dated May 15, 2025 of the Government stipulates:

"The project must be assessed by the feasibility study report on construction investment, construction design implemented after the basic design at the specialized construction agency and is included in Appendix III attached to this Decree and must be assessed by the specialized construction agency for fire prevention and fighting. The implementation of fire prevention and fighting design appraisal in the feasibility study report, construction design implemented after the basic design and the time to return appraisal results of fire prevention and fighting design are integrated and integrated with the process of appraisal of feasibility study report, construction design implemented after the basic design and return of appraisal results according to the provisions of the law on construction".

Accordingly, based on the nature, scale, capital and granting of works in the resettlement area approved by competent state agencies to compare with subjects subject to appraisal of the Construction Investment Feasibility Study Report at a specialized agency on construction according to the provisions of the law on Construction and subjects in Appendix III of Decree No. 105/2025/ND-CP to determine whether works in the resettlement area are subject to appraisal of fire prevention and fighting designs or not?

Xuyên Đông
RELATED NEWS

The Ministry of Agriculture and Environment proposes cases of land recovery that do not require an approved resettlement plan

|

According to the proposal of the Ministry of Agriculture and Environment, some cases will have their land reclaimed without an approved resettlement plan.

A series of resettlement houses left unused for many years, tired of waiting for people to move in

|

A series of resettlement housing projects in Hanoi have been completed for many years but there are still no people living there, leading to deterioration and waste of investment resources.

Compensation, support and resettlement for high-speed railway projects from 2026

|

Khanh Hoa - From 2026 and 2028, the locality will implement compensation, support and resettlement for the North-South high-speed railway project through the area.

26 provinces and 9 ministries have not yet completed the settlement of the regime for officials and civil servants on leave

|

The Minister of Home Affairs said that there are currently 26 provinces and 9 ministries that have not yet completed the settlement of the regime for cadres and civil servants on leave according to Decree 178.

Hai Phong struggles to build schools, reinforce weak dykes before storm No. 11

|

Hai Phong - Communes, wards and special zones in Hai Phong are urgently deploying measures to respond to storm No. 11 that is about to make landfall.

Mr. Le Ngoc Quang was appointed to continue to be Secretary of the Quang Tri Provincial Party Committee

|

Quang Tri - The first Provincial Party Congress announced the decision on the personnel of the Executive Committee, Mr. Le Ngoc Quang was appointed to continue to hold the position of Provincial Party Secretary.

Children in the border area enjoy the Mid-Autumn Festival with soldiers

|

Cao Bang - The locality has just coordinated to organize a Mid-Autumn Festival program with the theme "Diamond - Full Moon Festival Night".

Schools in Hanoi plan to let students stay home to prevent and combat storm No. 11 Matmo

|

Hanoi To proactively respond to storm No. 11 ( Matmo), educational institutions have planned to organize teaching during the days of storms and floods.

The Ministry of Agriculture and Environment proposes cases of land recovery that do not require an approved resettlement plan

Xuyên Đông |

According to the proposal of the Ministry of Agriculture and Environment, some cases will have their land reclaimed without an approved resettlement plan.

A series of resettlement houses left unused for many years, tired of waiting for people to move in

Việt Bắc |

A series of resettlement housing projects in Hanoi have been completed for many years but there are still no people living there, leading to deterioration and waste of investment resources.

Compensation, support and resettlement for high-speed railway projects from 2026

Bình Quý |

Khanh Hoa - From 2026 and 2028, the locality will implement compensation, support and resettlement for the North-South high-speed railway project through the area.