Slow land allocation, social housing projects in Ninh Binh face difficulties

NGUYỄN TRƯỜNG |

The implementation of social housing projects in Ninh Binh province is facing many difficulties and problems in site clearance (GPMB), land allocation, investor selection... leading to slow progress of projects, not meeting the requirements.

No social housing projects have been allocated land

Currently, in Ninh Binh province, there are 3 social housing projects being implemented and 2 projects have been detailed planned. However, up to now, no project has been allocated land.

Of the 3 projects being implemented, there is 1 independent social housing project for low-income people, which is the Social Housing Construction Project for low-income people in Ninh Phong ward (Hoa Lu city). The project is invested by Truong Thang Construction and Trading Investment Company Limited. Since 2016, the company has paid over 2.88 billion VND to implement the compensation and support plan for site clearance.

All 17 individuals and households whose land was recovered have received compensation and support and have not complained. However, because the project belongs to the "planning of a new residential area west of Ly Nhan Tong Street, Ninh Phong Ward, Hoa Lu City", land acquisition and land allocation procedures are still stuck.

For 2 other projects under implementation, including the Investment Project to build a new urban area in the North, sub-area IX (in Ninh Nhat commune and Ninh My ward, Hoa Lu city), the project is invested by Kosy Joint Stock Company with a total area of 40.7 hectares, of which, there is an investment in the construction of social housing over 20% of the total residential land area. The project has been implemented since 2020, but only now have 356/403 households with an area of 36.4 hectares been compensated and cleared.

The Yen Binh urban area project, Yen Binh ward, Tam Diep city is invested by The Light Group Joint Stock Company with a total investment capital of over VND 3,346 billion. Currently, the investor has not been decided by the competent State agency to allocate land or lease land in the field to implement the procedures to start construction according to the approved detailed project plan and investment policy.

Proposal to shorten time and land allocation procedures

In order to accelerate the progress of social housing projects and complete the target of 3,100 units assigned by the Central Government under the project "Investment in building at least 1 million social houses in the period of 2021-2030", the People's Committee of Ninh Binh province assigned the Department of Construction to preside and coordinate with the concerned departments, branches and localities to urgently complete and submit the project implementation plan for the period 2024-2025 and 2026-2030.

The People's Committee of Ninh Binh Province has also assigned the Department of Agriculture and Environment to preside over and coordinate with relevant units to study and advise the Provincial People's Committee to report to the Government for policies proposals to shorten the time and order of implementing social housing projects to ensure the requirements of land use planning and planning. At the same time, shorten the time and procedures for land allocation (land to implement social housing projects) and support and create conditions for investors to access soon with preferential loans.

Regarding the progress of implementing social housing projects in the area, Mr. Pham Quang Ngoc - Chairman of Ninh Binh Provincial People's Committee, also admitted that the investment in the construction of social housing projects in the area has not yet met the requirements.

After the National Online Conference on removing difficulties and obstacles, promoting the development of social housing chaired by Prime Minister Pham Minh Chinh held on the afternoon of March 6, Chairman of Ninh Binh Provincial People's Committee Pham Quang Ngoc requested relevant levels and sectors to closely review and inspect the implementation process and progress of investors to properly manage the target. At the same time, considering removing difficulties for businesses, especially difficulties in investment procedures, land procedures, amending planning and site clearance work so that projects can be quickly implemented...

NGUYỄN TRƯỜNG
TIN LIÊN QUAN

Quang Ngai workers wait to quench their thirst for social housing

|

Quang Ngai will promote the development of social housing, help thousands of workers settle down, reduce the burden of renting...

Progress of implementation of 2 social housing projects in Dong Anh

|

Hanoi - The city has established a working group to evaluate the implementation registration documents and approve the documents inviting interest in 2 social housing construction projects in Dong Anh district.

Bac Ninh, Bac Giang - Bright spot in social housing development

|

According to the Ministry of Construction, the two provinces of Bac Ninh and Bac Giang are considered bright spots in social housing development.

2 problems hindering the development of social housing

|

The Deputy Director of the Department of Land Management (Ministry of Agriculture and Environment) said that the major problem with the development of social housing is policies and policy implementation.

Consider opening a tourist route to Ha Long Bay - Lan Ha Bay

|

Quang Ninh - In 2025, Quang Ninh province will soon open a tourism route from Lan Ha Bay, Hai Phong to Ha Long Bay, Quang Ninh.

Mr. Pham Quang Linh is a member of the Central Committee of the Vietnam Fatherland Front

|

The Standing Committee of the Central Committee of the Vietnam Fatherland Front issued a Decision on the dismissal of Mr. Pham Quang Linh from the Central Committee of the Vietnam Fatherland Front.

Fine and collect nearly VND1,400 billion in taxes from e-commerce transactions

|

After reviewing more than 40 billion transactions from e-commerce platforms, the tax authority handled 33,003 violations, collected and fined nearly VND1,400 billion.

Vietnam prepares carefully to negotiate with the US on counterpart tariffs

|

Vietnam is organizing a negotiation delegation to the US next week, preparing the contents to discuss the 46% tax.

Quang Ngai workers wait to quench their thirst for social housing

VIÊN NGUYỄN |

Quang Ngai will promote the development of social housing, help thousands of workers settle down, reduce the burden of renting...

Progress of implementation of 2 social housing projects in Dong Anh

KHÁNH AN |

Hanoi - The city has established a working group to evaluate the implementation registration documents and approve the documents inviting interest in 2 social housing construction projects in Dong Anh district.

Bac Ninh, Bac Giang - Bright spot in social housing development

Vân Trường |

According to the Ministry of Construction, the two provinces of Bac Ninh and Bac Giang are considered bright spots in social housing development.

2 problems hindering the development of social housing

ANH HUY |

The Deputy Director of the Department of Land Management (Ministry of Agriculture and Environment) said that the major problem with the development of social housing is policies and policy implementation.