Compensation of 7,770 billion VND for Ho Chi Minh City Ring Road 3 through Binh Duong

ĐÌNH TRỌNG |

The component project of compensation, site clearance and resettlement for the construction of Ho Chi Minh City Ring Road 3 through Binh Duong has a total investment of 13,528 billion VND.

Ho Chi Minh City Ring Road 3 passing through Binh Duong province is about 26.6 km long, of which the Tan Van intersection section is 2.37 km long, the Binh Chuan - Saigon River section is 8.9 km long and the section coinciding with My Phuoc - Tan Van road is 15.3 km long.

The project has a total investment of 19,280 billion VND divided into 2 components: construction and compensation. Of which, component project 6 is implementing site clearance and resettlement with a total investment of 13,528 billion VND. Currently, the implementation is focused on Tan Van intersection and the section from Binh Chuan intersection to Saigon River.

Binh Duong province has focused on site clearance, according to the construction progress of the bidding packages. Binh Duong province's electronic information portal said that currently, the total land area recovered is 126.47 ha/129 ha. Regarding disbursement, compensation has been paid for 7,770 billion VND.

Cong truong thi cong doan nut giao Binh Chuan. Anh: Dinh Trong
Construction site of Binh Chuan intersection. Photo: Dinh Trong

According to records, in the bid packages, there are still some households and units that have not received compensation and relocation. Therefore, it affects the construction process of the bid packages.

For example, in the Binh Chuan intersection construction package, the water supply line, underground power system, overhead power poles, and transformer stations on My Phuoc Tan Van route have not been relocated. Furthermore, there are still some points at the intersection that have not yet completed site clearance, and some households and units have not yet received compensation due to disagreement on compensation prices... This has caused the construction units, Thai Son Corporation Limited Company and Dai Thien Truong Joint Stock Company, to not have the entire site to carry out construction.

Ban ve giai phong mat bang va thi cong nut giao Binh Chuan. Anh: Dinh Trong
Land clearance and construction drawing of Binh Chuan intersection. Photo: Dinh Trong

For construction package 3, construction of the section from Binh Chuan to Saigon River, the total area handed over to date is 389,124/498,878 m2, reaching about 78%.

Currently, there are still some locations with land clearance problems due to technical infrastructure problems such as the intersection of National Highway 13 and Nguyen Thi Minh Khai Street. The land clearance still has resettlement households who have not yet handed over their houses, so the land is not seamless. The public road to transport materials has not been implemented. The access road to the land that is eligible for implementation is prohibited.

Currently, contractors are recommending that investors coordinate with relevant parties to provide a more detailed roadmap so that construction units can grasp the time to hand over clean sites and organize construction to ensure progress according to the signed contract.

Mat bang dang duoc giai phong de thi cong duong Vanh dai 3 TPHCM. Anh: Dinh Trong
The site is being cleared for the construction of Ho Chi Minh City Ring Road 3. Photo: Dinh Trong
Ban ve tien do giao mat bang
Construction progress drawing of the construction site handover for the 3rd construction project from Binh Chuan to Saigon River. Photo: Dinh Tong
Cac ho dan va don vi
Households and compensation recipients hand over the site. Photo: Dinh Trong

Continue to mobilize households to receive compensation and relocate.

According to Mr. Nguyen Thanh Uy - Vice Chairman of Thuan An City People's Committee, the province is currently implementing a policy of financial support for people renting houses to move out of the project area. Thuan An City is also mobilizing people, basically in November and December 2024, people will hand over the land to the city.

Currently, there is still a problem at the intersection with Cach Mang Thang 8 Street and An Thanh 23 Street. Thuan An City has met with the people, will resettle and resolve policies for the people. In December 2024, the people will hand over the land to the city.

ĐÌNH TRỌNG
TIN LIÊN QUAN

Progress and roadmap of the 2,300 billion VND hospital

|

The 1,500-bed hospital with an investment capital of about VND2,300 billion in Binh Duong is being rushed to completion, expected to be put into operation at the end of 2025.

The Ho Chi Minh City Ring Road 3 project through Binh Duong has disbursed 9,248 billion

|

Binh Duong - The working delegation of the Standing Committee of Binh Duong Provincial Party Committee has supervised the implementation of the Ho Chi Minh City Ring Road 3 project on urgent issues.

Speeding up construction of 571 billion VND intersection in Ho Chi Minh City Ring Road 3 project

|

In the last months of the year, contractors are speeding up the construction progress of the Binh Chuan intersection of the Ho Chi Minh City Ring Road 3 project through Binh Duong.

Forecast of heavy rain in the North

|

According to the representative of the meteorological agency, from the evening and night of June 20 to June 22, it is necessary to be on guard against heavy rain in the midlands and mountainous areas of the North.

Recall Hai Be delicious syrup nationwide for being counterfeit

|

The delicious Hai Be syrup was identified as a fake product, not licensed for circulation by the authorities and required to recall all products nationwide.

2025 National Newspaper Association brings together 130 unique exhibition booths

|

Hanoi - 130 exhibition booths, hundreds of unique publications representing key press lines from the central to local levels at the 2025 National Press Festival.

With lights but not bright, the park in the center of Ho Chi Minh City is dark all year round

|

HCMC - Many people reported that the park at the end of Dang Thuy Tram Street (Binh Thanh District) has been in a state of "having lights but not bright" for a long time.

Many foreign enterprises are slow to pay social insurance and evade social insurance

|

According to the reporter of Lao Dong Newspaper, in recent times, many foreign enterprises have been slow to pay social insurance (SI).

Progress and roadmap of the 2,300 billion VND hospital

ĐÌNH TRỌNG |

The 1,500-bed hospital with an investment capital of about VND2,300 billion in Binh Duong is being rushed to completion, expected to be put into operation at the end of 2025.

The Ho Chi Minh City Ring Road 3 project through Binh Duong has disbursed 9,248 billion

ĐÌNH TRỌNG - NHƯ QUỲNH |

Binh Duong - The working delegation of the Standing Committee of Binh Duong Provincial Party Committee has supervised the implementation of the Ho Chi Minh City Ring Road 3 project on urgent issues.

Speeding up construction of 571 billion VND intersection in Ho Chi Minh City Ring Road 3 project

ĐÌNH TRỌNG |

In the last months of the year, contractors are speeding up the construction progress of the Binh Chuan intersection of the Ho Chi Minh City Ring Road 3 project through Binh Duong.