Basically completed the land inventory for compensation for the Ninh Thuan Nuclear Power Project

Hữu Long |

Khanh Hoa - Compensation, support and resettlement for people at two Ninh Thuan Nuclear Power Plant projects have been basically completed.

On July 21, the Khanh Hoa Provincial Construction Investment Management Board said that the compensation, support and resettlement work for people at the two nuclear power plant projects (NMDHN) Ninh Thuan 1 and Ninh Thuan 2 has basically completed the inventory, measurement and appraisal of land records, as a basis for the next steps.

At the Ninh Thuan 1 human resource and resettlement project, the factory area (409.53ha) and the resettlement area (64.85ha) have completed the inventory of 100% of households and related organizations; specific land prices have been approved, the measurement records have been appraised by the Department of Agriculture and Environment.

For Ninh Thuan 2 processing center, the factory area (404.5ha), the resettlement area (54.4ha) and the existing residential area (13.43ha) have also completed the inventory, approval of land prices and appraisal of survey maps.

In particular, the relocation of nearly 3,000 graves is still facing difficulties because the relatives of more than 1,000 graves have not been identified.

The Ninh Thuan nuclear power project is a national key project with a large scale of land acquisition, affecting thousands of households.

The People's Committee of Ninh Thuan province (before the merger) has proposed that the Government allocate about VND3,200 billion to implement the construction of resettlement areas, residential areas and site clearance.

Khanh Hoa Provincial People's Committee is currently giving strong instructions, striving to complete site clearance in 2025 in accordance with the direction of the Prime Minister.

Hữu Long
TIN LIÊN QUAN

Early payment of support money to people affected by Ninh Thuan nuclear power project

|

Khanh Hoa is meeting to discuss, remove obstacles to site clearance and soon pay support to people affected by Ninh Thuan 1 and 2 nuclear power projects.

Ninh Thuan adjusts provincial planning to implement the Nuclear Power Project

|

The locality has passed a Resolution to adjust the Ninh Thuan Provincial Planning for the period 2021 - 2030, with a vision to 2050.

Urgently need 3,200 billion VND to resettle and compensate for Ninh Thuan nuclear power project

|

Ninh Thuan - The locality calculates that for compensation, site clearance and relocation and resettlement, about VND200 billion is needed.

Man wearing a motorbike taxi shirt snatches more than 100 lottery tickets for people with disabilities in Ho Chi Minh City

|

HCMC - A man wearing a motorbike taxi shirt has snatched more than 100 lottery tickets from a disabled person in Tang Nhon Phu ward.

Storm No. 3 Wipha causes heavy rain, strong gusts of wind up to level 8 in Hanoi

|

A representative of the Northern Hydrometeorological Station warned that storm No. 3 Wipha could cause strong gusts of wind up to level 8 in Hanoi from tomorrow afternoon, July wholeheartedly warning of dangerous winds during thunderstorms.

Heavy rain, storms, needle workers still risk fishing at the foot of the hydropower plant

|

Phu Tho - Despite the heavy rain, Hoa Binh Hydropower Plant is opening floodgates, many "guards" are still gathering to fish right at the foot of the dam, despite warnings of danger.

Traffic congestion on Ho Chi Minh City - Long Thanh - Dau Giay Expressway, reason for not being exempted from toll collection

|

Repairing Long Thanh bridge on Ho Chi Minh City - Long Thanh - Dau Giay expressway caused widespread congestion, the operator shared the reason for not being exempted from reducing toll collection fees.

Storm No. 3 is about 250km away, Hung Yen and Ninh Binh have rain, light wind

|

Faced with the impact of the circulation of storm No. 3, ministries, branches and localities have requested urgent direction and response.

Early payment of support money to people affected by Ninh Thuan nuclear power project

Bình Quý |

Khanh Hoa is meeting to discuss, remove obstacles to site clearance and soon pay support to people affected by Ninh Thuan 1 and 2 nuclear power projects.

Ninh Thuan adjusts provincial planning to implement the Nuclear Power Project

Bình Quý |

The locality has passed a Resolution to adjust the Ninh Thuan Provincial Planning for the period 2021 - 2030, with a vision to 2050.

Urgently need 3,200 billion VND to resettle and compensate for Ninh Thuan nuclear power project

Hữu Long |

Ninh Thuan - The locality calculates that for compensation, site clearance and relocation and resettlement, about VND200 billion is needed.