A trillion-dong project under construction for more than a decade

Minh Hạnh |

Hanoi Many apartment buildings in Ha Dong district have been under construction for more than a decade, causing waste of resources and public outrage.

The Usilk City project - the commercial name of the Van Khe New Urban Area Expansion Area - was approved by the People's Committee of Ha Tay province (old) in Decision No. 2781/QD-UBND dated July 24, 2008. The project has a total area of nearly 92,107m2, located in La Khe and Van Phuc wards, Ha Dong district, Hanoi.

The project is expected to become a high-end apartment complex with 9 blocks of buildings from 25 to 50 floors (codiges from CT1-101 to CT4-109), providing more than 3,670 apartments, with a total investment of more than 291 billion VND. According to the commitment, the entire project will be completed and handed over in the fourth quarter of 2013.

Du an do dang vat lieu gi set. Anh: Huu Chanh
The project is unfinished with rust materials. Photo: Huu Chanh

However, 16 years have passed, in addition to the 4 buildings (CT1-101, CT1-102, CT1-103, CT2-105) that have been completed and put into use, most of the remaining blocks are still unfinished, only stopping at the rough construction.

On April 8, a series of unfinished construction works with cracked concrete, rusty steel... were recorded here, reflecting a serious waste of land and social financial resources.

Notably, some buildings have mobilized capital from customers at a rate of 70% to 100% of the value of the sale and purchase contract. At building 104-CT1, after being permitted by the Department of Construction, the investor is completing the items.

Thi cong do dang cong trinh xuong cap lang phi. Anh: Huu Chanh
Unfinished construction causes the project to deteriorate and waste. Photo: Huu Chanh

However, instead of focusing on completing the blocks of houses according to the committed schedule, the investor was accused of misusing the mobilized capital. As a result, hundreds of customers fell into a situation of "losing money, not seeing a house", many families were forced to rent temporary houses for more than a decade, some even died but still had not received an apartment.

According to the reporter of Lao Dong Newspaper, currently, the first floor of the unfinished construction blocks has been used by investors for lease as parking lots, warehouses, etc. This not only causes public outrage but also raises suspicions about the use of project assets and resources contrary to the original investment purpose.

Faced with the situation of blocks of houses in Usilk City being behind schedule for a long time, a representative of the Department of Economy, Infrastructure and Urban Areas of Ha Dong district said: The District People's Committee has repeatedly directed functional agencies to coordinate with investors to remove obstacles, and at the same time reported to the Hanoi People's Committee for direction to resolve them.

However, according to this person, "due to the limited financial and construction capacity of Song Da - Thang Long Joint Stock Company", the enforcement measures in recent years have not yet brought positive results. Unfinished apartment buildings continue to be "shelved", while the legitimate rights of hundreds of customers are not guaranteed.

A project that was once expected to become a new urban highlight has now become a "scare" in the heart of the capital. The question is: When will those cold, deserted blocks really "revive"?

Sau khi duoc su dong y cua So Xay dung toa CT bat dau trien khai hoan thien. Anh: Huu Chanh
After receiving the approval of the Department of Construction, building 104-CT1 began to be completed. Photo: Huu Chanh

To handle the problems related to the Van Khe Urban Area Expansion Project (Usilk City), La Khe Ward, Ha Dong District, Hanoi Department of Construction has issued Official Letter No. 503/SXD-TTr recommending the Hanoi People's Committee to allow the project's building 104-CT1 to continue construction and hand over the apartments to customers in time.

The Department of Construction requires the investor to organize the construction of the work in accordance with the approved construction drawing design dossier, and at the same time review the dossier of the design of fire prevention and fighting (fire prevention and fighting (fire prevention and fighting) of the competent authority as a basis for fire prevention and fighting and acceptance to put the work into use as prescribed.

The Department also requested Song Da - Thang Long Joint Stock Company to urgently contact the authorities to complete the fire prevention and fighting acceptance and hand over the project for buildings 101, 102, 103 (which are buildings with residents).

The People's Committee of Ha Dong District is assigned to inspect and supervise construction activities at the project, promptly detect, prevent and handle violations of construction order according to authority and legal regulations.

The abandonment of a series of blocks of houses at the Usilk City project not only causes heavy economic damage, damaging the urban face, but also erodes people's trust in investors and State management in the real estate sector.

To avoid wasting resources, protect the legitimate rights of the people and rectify the situation of "over-slow capital mobilization, unfinished construction", public opinion recommends that the Hanoi People's Committee should take stronger measures against investors, such as: revoking projects, transferring them to truly capable units or criminally prosecuting if signs of law violations are detected.

Minh Hạnh
TIN LIÊN QUAN

The project has a scale of 13.8 hectares, with a capital of nearly 290 billion VND, and is under construction in Hanoi

|

Hanoi - The nearly 14ha park project, when completed, will contribute to creating environmental landscape, opening up more entertainment and sports space for people.

Accelerating the construction of Hanoi Ring Road 4, many sections have been revealed

|

Hanoi - The packages of the Ring Road 4 parallel road project are being accelerated to complete in 2025.

Hanoi speeds up construction of Ring Road 4, striving to complete it in 2025

|

On the occasion of the beginning of spring, Hanoi leaders visited, wished a happy new year and encouraged cadres and workers at the construction site of the Ring Road 4 parallel road project and requested units to ensure progress and complete the project this year.

Sad news

|

Journalist Nguyen Huy Dan, born in 1928, due to his advanced age and weakness, died at 4:30 am on April 16, 2025, or 19.3 years, at 98 years old.

Set the degraded road in Thai Binh after the labor reflection

|

Thai Binh - Checking and leveling the center of the commune center has been degraded for many years in Thai Binh after the Lao Dong newspaper.

Review and sanction related to the case of illegal land exploitation in Quang Tri

|

Quang Tri - Regarding the case of illegal land exploitation that the Lao Dong newspaper, collectives and individuals related to review and sanctions.

Quang Tri people opposed sand exploitation because of landslides

|

People in Hai Son commune (Hai Lang district, Quang Tri province) oppose sand and grit exploitation on Thac Ma River because of concerns about the risk of landslides.

The conversion car operates on Hanoi street, potentially dangerous traffic

|

Hanoi - UAZ, Jeep cars ... converted, carrying tourists operating on the streets, there are many risks of traffic safety.

The project has a scale of 13.8 hectares, with a capital of nearly 290 billion VND, and is under construction in Hanoi

SÓNG HỮU |

Hanoi - The nearly 14ha park project, when completed, will contribute to creating environmental landscape, opening up more entertainment and sports space for people.

Accelerating the construction of Hanoi Ring Road 4, many sections have been revealed

HỮU CHÁNH |

Hanoi - The packages of the Ring Road 4 parallel road project are being accelerated to complete in 2025.

Hanoi speeds up construction of Ring Road 4, striving to complete it in 2025

Hữu Chánh |

On the occasion of the beginning of spring, Hanoi leaders visited, wished a happy new year and encouraged cadres and workers at the construction site of the Ring Road 4 parallel road project and requested units to ensure progress and complete the project this year.