Site clearance for 19km of Suoi Cai, 33 cases have not yet handed over land

ĐÌNH TRỌNG |

Ho Chi Minh City - Currently, there are still 33 cases that have not handed over clean land for the Suoi Cai dredging and reinforcement project. Units are accelerating the progress of site clearance for this project.

According to the Ho Chi Minh City Urban Infrastructure Project Management Board, the Suoi Cai dredging and reinforcement project, the section from Tho Ut bridge to Dong Nai river, includes 10 bidding packages for the canal construction, works on the canal and 3 bidding packages for electricity relocation. To date, bidding packages 2A, 2B have been basically completed, and the entire project is expected to be completed in 2026.

However, currently, some bidding packages are still slow compared to the signed contracts. The main reason for the delay is difficulties in site clearance. Currently, 33 households have not yet handed over clean land. Households also petitioned about land compensation prices, resettlement policies, or disputes over land origin.

Tiến độ dự án bị ảnh hưởng khi còn 33 trường hợp chưa bàn giao đất sạch. Ảnh: Đình Trọng
Project progress is affected when there are still 33 cases that have not handed over clean land. Photo: Dinh Trong

The Ho Chi Minh City Urban Infrastructure Project Management Board said that it will continue to closely coordinate with the People's Committees of localities to synchronously deploy site clearance work. Urge communes and wards to urgently mobilize and directly dialogue with people. Request the Land Fund Development Center to accelerate the completion of compensation procedures, completing them before June 15.

In case households still do not hand over land despite many mobilizations, functional agencies will complete administrative procedures and organize land recovery coercion. It is expected to focus on completing it before June 15 and the most complex households will be completed in August 2026.

It is known that the above project has a length of nearly 19km, with a total investment of nearly 5,900 billion VND from the central and Ho Chi Minh City budgets. This is a key level II project to ensure drainage of rainwater and treated wastewater for a basin area of 22,503 ha.

Công tác giải phóng mặt bằng cho dự án đang được đẩy nhanh tiến độ. Ảnh: Đình Trọng
Site clearance for the project is being accelerated. Photo: Dinh Trong

Responding to heavy rain

According to records, currently, Ho Chi Minh City is experiencing heavy rains continuously. Water from upstream flowing to Suoi Cai seriously affects the construction progress under the stream bed.

Mưa lớn gây ảnh hưởng đến tiến độ thi công dự án. Ảnh: Đình Trọng
Heavy rain affects project construction progress. Photo: Dinh Trong

Currently, the Ho Chi Minh City Urban Infrastructure Project Management Board has requested contractors to take advantage of favorable weather, increase manpower, machinery and equipment, and organize "3 shifts, 4 crews" to compensate for the delayed progress. At the same time, proactively prepare technical plans to guide the flow, arrange more large-capacity pumps to promptly pump dry the foundation pits, clean the enclosure frame, and drain water immediately when there is heavy rain, minimizing the time of construction interruption.

ĐÌNH TRỌNG
RELATED NEWS

Outside the boundary of site clearance, a woman in Quang Ninh still donates land to expand the road

|

Quang Ninh - The donated area is outside the site clearance boundary of the project, but Ms. Nguyen Thi Thi's family still voluntarily handed it over.

45 km long expressway in Ho Chi Minh City must complete site clearance before October 2026

|

Ho Chi Minh City - Ho Chi Minh City People's Committee requests units and localities to coordinate to accelerate the site clearance progress of the Ho Chi Minh City - Thu Dau Mot - Chon Thanh expressway.

Urgently clear the site for the Vinh - Thanh Thuy expressway project

|

The site clearance for the Vinh - Thanh Thuy expressway project is being strongly urged by Nghe An province, in order to soon complete the project, which is important in connecting the region, expanding development space to the West and strengthening trade through Thanh Thuy Border Gate.

Russia launches fierce attack on Kiev

|

Kiev suffered a wave of fierce attacks from Russia, many people are believed to be trapped under the rubble of an apartment building.

Stock market has not shown signs of bottoming out

|

The stock market will continue to adjust to retest support zones if demand does not improve soon in the coming sessions.

Candidates are concerned about the actual type of math in the 10th grade Math exam in Ho Chi Minh City

|

Entering the 120-minute Math exam in the 10th grade entrance exam in Ho Chi Minh City, many candidates said they were most worried about the practical application questions.

Expecting Vietnam Trade Union to have a large-scale program on AI and digital skills universalization

|

That is the expectation of Ms. Tran Thuy Duong - Member of the Executive Committee of FPT Corporation Trade Union, Chairwoman of FPT University Trade Union.

New look of the ring road project worth more than 7,210 billion VND in Hanoi

|

Hanoi - The Ring Road 1 project, Hoang Cau - Voi Phuc section, is being urgently implemented, in which some sections have been asphalted.

Outside the boundary of site clearance, a woman in Quang Ninh still donates land to expand the road

Nguyễn Huệ |

Quang Ninh - The donated area is outside the site clearance boundary of the project, but Ms. Nguyen Thi Thi's family still voluntarily handed it over.

45 km long expressway in Ho Chi Minh City must complete site clearance before October 2026

ĐÌNH TRỌNG |

Ho Chi Minh City - Ho Chi Minh City People's Committee requests units and localities to coordinate to accelerate the site clearance progress of the Ho Chi Minh City - Thu Dau Mot - Chon Thanh expressway.

Urgently clear the site for the Vinh - Thanh Thuy expressway project

QUANG ĐẠI |

The site clearance for the Vinh - Thanh Thuy expressway project is being strongly urged by Nghe An province, in order to soon complete the project, which is important in connecting the region, expanding development space to the West and strengthening trade through Thanh Thuy Border Gate.