Complete the nearly 220 billion VND connecting road project in Hai Phong in December

Hoàng Khôi |

Hai Phong - Phu Lien ward leaders directed the completion of the construction of the road connecting Nguyen Luong Bang - Tran Nhan Tong road in December.

The project of connecting Nguyen Luong Bang Street with Tran Nhan Tong Street was approved by the 16th Hai Phong City People's Council at the 6th session on July 20, 2022.

On March 8, 2023, the City People's Committee approved the project in Decision No. 600/QD-UBND with a total investment of 189.312 billion VND. The investment scale of the project is to build a road connecting Nguyen Luong Bang Street with Tran Nhan Tong Street about 1.5 km long; move electricity, transformer stations, complete the construction of urban technical infrastructure works such as drainage systems; lighting systems, trees, and road signs according to current standards.

According to the plan, the project is expected to be completed in 2024. However, in October 2024, at the 19th session, the 16th Hai Phong City People's Council decided to adjust the investment policy of this project in terms of both investment level and implementation time. Accordingly, in addition to 189.312 billion VND from the city budget, the project was supplemented with more than 29 billion VND from the budget of the old Kien An district (total investment is 218.327 billion VND). The implementation period has also been extended to 2025.

According to the report of the Kien An Project Management Board, by November 28, the project had reached about 75-85% of the construction volume. Contractors are continuing to implement the remaining construction work, expected to be completed before December 30, 2025. Ancillary items such as lighting systems, traffic signs and related technical infrastructure are also being deployed synchronously to ensure the route can be put into operation immediately upon completion.

Regarding the cemetery land area, the unit has publicized and solicited opinions on the draft compensation and support plan for 13/13 cases; 4 cases have approved the compensation and support plan; submitted an appraisal of the compensation and support cost for 2 households with residential land.

Du an da dat 75-85% tien do. Ảnh: Cong TTDT phuong Phu Lien
The project has reached 75-85% progress. Photo: Phu Lien Ward Portal

Speed up progress, complete in December

Recently, through the project progress check, Ms. Bui Thi Tuyet Mai - Party Committee Secretary, Chairman of the Ward People's Council noted that construction units should focus on human resources and machinery to complete all items before December 25, and urgently complete the documents to serve the settlement work. The Ward People's Committee continues to closely coordinate with the investor, the Kien An Project Management Board, to urge contractors to closely follow the progress, promptly remove difficulties, and ensure the project is completed on schedule. The ward police ensure security and order at the construction area, creating favorable conditions for units to deploy work.

Regarding site clearance, the Party Secretary and Chairman of the Ward People's Council requested specialized agencies to focus highly to complete 95% of the site clearance task for phase 2 of the project connecting Nguyen Luong Bang Street and Tran Nhan Tong Street in December. Units comply with regulations on compensation and site clearance policies, continue to propagate and mobilize households to agree to hand over the site. The Economic - Infrastructure and Urban Affairs Department closely follows the city's departments and branches, promptly advises, removes difficulties and obstacles, and ensures that the project is implemented on schedule.

Hoàng Khôi
RELATED NEWS

Paying nearly 500 billion VND in compensation for the project in the West of Hai Phong

|

Hai Phong - Kim Thanh Commune has just paid compensation and support for site clearance to serve the implementation of the Kim Thanh 2 Industrial Park project (phase 1).

294 more households receive compensation for the trillion-dong industrial park project in Hai Phong

|

Hai Phong - Kien Hung commune has just paid compensation for site clearance to 294 households in Ky Son village.

Hai Phong adjusts resolution on social housing development until 2030

|

Hai Phong - On November 29, Mr. Le Tien Chau, member of the Party Central Committee, Secretary of the City Party Committee, Head of the Hai Phong National Assembly Delegation chaired the City Party Committee conference.

Price increase covers the mountain top in Na Ngoi commune when the temperature drops below 0°C

|

Nghe An - Willpower appears at many high points of Na Ngoi commune, local authorities recommend that people keep warm and protect their livestock.

President Bui Thi Minh Hoai sent a congratulatory letter on the occasion of the 50th anniversary of the National Day of the Lao People's Democratic Republic

|

On the occasion of the 50th anniversary of the National Day of the Lao People's Democratic Republic (December 2, 1975 - December 2, 2025) and the 105th anniversary of the birth of President Cay-xong Phom-vi-han (December 13, 20,000 - December 13, 2025), on behalf of the Central Committee of the Vietnam Fatherland Front, Ms. Bui Thi Minh Hoai, Politburo member, Secretary of the Party Central Committee, Chairman of the Central Committee of the Vietnam Fatherland Front, sent a congratulatory letter to comrade and comrade Xinh-La-Vong Khuot-phay-thun, Politburo member of the Lao People's Revolutionary Party, Chairman of the Central Committee of the Lao Fatherland Building Front and all leaders and officials of the Lao Fatherland Building Front.

Power and water cuts for a series of works of thousands of square meters illegally built on agricultural land

|

Duong Hoa commune, Hanoi City has just issued a decision to enforce and sanction administrative violations on agricultural land.

The issue of ensuring security for Ukraine remains uncertain after negotiations in Florida

|

The US-Ukraine talks on November 30 ended with positive signals, but the issue of ensuring security for Ukraine has not yet been agreed upon.

Son La coffee growers worry about frost and frost arriving early

|

Son La - Coffee growers " sit restless" when frost and ice appear early, causing damage at the right time of harvest.

Paying nearly 500 billion VND in compensation for the project in the West of Hai Phong

Hoàng Khôi |

Hai Phong - Kim Thanh Commune has just paid compensation and support for site clearance to serve the implementation of the Kim Thanh 2 Industrial Park project (phase 1).

294 more households receive compensation for the trillion-dong industrial park project in Hai Phong

Hoàng Khôi |

Hai Phong - Kien Hung commune has just paid compensation for site clearance to 294 households in Ky Son village.

Hai Phong adjusts resolution on social housing development until 2030

Mai Dung |

Hai Phong - On November 29, Mr. Le Tien Chau, member of the Party Central Committee, Secretary of the City Party Committee, Head of the Hai Phong National Assembly Delegation chaired the City Party Committee conference.