Khanh Hoa solicits opinions from residents of the resettlement area serving the evacuation of the No. 2 Nuclear Power Plant

Phương Linh |

Khanh Hoa - Resettlement area serving migrants of Nuclear Power Plant No. 2 is proposed at 2 new locations.

Proposing 2 options for arranging the construction of new resettlement areas

On the morning of October 23, at the headquarters of the People's Committee of Vinh Hai commune, the People's Committee of Khanh Hoa province organized a survey to collect public opinions on the location for the construction of a resettlement area to serve the evacuation of the No. 2 Nuclear Power Plant.

Vice Chairman of Khanh Hoa Provincial People's Committee, Mr. Trinh Minh Hoang chaired the conference.

Previously, the resettlement area of the Ninh Thuan 2 Nuclear Power Plant Project was identified in Thai An village (Vinh Hai commune) with an area of 54.4 hectares.

However, part of this area is in an emergency protection zone and is no longer suitable for implementation.

Anh: Phuong Linh
Khanh Hoa Provincial Construction Investment Project Management Board presents new locations. Photo: Phuong Linh

To ensure the principle of building nuclear power plants according to the regulations of the International Atomic Energy Agency, in September 2025, the Provincial Construction Investment Project Management Board in coordination with the People's Committee of Vinh Hai commune surveyed the new location.

There are 2 locations that meet the requirements for area and number of resettlement plots, arranging commercial - service areas to serve job conversion for people and in accordance with the recommendations of the Ministry of Science and Technology.

Accordingly, location 1 in My Phong village, Vinh Hai commune, in sub-area No. V, is planned to build Ninh Chu National Tourist Area until 2045.

This area has an estimated area of about 69.24 hectares, about 6.8 km from the nearest reactor center to the resettlement area construction site.

Total expected lots of 1,095 residential land lots/24.13ha. The expected area to be arranged as a commercial service area to serve job conversion is 14.68ha.

At the second proposed location in Khanh Nhon 1 village, Vinh Hai commune, in area No. V of the Ninh Chu National Tourist Area construction planning, the expected area is about 76.63 hectares.

The distance from the nearest reactor center to the resettlement area construction site is about 8.0 km. The total expected number of lots is 1,415 residential land lots/21.09ha. The expected area for arranging a commercial service area to serve job conversion is 8.06ha.

Nguoi dan y kien ve vi tri khu tai dinh cu moi doi voi du an Nha may dien hat nhan so 2. Anh: Phuong Linh
People commented on the location of the new resettlement area for the nuclear power plant No. 2 project. Photo: Phuong Linh

Research on construction locations to ensure harmony

The survey included 50 households, representatives of cadres, party members, retirees... in the area. People affirmed their agreement with the implementation of the nuclear power project for national benefits.

However, with the new resettlement project, representatives of some households have suggested that the authorities study the relocation of people within the locality.

Propose that the province consider adding the location of Hon Mot area, Vinh Hai commune to make it more convenient for people's lives and production when resettling.

Anh: Phuong Linh
Mr. Tiet hopes that the compensation and support policy in the coming time should be appropriate, ensuring the long-term life and livelihood of the people. Photo: Phuong Linh

According to Mr. Le Van Tiet (residing in Thai An village), he is very in agreement to give up land for the project, but the resettlement location needs to be more convenient for transportation and have production conditions for the people.

Accepting the opinions and recommendations of the people at the survey, Mr. Trinh Minh Hoang suggested that relevant agencies survey and provide additional advice so that the Provincial People's Committee can propose and choose the optimal solution.

Mr. Trinh Minh Hoang added that at the meeting on the afternoon of October 22, the Prime Minister especially emphasized the need to do a good job of resettlement for people in the project area.

The location of the new resettlement area is guaranteed to be outside a radius of 3-5km (urgent protection zone - PAZ).

The Government also agreed to review and supplement policies to support people in converting careers to suit the current practical situation...

Phương Linh
RELATED NEWS

The Prime Minister requested to do a good job of resettlement for people in the nuclear power plant project area

|

The Prime Minister especially emphasized the need to do a good job of resettlement for people in the nuclear power plant project area.

Supplementing procedures for deciding on investment policies for nuclear power plant projects

|

The Government has just issued Decree No. 275/2025/ND-CP, supplementing the order and procedures for deciding on the investment policy for the nuclear power plant project.

Prime Minister requests report on the construction of nuclear power plants

|

The Prime Minister requested the Ministry of Industry and Trade and agencies to report on the construction situation and issue mechanisms and policies for the construction of nuclear power plants.

Special attention is paid to rewarding workers and those who directly work in production

|

Chairman of the Central Committee of the Vietnam Fatherland Front Do Van Chien emphasized that it is necessary to pay special attention to rewarding workers, those who directly work in production, and collectives operating in disadvantaged areas, remote areas, and areas.

Mr. Putin calls the signing of the Hanoi Convention a historic milestone

|

Russian President Vladimir Putin called the signing of the Convention against Cybercrime a historic event, highlighting Russia's pioneering role in this global effort.

The old lady's rib porridge shop is packed with customers in Hanoi's Old Quarter

|

Hanoi - Ba Loi Cong cartilage rib porridge shop leaves an impression in the hearts of many people in the capital because of its old, rustic flavor.

Landslides, local congestion on Lo Xo Pass due to heavy rain

|

Quang Ngai - Due to heavy rain lasting for more than two days, the Lo Xo Pass area on Ho Chi Minh Road was partially congested due to landslides on the road.

Israel announces new attack in Gaza

|

The Israeli military said it had launched a targeted attack in the central Gaza Strip.

The Prime Minister requested to do a good job of resettlement for people in the nuclear power plant project area

HƯƠNG NHA |

The Prime Minister especially emphasized the need to do a good job of resettlement for people in the nuclear power plant project area.

Supplementing procedures for deciding on investment policies for nuclear power plant projects

HƯƠNG NHA |

The Government has just issued Decree No. 275/2025/ND-CP, supplementing the order and procedures for deciding on the investment policy for the nuclear power plant project.

Prime Minister requests report on the construction of nuclear power plants

PHẠM ĐÔNG |

The Prime Minister requested the Ministry of Industry and Trade and agencies to report on the construction situation and issue mechanisms and policies for the construction of nuclear power plants.