On the afternoon of October 22, at the Government headquarters, Politburo member and Prime Minister Pham Minh Chinh - Head of the Steering Committee for the Construction of the Nuclear Power Plant, chaired the 3rd meeting of the Steering Committee.
In his concluding remarks, Prime Minister Pham Minh Chinh acknowledged and commended ministries, agencies and localities for being proactive and actively implementing assigned tasks and achieving specific results after the second meeting of the Steering Committee.
Of the 18 assigned tasks, 9 tasks have been completed, including a number of important tasks, such as issuing an action plan of the Government to implement Resolution 189 of the National Assembly, adjusting the VIII power plan, submitting to the National Assembly to promulgate the Law on Atomic Energy and assigning Khanh Hoa province 3,236 billion VND to implement a migration and resettlement project...
Prime Minister Pham Minh Chinh requested relevant ministries, branches and localities to effectively implement Resolution 328/NQ-CP on the Government's Action Program to implement Resolution No. 70-NQ/TW dated August 20, 2025 of the Politburo on ensuring national energy security until 2030, with a vision to 2045.
The Prime Minister directs many key tasks, specifically for ministries, branches and localities related to proposing additional capital for site clearance to meet the requirements and standards of the International Atomic Energy Agency;
Complete the legal basis and specific mechanisms for implementing the work, including advising on the development of a Resolution of the National Assembly and a National Assembly Standing Committee to handle related legal problems.
The Prime Minister also directed the promotion of negotiations and the completion of agreements with partners according to the principles of harmonious benefits, shared risks, cutting cumbersome procedures, developing appropriate standards and regulations to ensure compliance with safety standards and security instructions of the International Atomic Energy Agency and international conventions related to the nuclear field.
EVN urgently establishes a pre-feasibility project in October; agencies complete negotiations on cooperation agreements to build nuclear power plant 1 and complete legal corridors in November 2025.
The Ministry of Education and Training closely coordinates with EVN and Petrovietnam to clearly identify the need for quantity, qualifications, and human resource expertise to serve nuclear power plants; on that basis, organize training and call for and attract domestic and foreign human resources to work.
Prime Minister Pham Minh Chinh requested Khanh Hoa province to mobilize the entire political system to focus on site clearance and migration, and directly the Provincial Party Secretary must closely direct and support ministries and branches.
The Prime Minister especially emphasized the need to do a good job of resettlement for people in the project area according to the principle of ensuring that the new place of residence is at least equal to or better than the old place of residence; quickly stabilize people's lives and ensure the legitimate and legal rights and interests of the people; at the same time, propose policies to support people in converting their careers and occupations to competent authorities.
Ministries, branches and agencies, according to their functions and tasks, coordinate in handling recommendations from the Khanh Hoa Provincial People's Committee on mechanisms to implement projects of migration, resettlement, and site clearance for nuclear power plant projects.