Doing procedures in parallel to speed up the progress of social housing

Phan Anh |

The company believes that carrying out procedures in parallel with construction can speed up the progress of social housing projects (NOXH).

Speed up progress from actual implementation

Sharing at the National Online Conference on removing difficulties and obstacles, promoting the development of social housing chaired by Prime Minister Pham Minh Chinh, a representative of Phu Cuong Group said that this enterprise used to be the investor of a social housing apartment project in Ho Chi Minh City with a scale of 1,271 apartments.

Thanks to the optimization of the implementation process, the project only took 4 months to complete legal procedures and was completed after 18 months of construction and handover of the house within 2 years.

This is considered one of the projects with the fastest implementation progress in Ho Chi Minh City, and is highly appreciated for its quality and is on the list of typical social housing projects of Ho Chi Minh City Police.

Recently, Ho Chi Minh City has shown a strong determination in promoting the development of social housing. The city organizes many working sessions, listening to the opinions of businesses to remove difficulties, creating more favorable conditions for projects to be implemented quickly.

A representative of Phu Cuong Group emphasized that the timely participation of management agencies has helped the enterprise have more motivation and determination in implementing social housing projects.

Doanh nghiep cho rang, viec lam thu tuc song song voi thuc hien du an se giup rut ngan thoi gian trien khai, day nhanh tien do xay dung va som dua nha o xa hoi vao su dung. Anh: Huu Chanh
The company believes that carrying out procedures in parallel with project implementation will help shorten implementation time, speed up construction progress and soon put social housing into use. Illustrative photo: Huu Chanh

Need for an open mechanism and synchronous policies

Despite their desire to invest heavily in the social housing segment in Ho Chi Minh City, real estate businesses still face many difficulties due to limited land funds and many abandoned land plots due to legal problems.

According to the representative of Phu Cuong Group, to remove this bottleneck, there need to be many harmonious policies, mechanisms, solutions, and lightly streamlined procedures: "Staur the Ministry of Construction to submit to the Government to get a pilot project with quick procedures".

In addition, a proposal that received much attention was the need to carry out legal procedures in parallel with the project implementation process. This will significantly reduce waiting time, ensure implementation progress, thereby helping to increase the supply of social housing effectively.

"If the Government, banks and businesses are all in agreement, we can not only do it but also do it better and faster, bringing real benefits to society" - Phu Cuong Group representative affirmed.

The conference also recognized many contributions from many businesses and experts to remove obstacles and speed up the implementation of social housing projects.

These recommendations not only help remove obstacles that are hindering the implementation of social housing, speed up the progress of projects, but also create motivation to promote the real estate market to develop sustainably, ensuring a housing supply suitable for the needs of low-income workers.

Phan Anh
TIN LIÊN QUAN

Proposal for social housing buyers to borrow 25 years with fixed interest

|

The company believes that 100% of countries that are successful in building social housing have a 25-year lending policy with a fixed interest rate.

Opportunity to buy a house when Vingroup builds 500,000 social housing units

|

Vingroup Corporation has registered to build 500,000 social housing units by 2030.

Abolish the thinking of banning when you can't manage it in law-making

|

Head of the Central Internal Affairs Commission Phan Dinh Trac emphasized the spirit of resolutely abandoning the thinking of "if you can't manage, then ban" in law-making.

Big fire at scrap yard in Buon Ma Thuot city

|

Dak Lak - A major fire broke out at a scrap, soap, and waste collection site in Buon Ma Thuot city.

Explaining the hot scene amid bombs and bullets in the movie Geography

|

There are many questions and different explanations for the hot scene at the end of the film Tunnel: Sun in the dark by director Bui Thac Chuyen.

The Russian budget faces a storm

|

Russian Urals are sliding to $50 a barrel, could seriously weigh on Moscow's budget.

Bac Lieu province plans to have 32 communes after the arrangement

|

Bac Lieu - Bac Lieu province has 64 communes, wards and towns, and it is expected to reduce to 32 communes and wards after the arrangement.

With enough conditions to buy social housing, people are still struggling with procedures

|

Hanoi - Although meeting all the conditions, many people still cannot buy social housing due to a series of procedures.

Proposal for social housing buyers to borrow 25 years with fixed interest

Xuyên Đông |

The company believes that 100% of countries that are successful in building social housing have a 25-year lending policy with a fixed interest rate.

Opportunity to buy a house when Vingroup builds 500,000 social housing units

Phan Anh |

Vingroup Corporation has registered to build 500,000 social housing units by 2030.

Abolish the thinking of banning when you can't manage it in law-making

Vương Trần |

Head of the Central Internal Affairs Commission Phan Dinh Trac emphasized the spirit of resolutely abandoning the thinking of "if you can't manage, then ban" in law-making.