Developing a plan to enforce land recovery for industrial park projects in Hai Phong

Hoàng Khôi |

On April 5, Thuy Nguyen City (Hai Phong) had a dialogue and mobilized the handover of the site for the VSIP Hai Phong Urban, Industrial and Service Area Construction Investment Project.

The Land Acquisition Enforcement Board under Decision No. 2595/QD-UBND dated April 2, 2025 of the Chairman of Thuy Nguyen City People's Committee will dialogue to mobilize households and individuals to comply with the handover of land to implement the VSIP Hai Phong Urban, Industrial and Service Area Construction Investment Project in the wards of An Lu, Thuy Ha, Lap Le.

According to the report of Thuy Nguyen City People's Committee, in the process of implementing compensation and site clearance for the project, Thuy Nguyen City People's Committee has taken steps in accordance with the correct procedures; dialogue and mobilize households to comply with the handover of the site.

However, up to now, 2 households in Lap Le ward, 4 households in An Lu ward, 41 households in Thuy Ha ward have not complied and handed over the site to implement the project.

At the dialogue, representatives of households expressed their agreement with the state's land acquisition policy and continued to have opinions and recommendations on compensation unit prices, resettlement support, etc. In the spirit of publicity and democracy, the city leaders directly explained and responded to the recommendations of households on the basis of comparing them with the provisions of law.

Concluding the dialogue, Mr. Nguyen Van Vien, Vice Chairman of Thuy Nguyen City People's Committee, said: The VSIP Hai Phong Urban, Industrial and Service Area Construction Investment Project is a key project, implementing the socio-economic development tasks of Hai Phong. The application of unit prices, compensation and support plans, and resettlement consideration are all implemented in accordance with the provisions of law and the decision of the Hai Phong City People's Committee.

The leader of Thuy Nguyen City also said that this is the last dialogue before implementing the compulsory land recovery according to regulations. Therefore, it is recommended that the People's Committees of wards, departments, branches and organizations involved continue to propagate and mobilize, as well as hope that households will agree on the compensation and support plan; voluntarily hand over the site no later than April 15.

After this dialogue, localities coordinated with the Department of Natural Resources and Environment to publicize cases that must comply with the handover of land for project implementation through the local loudspeaker system. At the same time, they will post relevant legal information and knowledge at the headquarters and workplace for the people to grasp.

The Department of Natural Resources and Environment submitted a compulsory plan, asked for opinions from the city's departments and branches, completed the dossier and reported to the Hai Phong City Party Committee. For cases where households and individuals still do not hand over the land within the prescribed time limit, it is expected that land will be forcibly reclaimed in April 2025.

Hoàng Khôi
TIN LIÊN QUAN

Hai Phong welcomes the first test ship of MSC

|

On April 5, TIL Hai Phong International Port Company Limited (HTIT) welcomed the first trial ship of Mediterranean Shipping Company S.A (MSC).

Site clearance progress for a project worth nearly 147 billion VND in Hai Phong

|

Duong Kinh District, Hai Phong has just completed the enforcement, basically handing over the site for the Hai Phong road construction investment project worth nearly 147 billion VND.

Mr. Trump sends more letters to many countries, promotes tariff agreements

|

President Trump continues to put trade pressure on many countries with letters announcing new tax rates expected to be applied.

Difficulty in clearing the channel to 2 fishing ports that are silted up, boats stranded

|

Ha Tinh - The channel to Thach Kim Fishing Port and Cua Nhuong Fishing Port is silted up, causing ships and boats to strand when the tide goes down.

Director of Hanoi Police issues request to the new commune-level police

|

The Director of Hanoi Police requested the new commune-level police to be closer to the people, closer to the people, and take the people's satisfaction as the target.

Minister of National Defense chaired the Conference on handover of the position of Commander of Military Region 7

|

HCMC - On July 9, General Phan Van Giang, Politburo member, Deputy Secretary of the Central Military Commission, Minister of National Defense chaired the Conference to hand over the position of Commander of Military Region 7.

Hanoi sets out the principles for arranging commune-level cadres and civil servants

|

Hanoi - The arrangement of commune-level civil servants and public employees is carried out according to the principle of maintaining existing staff, allocating them in accordance with job positions and training levels.

A series of precious artifacts were excavated at the thousand-year-old Lieu Coc Joint Tower in Hue

|

HUE - Excavation of phase 2 of Lieu Coc twin towers reveals many special architectural and historical values, opening the way for research on Champa cultural conservation in Hue.

Hai Phong welcomes the first test ship of MSC

Mai Dung |

On April 5, TIL Hai Phong International Port Company Limited (HTIT) welcomed the first trial ship of Mediterranean Shipping Company S.A (MSC).

Công an phường tuần tra, bắt đối tượng tàng trữ ma túy ở Hải Phòng

Hoàng Khôi |

Chiều 5.4, Công an TP Hải Phòng thông tin, Công an phường Lê Lợi (An Dương) vừa bắt giữ đối tượng tàng trữ 0,62 gram heroin trong quá trình tuần tra.

Site clearance progress for a project worth nearly 147 billion VND in Hai Phong

Hoàng Khôi |

Duong Kinh District, Hai Phong has just completed the enforcement, basically handing over the site for the Hai Phong road construction investment project worth nearly 147 billion VND.