Thanh Xuan Ward has not completed site clearance for Nguyen Tuan street project

SÓNG HỮU |

Hanoi - The Nguyen Tuan road expansion project (Thanh Xuan ward) is facing a 2-story apartment building related to 6 households.

According to Lao Dong's records in mid-January 2026 at the project to renovate and expand Nguyen Tuan street (Thanh Xuan ward, Hanoi), the contractor has completed the asphalt concrete section of the road surface from alley 162 Nguyen Tuan to Nguyen Huy Tuong intersection, with a length of nearly 250m.

The expanded route section helps people travel more conveniently. However, some super-thin structures appear here, causing unsightliness.

The remaining section from Nguyen Huy Tuong intersection to the intersection with Nguyen Trai street is under construction.

a
Nguyen Tuan street, the section from alley 162 to Nguyen Huy Tuong intersection, with a length of nearly 250m has been expanded. Photo: Song Huu
a
Sidewalk paving stones are gathered on Nguyen Tuan street. Photo: Song Huu
a
Workers constructing project items. Photo: Song Huu
a
Series of super-thin houses appear on Nguyen Tuan street. Photo: Song Huu

Regarding the project to renovate and expand Nguyen Tuan street, in an exchange with Lao Dong Newspaper, the leader of the Investment - Infrastructure Project Management Board of Thanh Xuan ward said that the project is still stuck with the site of a 2-story collective house at address No. 35A Nguyen Tuan, involving 6 households.

Currently, the land price has been approved and the ward is applying for resettlement housing prices from the Department of Construction. After the resettlement housing price is available, we will publicize the plans and try to approve them in February 2026. If people do not support it, the ward will continue to implement the prescribed steps" - said the leader of the Investment - Infrastructure Project Management Board of Thanh Xuan ward.

Leaders of the Project Management Board also said that the construction contract was signed between the investor and the contractor until the end of March 2026.

a
2-story apartment building has not been cleared for expansion of Nguyen Tuan street. Photo: Song Huu
a
There are 6 households living in apartment building No. 35A Nguyen Tuan street. Photo: Song Huu

The project to renovate and expand Nguyen Tuan street was approved by the People's Committee of Thanh Xuan district (old) in 2018.

The project is 720m long, the starting point intersects with Nguyen Trai street, the ending point reaches alley 162 Nguyen Tuan, the cross-section is expanded to 21m, including a 15m wide road surface and 2 sidewalks each side 3m wide.

The project encountered obstacles in the implementation process, when many households did not agree to hand over the site, and at the same time there were many complaints related to the project.

a
Overview of the Nguyen Tuan road expansion project. Photo: Song Huu
a
The beginning of the route is under construction for expansion. Photo: Song Huu
a
Construction materials gathered at the project construction site. Photo: Song Huu
a
The Nguyen Tuan road expansion project (Thanh Xuan ward) is expected to be completed in the first quarter of 2026. Photo: Song Huu

After many times of local propaganda, mobilization and dialogue, by November 2024, most households had handed over land for the project.

From July 1, 2025, after being operated by the 2-level government, the Nguyen Tuan road expansion project will be transferred to Thanh Xuan Ward People's Committee as the investor.

SÓNG HỮU
RELATED NEWS

Hanoi deploys digital technology park project with an area of nearly 200ha

|

Hanoi - On the morning of January 16, the Digital and Mixed Technology Park project was started, aiming to create new growth momentum from science and technology.

Hanoi to recover land for 600 households in the center to open a 40m wide road

|

Hanoi - About 600 cases of organizations and households in Thanh Xuan ward will have their land recovered to build Ring Road 2.5 section 0.95km long, cross-section 40m.

Current status of super-thin houses on Nguyen Tuan Street expansion waiting for handling solutions

|

Hanoi - Super thin works with an area of 68m2 on the expanded Nguyen Tuan Street are waiting for the authorities to come up with a direction for handling in accordance with the law.

Hanoi photography studio is in high demand with white ao dai and red flag with yellow star concepts on the occasion of April 30

|

Hanoi - During the April 30th holiday, many photo shops recorded increased customers as the concept of white ao dai and red flag with a yellow star became a trend loved by young people.

Public non-business units continue to be streamlined in Q2/2026

|

One of the important tasks in the second quarter of 2026, the Ministry of Home Affairs will continue to advise on streamlining public non-business units.

Ho Chi Minh City simultaneously starts construction of 4 projects with a total capital of 142,000 billion VND

|

Ho Chi Minh City - This morning (April 29), Ho Chi Minh City held a groundbreaking ceremony for 4 projects with a total capital of 142,000 billion VND and awarded investment certificates for the Can Gio International Transshipment Port project.

Hanoi deploys digital technology park project with an area of nearly 200ha

Phương Anh |

Hanoi - On the morning of January 16, the Digital and Mixed Technology Park project was started, aiming to create new growth momentum from science and technology.

Hanoi to recover land for 600 households in the center to open a 40m wide road

SÓNG HỮU |

Hanoi - About 600 cases of organizations and households in Thanh Xuan ward will have their land recovered to build Ring Road 2.5 section 0.95km long, cross-section 40m.

Current status of super-thin houses on Nguyen Tuan Street expansion waiting for handling solutions

Tùng Giang |

Hanoi - Super thin works with an area of 68m2 on the expanded Nguyen Tuan Street are waiting for the authorities to come up with a direction for handling in accordance with the law.