Hanoi to recover land for 600 households in the center to open a 40m wide road

SÓNG HỮU |

Hanoi - About 600 cases of organizations and households in Thanh Xuan ward will have their land recovered to build Ring Road 2.5 section 0.95km long, cross-section 40m.

Hanoi Ring Road 2.5 has a total length of about 19.64km, planned width of 40-50m. Starting point in Ciputra New Urban Area, ending at the intersection with Ring Road 3 (section near Thanh Tri bridge).

To date, Ring Road 2.5 has been put into use 5/13 sections with a length of 11.28km. The Ministry is implementing 8/13 sections with a length of more than 8km.

Regarding the Ring Road 2.5 project, Politburo Member, Secretary of the Hanoi City Party Committee Nguyen Duy Ngoc requested the Party Committee and City People's Committee to direct the City People's Committee, departments, branches, and the City Traffic Construction Investment Project Management Board; Party committees and ward authorities must clearly define political responsibilities to complete site clearance (GPMB) and complete the entire project in 2026.

In the 8 sections being implemented, Thanh Xuan ward is assigned to be the investor of the compensation and support component project, technical infrastructure works in the Nguy Nhu Kon Tum - Nguyen Trai section.

The route section is about 0.95km long, with a cross-section of 40m.

Preliminary statistics show that there are about 600 cases including organizations, households and individuals subject to land acquisition and site clearance for project implementation, with a total land acquisition area of about 39,059m2.

The cost of site clearance is about 3,686 billion VND, from the city budget.

To meet the urgent requirements of the project, in the early days of 2026, Thanh Xuan Ward People's Committee issued a land recovery plan to implement the Ring Road 2.5 project, Nguy Nhu Kon Tum - Nguyen Trai section.

In January 2026, functional forces will conduct land recovery notices, and at the same time conduct surveys, measurements, inventory and verification of land and population contents, thereby classifying dossiers to have handling directions.

In February 2026, the ward will focus on preparing, publicizing and approving compensation, support and resettlement plans.

The peak is March 2026, when local authorities will proceed to pay compensation, arrange housing and land funds for resettlement, issue decisions to recover land and receive land handover, and be ready to enforce coercion for non-compliance cases.

To ensure the feasibility of this "drawdown" progress, the plan clearly states the application of specific mechanisms and policies according to the Capital Law 2024 and new National Assembly Resolutions such as Resolutions 254 and 258 in 2025.

The principle of implementation is thoroughly grasped according to the motto "6 clears", including clear people, clear tasks, clear authority, clear responsibilities, clear time and clear results. In particular, the process of preparing compensation plans will be carried out in a "rolling" and chained manner: wherever the dossier is completed, plans will be prepared immediately to save time.

Besides the drastic progress, the work of ensuring social security and order is also focused on. The Ward People's Committee assigned the Department of Economy, Infrastructure and Urban Affairs to preside over the review and advising on handling cases of "super-thin, super-skewed" houses or architectural problems arising after the clearance.

At the same time, the Ward Police force will develop a plan to ensure security and order throughout the process from people's meetings, payment of money to coercive land recovery if necessary, resolutely preventing the emergence of complicated "hot spots" in the area.

The completion of site clearance for this Ring Road 2.5 section is of great significance in removing traffic bottlenecks in the Thanh Xuan area, contributing to completing the framework traffic network of Hanoi Capital.

It's a bit of a bit of a bit of a bit of a bit of a bit.

SÓNG HỮU
RELATED NEWS

Hanoi handles hotspots for site clearance of Ring Road 2.5 project

|

Hanoi launches ground clearance for Ring Road 2.5 project, section passing through Xuan Dinh ward, removing bottlenecks that have existed for many years.

Receiving compensation for more than 20 years but not yet handing over land for Ring Road 2.5

|

Hanoi - Khuong Dinh Ward People's Committee requests households that have received compensation money since 2003 to hand over land for Ring Road 2.5 project before January 26, 2026.

Accelerate site clearance for Ring Road 2.5 Nguyen Trai - Dam Hong section

|

Hanoi - Khuong Dinh Ward is implementing land acquisition and site clearance to implement the Ring Road 2.5 project, Nguyen Trai - Dam Hong section.

Many households do not comply with the direction on the Ring Road 2.5 project

|

Hanoi - Many households have not terminated or stopped leasing or lending houses and land within the Ring Road 2.5 project area as directed by Cau Giay ward.

Da Nang people celebrate Tet in the warm home of Quang Trung Campaign

|

Da Nang - The wooden house of Mr. Nguyen Dinh (Thuong Duc commune) swept away by floods has been replaced by a solid shelter during the Quang Trung Campaign.

Forecast of low pressure combined with extremely strong cold air coming soon

|

Extremely strong cold air is forecast to be coming down, in the context of 2 consecutive low pressures expected to appear near the East Sea.

The truth about Venezuela hiding 60 billion USD of Bitcoin

|

Rumors that Venezuela may hold up to 60 billion USD of Bitcoin are spreading, but experts believe that this number is still a big question mark.

National Highway 279 will be the axis of the new administrative center of Quang Ninh province

|

The Chairman of Quang Ninh Provincial People's Committee requested departments, agencies, branches, and localities to focus on preparing for the construction of a new Administrative Center area.

Hanoi handles hotspots for site clearance of Ring Road 2.5 project

Minh Hạnh |

Hanoi launches ground clearance for Ring Road 2.5 project, section passing through Xuan Dinh ward, removing bottlenecks that have existed for many years.

Receiving compensation for more than 20 years but not yet handing over land for Ring Road 2.5

SÓNG HỮU |

Hanoi - Khuong Dinh Ward People's Committee requests households that have received compensation money since 2003 to hand over land for Ring Road 2.5 project before January 26, 2026.

Accelerate site clearance for Ring Road 2.5 Nguyen Trai - Dam Hong section

SÓNG HỮU |

Hanoi - Khuong Dinh Ward is implementing land acquisition and site clearance to implement the Ring Road 2.5 project, Nguyen Trai - Dam Hong section.

Many households do not comply with the direction on the Ring Road 2.5 project

SÓNG HỮU |

Hanoi - Many households have not terminated or stopped leasing or lending houses and land within the Ring Road 2.5 project area as directed by Cau Giay ward.