Sa Pa removes site obstacles for 910 billion VND administrative center project

Đinh Đại |

Lao Cai - Sa Pa is focusing on removing obstacles in site clearance, accelerating the progress of the new administrative center project with a total capital of more than 910 billion VND.

On April 7, information from Sa Pa Ward People's Committee, the unit just worked with the Provincial Construction Investment Project Management Board to review the progress and remove difficulties in land acquisition, compensation and site clearance for the new administrative center project.

Attending the working session were Mr. To Ngoc Lien - Chairman of the Ward People's Committee; Mr. Dinh Van Dang - Director of the Provincial Construction Investment Project Management Board; along with representatives of professional departments and related units.

The new Administrative Center Area project was approved in 2018, with a total investment of more than 910 billion VND, the initial planning scale of 64 hectares, after adjustment it is 61.4 hectares.

Phường Sa Pa có buổi làm việc với Ban Quản lý Dự án Đầu tư  Xây dựng tỉnh Lào Cai về công tác thu hồi, bồi thường, giải phóng mặt bằng dự án Khu trung tâm hành chính mới. Ảnh: Đơn vị cung cấp
Sa Pa Ward has a working session with the Lao Cai Provincial Construction Investment Project Management Board on the work of recovering, compensating, and clearing ground for the new administrative center area project. Photo: Provider

Within the project scope, there are 84 households, individuals and 5 organizations, the actual area to be recovered is about 55.4 ha.

According to the report at the working session, some items have changed. For the HC1 road, decisions have been issued to recover land for 3 organizations and 3 households; of which 3 households and 2 organizations have received money and handed over the site for construction.

However, the overall progress still faces many obstacles. Some locations are still stuck in determining the origin of land, developing compensation plans and creating consensus from the people. This is identified as the main "bottleneck" affecting the progress of clear site handover.

At the meeting, the parties agreed that it is necessary to accelerate the determination of specific land prices as a basis for compensation and support. The Economic, Infrastructure and Urban Department of Sa Pa Ward is requested to soon advise on residential land price plans.

Trụ sở hành chính mới của Sa Pa đã hoàn thiện phần thô phía ngoài. Ảnh: Đinh Đại
The new administrative headquarters of Sa Pa has completed the rough exterior. Photo: Dinh Dai

At the same time, the Lao Cai Provincial Construction Investment Project Management Board is considering extending the project implementation time to suit the actual situation.

Local authorities emphasized that they will continue to strengthen propaganda and mobilize people to agree, coordinate inventory, receive compensation, and soon hand over the site.

The goal is to gradually remove obstacles, accelerate progress, and create a clean land fund to deploy the new Administrative Center according to the plan.

Đinh Đại
RELATED NEWS

Workers travel through cold mist to accelerate traffic projects in Sa Pa

|

Lao Cai - In the cold weather, fog covering the highlands, many workers are still diligently constructing on the road to Thac Bac tourist area.

Sa Pa airport continues to be motionless after 4 years of groundbreaking

|

Lao Cai - 4 years after the groundbreaking ceremony in March 2022, the progress of the Sa Pa airport project (Sa Pa Airport) has not changed much.

Improving the progress of the hundred-billion-dong administrative headquarters in Sa Pa

|

Lao Cai - After many years of construction, the headquarters of the administrative agencies of Sa Pa ward with an investment capital of nearly 200 billion VND has gradually emerged.

Chairwoman Bui Thi Minh Hoai sends congratulatory letter to Khmer ethnic people

|

On the occasion of the Chol Chnam Thmay Tet of the Khmer ethnic people in 2026, Politburo Member, Secretary of the Party Central Committee, Chairman of the Central Committee of the Vietnam Fatherland Front Bui Thi Minh Hoai sent congratulatory letters to the monks, Achar and all Khmer ethnic people.

More than 40 elementary school students in Ho Chi Minh City vomiting, symptoms of digestive disorders

|

Ho Chi Minh City - 41 students of Binh Quoi Tay Elementary School showed symptoms of digestive disorders and went for examination, including 3 cases requiring hospitalization.

Justice and civil status officials at the commune level are very thin, in many places there is only one person

|

The Chairman of the Law and Justice Committee stated the reality that the team of justice and civil status officials at the commune level is very thin, and in many places there is only one official, which needs to be strengthened.

From 2027, hospitals will stop using paper medical records

|

More than 75% of hospitals have implemented electronic medical records, aiming to completely abolish paper medical records from 2027.

Forecast of the possibility of a tropical depression strengthening into a storm entering the East Sea

|

It is forecast that the tropical depression in the Northwest Pacific has the potential to strengthen into a storm but is unlikely to enter the East Sea.

Workers travel through cold mist to accelerate traffic projects in Sa Pa

Đinh Đại |

Lao Cai - In the cold weather, fog covering the highlands, many workers are still diligently constructing on the road to Thac Bac tourist area.

Sa Pa airport continues to be motionless after 4 years of groundbreaking

Đinh Đại |

Lao Cai - 4 years after the groundbreaking ceremony in March 2022, the progress of the Sa Pa airport project (Sa Pa Airport) has not changed much.

Improving the progress of the hundred-billion-dong administrative headquarters in Sa Pa

Đinh Đại |

Lao Cai - After many years of construction, the headquarters of the administrative agencies of Sa Pa ward with an investment capital of nearly 200 billion VND has gradually emerged.