Progress of site clearance for Tien Lang 1 industrial park project, Hai Phong

Hoàng Khôi |

Hai Phong - It is expected that by August 2026, the Tien Lang 1 Industrial Park project will complete the surveying and drawing, and make survey drawings on the entire area.

The Project to Invest in Construction and Business of Infrastructure of Tien Lang 1 Industrial Park, invested by Asia Pacific Sustainable Green Development Joint Stock Company, is being built in Hung Thang commune, Hai Phong city.

The project has a scale of 596.78 ha, with a total investment of: 13,061 billion VND. Project implementation progress: Phase 1 (Zone A, area 416.06 ha): Deploying site clearance and infrastructure construction from the first quarter of 2026 to the second quarter of 2028, starting business from 2027; Phase 2 (Zone B, area 180.72 ha): Deploying site clearance and infrastructure construction from the 4th quarter of 2027 to 2031, starting business from 2029.

According to the investor's report, by June 3, the investor will carry out surveying and making cadastral extracts to serve site clearance work. It is expected that by August 2026, the surveying and drawing and making extracts will be completed on the entire project area.

For area A with an area of more than 137 ha, related to 7 villages with a total of 983 land plots of 635 households. Up to now, the consulting unit has coordinated with the Commune People's Committee and villages to complete external surveying and review internal records. The confirmation of completed area for 591/635 households has reached about 93%. For area B with an area of 435.52 ha, the consulting unit is simultaneously deploying surveying and preparing cadastral extracts in 11 villages within the project scope. It is expected that in June, the unit will complete external surveying and internal records; in July and mid-August, complete the review and confirmation of area with related households.

Regarding the progress of infrastructure construction, according to the plan, from January 2027, construction units will deploy leveling of area A on an area of about 93 hectares out of a total of 137.5 hectares allocated land, with a total leveling volume of about 3.2 million m3, the expected construction time is 18 months. The main road of area A will be constructed in 8 months. From April 2027, the investor will deploy the construction of an internal traffic road system with a construction time of about 12 months.

Along with that, the project will build a clean water plant with a capacity of 20,000 m3/day and night, expected to be put into operation from April 2028; a wastewater treatment plant with a capacity of 3,500 m3/day and night will be started in June 2027 and put into operation from June 2028.

Inspecting the project progress, representatives of the Hai Phong Economic Zone Management Board requested units to focus highly, proactively coordinate to remove difficulties, accelerate the progress of surveying, complete dossiers, and prepare necessary conditions to deploy site clearance and infrastructure construction investment according to the set plan. Thereby, contributing to early putting the industrial park into operation, creating motivation to promote socio-economic development in the southern area of the city.

Hoàng Khôi
RELATED NEWS

Site clearance for high-speed railway project in Ninh Binh faces difficulties due to relics

|

Ninh Binh - Site clearance for the high-speed railway project section passing through the province is facing difficulties because the project's route passes through some relic works.

Launching a model of a drug-free industrial park in Hai Phong

|

Hai Phong - On June 3, Thien Huong Ward People's Committee held a launching ceremony and signed an emulation agreement to implement the model "Nam Cau Kien Industrial Park without drugs".

Hai Phong operates 2-level government effectively, 99.82% of dossiers on schedule

|

Hai Phong - On June 2nd, Hai Phong City held a preliminary review of one year of operating the overall organizational model of the political system and the 2-level local government model.

Proposing 2 more days off on National Day

|

Union members, workers and trade union organizations proposed considering and adding 2 more holidays on National Day.

The mark of a female Trade Union leader in a business in Gia Lai

|

At the grassroots trade union, Huynh Thi Thanh Hoa - Chairwoman of the grassroots trade union of Gia Lai Education Development Investment Printing Joint Stock Company (Thong Nhat Ward Trade Union) made efforts to build many clauses that benefit workers, difficult circumstances, and sick people who are wholeheartedly helped and shared by the Trade Union.

Creating motivation for workers to emulate creative labor, improving labor productivity

|

The Trade Union of Vietnam National Energy Industry Group (Petrovietnam Trade Union) always encourages, cares for, protects and encourages; creates motivation for workers to preserve the tradition of "people seeking fire", nurture aspirations, constantly emulate, study, train, and improve their qualifications.

Hai Phong City Trade Union: From equipping free wifi to improving the spiritual life of workers

|

Recently, 90 worker dormitories in Hai Phong City were equipped with free wireless Internet access systems, bringing joy to thousands of migrant workers.

More than 13,500 Vinh Long workers join the Trade Union organization

|

In the first 6 months of 2026, Vinh Long province's trade union levels developed more than 13,500 new union members, reaching over 51% of the annual plan, affirming the attraction from practical benefits for workers.

Site clearance for high-speed railway project in Ninh Binh faces difficulties due to relics

NGUYỄN TRƯỜNG |

Ninh Binh - Site clearance for the high-speed railway project section passing through the province is facing difficulties because the project's route passes through some relic works.

Launching a model of a drug-free industrial park in Hai Phong

Hoàng Khôi |

Hai Phong - On June 3, Thien Huong Ward People's Committee held a launching ceremony and signed an emulation agreement to implement the model "Nam Cau Kien Industrial Park without drugs".

Hai Phong operates 2-level government effectively, 99.82% of dossiers on schedule

Hoàng Khôi |

Hai Phong - On June 2nd, Hai Phong City held a preliminary review of one year of operating the overall organizational model of the political system and the 2-level local government model.