Ho Chi Minh City plans to spend more than 9,800 billion VND to recover land for Ben Thanh - Can Gio Metro

MINH QUÂN |

Ho Chi Minh City plans to spend more than 9,800 billion VND to recover land, compensate, support and resettle for 510 households and 17 organizations to implement the Ben Thanh - Can Gio Metro project.

The Ho Chi Minh City Urban Railway Management Board (MAUR) has just submitted a report to the Ho Chi Minh City Department of Agriculture and Environment requesting appraisal of the feasibility study report of the compensation, support, and resettlement project serving the Ben Thanh - Can Gio Metro line.

The Ben Thanh - Can Gio Metro line is about 53.8 km long, starting point at Ben Thanh station (9/23 Park) and ending point at Can Gio Depot on a land area of about 39 hectares in Can Gio commune.

The project passes through the wards of Ben Thanh, Khanh Hoi, Xom Chieu, Tan Thuan, Tan My and the communes of Nha Be, Binh Khanh, An Thoi Dong, Can Gio.

This metro line was started on December 19, 2025 under the BOO (build - own - operate) contract form, with a total investment of more than 102,000 billion VND arranged by the investor.

Specifically, compensation, support and resettlement for the project will be undertaken by the Ho Chi Minh City budget, with a total investment of about 9,834 billion VND.

The total affected land area is about 153.8 ha. There are about 510 affected cases, including 418 cases of partial clearance and 92 cases of full clearance. In addition, there are 17 organizations affected by land acquisition.

In which, Binh Khanh commune is the locality with the most affected households with 187 households and 1 organization. Nha Be commune has 170 households and 3 organizations affected; An Thoi Dong commune has 92 households and 1 organization; Can Gio commune has 26 households and 5 organizations.

In the inner city area, Tan Thuan ward has 27 households and 2 organizations affected; Xom Chieu ward has 8 households; Tan My ward has 5 organizations in the land acquisition area.

Metro Bến Thành - Cần Giờ sẽ kết nối với ga ngầm Bến Thành tuyến Metro số 1. Ảnh: Minh Quân
Ben Thanh - Can Gio Metro will connect with Ben Thanh underground station, Metro Line 1 HCMC. Photo: Minh Quan

According to MAUR, the compensation, support, and resettlement project serving the Ben Thanh - Can Gio Metro line has met the conditions to submit to specialized agencies and competent authorities for appraisal and approval according to regulations.

MAUR requests the Department of Agriculture and Environment to consider and appraise to submit to the Ho Chi Minh City People's Committee for approval the feasibility study report dossier, as a basis for implementing the next steps.

At the same time, MAUR also proposed that departments and branches advise the Ho Chi Minh City People's Committee to arrange a resettlement apartment fund for affected households to ensure housing, create favorable conditions for site clearance and stabilize social security.

According to the plan, in June 2026, Ho Chi Minh City will complete the preparation, appraisal and approval of compensation, support, and resettlement projects.

The work of land acquisition, compensation and resettlement is strived to be completed to hand over the site to investors in the fourth quarter of 2026. The relocation of affected technical infrastructure works must also be completed before this time.

Ben Thanh - Can Gio Metro is expected to be completed in 2028. When put into operation, the metro line will shorten the travel time from the center of Ho Chi Minh City to Can Gio to about 13 minutes, contributing to the formation of a large-volume public transport axis and promoting socio-economic development in the southern area of the city.

MINH QUÂN
RELATED NEWS

Ho Chi Minh City approves Ben Thanh - Can Gio Metro line plan

|

Ho Chi Minh City - Ben Thanh - Can Gio Metro passes through the buffer zone of Can Gio Biosphere Reserve, not going into the core zone to limit impact on the ecological environment.

Ben Thanh - Can Gio Metro broke ground, expected to be completed by the end of 2028

|

Ho Chi Minh City - The Ben Thanh - Can Gio Metro Line is more than 54 km long, with a total capital of more than VND102,000 billion, expected to be completed in the fourth quarter of 2028.

Ben Thanh - Can Gio Metro changes starting point to avoid affecting relics around Ben Thanh Market

|

Ho Chi Minh City - The Ben Thanh - Can Gio Metro Line will move the entrance to the 23/9 Park to avoid affecting the relics around Ben Thanh Market.

The 14th Vietnam Trade Union Congress takes place from June 3-5, 2026

|

The 14th Vietnam Trade Union Congress, term 2026-2031, takes place from June 3-5 at the National Convention Center, Hanoi City.

The Prime Minister will exchange views with delegates at the 14th Vietnam Trade Union Congress

|

On the afternoon of May 29, the Vietnam General Confederation of Labour held a press conference to inform about the 14th Congress of Vietnam Trade Unions, term 2026-2031.

Deploying about 92 social housing development projects serving workers and students

|

Hanoi - In the afternoon of May 29, Mr. Vu Dai Thang, Member of the Party Central Committee, Deputy Secretary of the City Party Committee, Chairman of the Hanoi People's Committee, had a dialogue with workers.

Iran reactivates giant underground missile depot

|

CNN said Iran is quickly restoring access to submarine missile depots after recent attacks by the US and Israel.

Trillion-VND revenue, continuously reporting losses, game businesses in the sights of tax inspection

|

With trillions of VND in revenue but continuously reporting losses or slight profits, some game publishing businesses are subject to tax authorities' inspection in 2026.

Ho Chi Minh City approves Ben Thanh - Can Gio Metro line plan

MINH QUÂN |

Ho Chi Minh City - Ben Thanh - Can Gio Metro passes through the buffer zone of Can Gio Biosphere Reserve, not going into the core zone to limit impact on the ecological environment.

Ben Thanh - Can Gio Metro broke ground, expected to be completed by the end of 2028

MINH QUÂN |

Ho Chi Minh City - The Ben Thanh - Can Gio Metro Line is more than 54 km long, with a total capital of more than VND102,000 billion, expected to be completed in the fourth quarter of 2028.

Ben Thanh - Can Gio Metro changes starting point to avoid affecting relics around Ben Thanh Market

MINH QUÂN |

Ho Chi Minh City - The Ben Thanh - Can Gio Metro Line will move the entrance to the 23/9 Park to avoid affecting the relics around Ben Thanh Market.