Accordingly, to compete in the Long Phu 1 Thermal Power Plant Project to truly go into depth, closely linked to construction practice, Petrovietnam Trade Union has chosen the emulation theme "Innovation in thinking, creative action, fast speed, ensuring safety, achieving high efficiency".
In that spirit, Petrovietnam Trade Union and Long Phu 1 Project Management Board will build 8 specific emulation progress milestones, identified as important destinations in each stage.
Each milestone is both a commitment to responsibility and a motivation to arouse the spirit of creative competition, overcoming difficulties, daring to think, daring to do of the collective of cadres, engineers, and workers on the construction site.
Of the 8 progress milestones, progress milestone 1 is from June to November 2025 with the completion of selection and signing of BOP packages. Progress milestone 7, from March to September 2027 with the goal of burning fire for the first time in Group 1, washing chemicals, blowing out pipes, and putting air into turbines. Power generation and synchronization of compost No. 1. Progress mark 8 ends in December 2027, the goal is to set off the first fire of the 2nd Plant, wash chemicals, blow the furnace pipes, and put the steam into the turbine. Power generation, synchronization of compost No. 2.
The emulation content closely follows each stage and each construction item, promoting the spirit of "Solidarity - Creativity - fast speed - High efficiency". From the main construction site to each department, the competitive atmosphere spreads strongly, urging each collective and individual to act together for the common goal.
Each cadre, engineer and worker is encouraged to promote the spirit of initiative, creativity, daring to think, daring to do; constantly improving techniques, rationalizing processes, improving labor productivity, considering progress and quality of the project as an honor and pride of Petrovietnam workers.