Trade Union assists workers to bring electricity to Con Dao

PHƯƠNG ANH |

Soc Trang - Vietnam Electricity Trade Union visited, presented gifts, and gave encouragement to workers constructing the national grid project to Con Dao.

On June 17, the Vietnam Electricity Trade Union coordinated with the Soc Trang Provincial Labor Federation to organize a working delegation to visit, encourage and present gifts to union members and workers working on the Power Supply Project for Con Dao district (Ba Ria - Vung Tau province).

Doan cong tac tham, tang qua cho doan vien, cong nhan lao dong thi cong Du an cap dien cho huyen Con Dao (Ba Ria - Vung Tau). Anh: LDLD tinh Soc Trang
The working group visited and presented gifts to union members and workers working on the construction of the Power Supply Project for Con Dao district (Ba Ria - Vung Tau). Photo: Soc Trang Provincial Federation of Labor

The delegation was present in Vinh Chau town (Soc Trang province) where important items of the project are being implemented to visit the working and living conditions of workers and record the positive working spirit of the construction force in complex weather and terrain conditions.

On this occasion, the delegation presented gifts to 5 groups, with a total value of 110 million VND to encourage the spirit of working and sharing difficulties with the workforce.

Mot tru dien thuoc Du an cap dien cho huyen Con Dao dang duoc thi cong. Anh: LDLD tinh Soc Trang
A power pole under the Power Supply Project for Con Dao district is under construction. Photo: Soc Trang Provincial Federation of Labor

Previously, on March 8, Vietnam Electricity Group (EVN) coordinated with Vietnam Electricity Trade Union to organize a launching ceremony to compete in completing the construction progress goals of the National Power Grid Supply Project for Con Dao district (Ba Ria - Vung Tau province).

The project has a total investment of VND4,923 billion, expected to be completed and energized in 2025. The scale of the project includes a 110kV line of 103.7km long, including 17.5km of overhead line through Soc Trang, 77.7km of underground cables across the sea and 8.5km of underground cables on Con Dao island. The project also includes the expansion of Vinh Chau 220kV transformer station (Soc Trang) and the construction of a 110/22kV GIS transformer station in Con Dao.

Con Dao is a locality with a strategic position in terms of national defense, security and island sovereignty, and is also an important tourist destination. The current power system of the island district mainly relies on diesel with limited capacity (11.8 MW), not meeting the needs of socio-economic development. After completion, the project will supply power to Con Dao with a total capacity of about 29MW in 2026, 55MW in 2030 and 90MW in 2035.

PHƯƠNG ANH
TIN LIÊN QUAN

Resolving the problem of a series of broken 22kV power lines in Thanh Hoa

|

Thanh Hoa - After the thunderstorms that broke a series of power poles, the electricity industry urgently repaired them and restored power to the people.

Vietnam Electricity Trade Union encourages workers in remote areas

|

On the occasion of Workers' Month 2025, leaders of the Vietnam Electricity Trade Union came to present gifts to encourage workers of Power Transmission Company 2 (PTC2) and Quang Nam Power Transmission.

Morning in the West: Bringing national grid across the sea to Con Dao

|

Morning in the West 11.3: Opening of a hospital worth more than 2,300 billion in Can Tho; Durian garden adds to disease concerns; Bringing national grid power to Con Dao;...

Nearly 78 km of underground cables across the sea to pull the grid to Con Dao

|

Ba Ria - Vung Tau - The project to supply power to Con Dao by underground cable nearly 78 km long is being implemented. The island district will have national grid power in early September 2025.

Man suspected of falling from a high-rise apartment building in Long Bien

|

Hanoi After a loud noise, people discovered a man lying motionless on the ground, suspected of falling from a high floor of an apartment building.

Meritorious Artist Hoai Linh speaks out before a series of news of a rare disease and passed away

|

In the face of many negative rumors about him, Meritorious Artist Hoai Linh has responded.

Advising Vietnamese people to proactively leave Israel through road border gates

|

The Vietnamese Embassy in Israel recommends that people proactively leave Israel through the border gate, especially towards Jordan or Egypt.

Dak Nong Secretary speaks out about rumors of daughter being restructured to become commune leader

|

Dak Nong - Mr. Ngo Thanh Danh - Secretary of the Provincial Party Committee responded after rumors that daughters were restructured to become commune leaders.

Resolving the problem of a series of broken 22kV power lines in Thanh Hoa

QUÁCH DU |

Thanh Hoa - After the thunderstorms that broke a series of power poles, the electricity industry urgently repaired them and restored power to the people.

Vietnam Electricity Trade Union encourages workers in remote areas

Quang Thắng |

On the occasion of Workers' Month 2025, leaders of the Vietnam Electricity Trade Union came to present gifts to encourage workers of Power Transmission Company 2 (PTC2) and Quang Nam Power Transmission.

Morning in the West: Bringing national grid across the sea to Con Dao

Nhóm PV |

Morning in the West 11.3: Opening of a hospital worth more than 2,300 billion in Can Tho; Durian garden adds to disease concerns; Bringing national grid power to Con Dao;...

Nearly 78 km of underground cables across the sea to pull the grid to Con Dao

PHƯƠNG ANH |

Ba Ria - Vung Tau - The project to supply power to Con Dao by underground cable nearly 78 km long is being implemented. The island district will have national grid power in early September 2025.