Final sprint to complete border boarding schools in Tuyen Quang

Nguyễn Tùng |

Border boarding schools in Tuyen Quang province are racing to complete and put into use in the new school year.

At the beginning of May 2026, amidst intense hot weather, the construction site of the Thanh Thuy Inter-level Ethnic Minority Boarding School Project, Thanh Thuy commune, is still bustling with the sound of construction machinery.

Nearly 300 workers were divided into many teams, urgently completing construction items. After more than 6 months of construction, the excavation and foundation filling items and 12 main building blocks such as classrooms, administration buildings, and basic accommodation areas have been completed.

Currently, the contractor is focusing on completing the interior and exterior of the project; and at the same time deploying electricity, water and auxiliary works. The implemented volume has reached over 70%.

Representatives of the contractor - Mien Tay Co., Ltd. - said that the unit has mobilized maximum manpower and vehicles, organized "3 shifts, 4 teams" construction, striving to make the project the first inter-level boarding school in the province to be completed and put into use before August 30, 2026.

Dự án trường nội trú liên cấp Thanh Thủy đang được đẩy nhanh tiến độ, phấn đấu là trường về đích đầu tiên của tỉnh Tuyên Quang. Ảnh: Việt Bắc.
The Thanh Thuy Inter-level Boarding School project is being accelerated, striving to be the first school to reach the finish line in Tuyen Quang province. Photo: Viet Bac

Thanh Thuy Inter-level Boarding School project has a total investment of more than 211 billion VND on an area of 5.37ha. The project includes 31 classrooms, 15 subject rooms, 1 library, 25 office rooms, 198 boarding rooms for students and teachers and many auxiliary items, meeting the learning and living needs of more than 1,000 students.

To date, 17/17 inter-level boarding schools in border communes of Tuyen Quang province have been started. Among them, 6 projects started in 2025 are being focused on accelerating progress.

According to the Project Management Board for Construction Investment of Tuyen Quang province, among the schools starting construction in 2025, 2/6 projects are ahead of schedule and are expected to be completed and handed over earlier than planned.

For projects started in 2026, currently 1 project has been implemented; 10/11 remaining projects are in the process of appraisal and approval. Accumulated disbursement by the end of June 2026 is expected to reach 688 billion VND.

According to the investor, the project implementation process faced many difficulties due to complex terrain and geological conditions in many areas. Some projects had to adjust designs due to the risk of landslides. In addition, fluctuating prices of construction materials, fuel and transportation costs also affected the construction progress.

Typically, the Xin Man Boarding School Project, Xin Man commune - one of the projects facing many geological obstacles. During construction, the unit discovered a groundwater vein in the construction area, increasing the risk of foundation subsidence and taluy landslides behind the project.

Vượt khó khăn về địa hình, thời tiết, công tác thi công trường nội trú tại Tuyên Quang đang được đẩy nhanh. Ảnh: Việt Bắc.
Overcoming difficulties in terrain and weather, the construction of the dormitory in Tuyen Quang is being accelerated. Photo: Viet Bac

Talking to PV, Mr. Ta Quoc Tuan - Director of Dong Bac One Member Limited Liability Company, the construction unit of Xin Man Boarding School - said that due to complex geological conditions, the project must adjust the design and supplement technical solutions to ensure project safety.

Despite facing many difficulties in terrain and geology, we are determined to accelerate progress. At favorable locations, the unit has increased manpower and machinery to continuously construct," Mr. Tuan said.

At a working session with the Construction Investment Project Management Board and localities with projects, Ms. Vuong Ngoc Ha - Vice Chairwoman of Tuyen Quang Provincial People's Committee - requested contractors to review and clearly identify outstanding contents, promptly remove difficulties, and not affect the overall progress.

Local leaders are also requested to focus on reviewing all tasks in the area, especially procedures related to land and site clearance; and at the same time closely coordinate to create the most favorable conditions for investors and contractors in the project implementation process.

Nguyễn Tùng
RELATED NEWS

Groundbreaking ceremony for housing project for police forces in Tuyen Quang

|

Tuyen Quang - Housing project for the Police force in An Tuong ward with an area of 5.5 ha, scale of 822 apartments.

Creating consensus when arranging villages and residential groups in Tuyen Quang

|

With more than 85% of villages and residential groups in the area under arrangement, Tuyen Quang province is proactive, cautious and creating consensus when implementing.

Ready to start construction simultaneously of boarding schools in Tuyen Quang

|

Tuyen Quang - Preparations for the groundbreaking ceremony of 11 inter-level boarding schools for primary and secondary schools in border communes are being urgently implemented.

The numbers show that Elon Musk is incredibly rich

|

Elon Musk became the first person in the world to own more than 1,000 billion USD, with asset scale far exceeding what most people can imagine.

Pretty girl" Ngo Lan Huong: I studied at Foreign Trade University and once thought I would work in import and export

|

Em xinh say hi Ngo Lan Huong shared about her professional views and the past of almost not pursuing art.

Ukraine lost more than 1,460 soldiers last week

|

The Russian Ministry of Defense said on June 12 that Ukrainian forces lost more than 1,460 soldiers in the operating area of the Western Combat Group in the past week.

The moon's words "Binh Xuan Truong" and the journey to find the martyr's grave for 50 years

|

Thanh Hoa - For more than 50 years, Mr. Do Dinh Ninh's family has been deeply concerned about the journey to find the martyr's grave. Taking DNA samples from relatives of martyrs has ignited hope.

Groundbreaking ceremony for housing project for police forces in Tuyen Quang

Nguyễn Tùng |

Tuyen Quang - Housing project for the Police force in An Tuong ward with an area of 5.5 ha, scale of 822 apartments.

Creating consensus when arranging villages and residential groups in Tuyen Quang

Nguyễn Tùng |

With more than 85% of villages and residential groups in the area under arrangement, Tuyen Quang province is proactive, cautious and creating consensus when implementing.

Ready to start construction simultaneously of boarding schools in Tuyen Quang

Nguyễn Tùng |

Tuyen Quang - Preparations for the groundbreaking ceremony of 11 inter-level boarding schools for primary and secondary schools in border communes are being urgently implemented.