Chairman of Quang Ngai Provincial People's Committee directs to remove obstacles and accelerate construction of schools in border areas

ĐÔNG GIANG |

Quang Ngai - Despite facing difficulties in manpower and weather, the projects of ethnic minority boarding schools in the border area are still being accelerated.

On the afternoon of June 19, Mr. Nguyen Hoang Giang - Member of the Party Central Committee, Chairman of the Provincial People's Committee inspected the progress of the project to build inter-level boarding primary and secondary schools in border communes (phase 1) including Mo Rai, Ro Koi, Sa Loong and Duc Nong.

According to a report by the Western Quang Ngai Investment Project Management Board, the construction progress of inter-level ethnic minority boarding primary and secondary schools (phase 1) in the land border area is being accelerated.

Kiểm tra tiến độ thi công tại Trường Phổ thông Dân tộc nội trú liên cấp Tiểu học - THCS xã Rờ Kơi. Ảnh: HƠ JAN
Inspecting the construction progress at Ro Koi Commune Inter-level Ethnic Minority Boarding Primary and Secondary School. Photo: HO JAN

Up to now, the construction progress at Ro Koi Commune Inter-level Ethnic Minority Boarding Primary and Secondary School has reached about 79%; Duc Nong commune reached 73% and Sa Loong commune reached 67%. The project in Mo Rai commune alone has reached about 50%, slower than the set plan.

The total investment of the projects is more than 872 billion VND. Currently, the Western Quang Ngai Investment Project Management Board is implementing contractor selection according to a special mechanism, deploying equipment procurement to ensure progress of the project.

The construction progress of school projects in border areas is still facing many difficulties. The main reason is the shortage of human resources, affecting the construction progress. The projects are located in border areas, far from the center, and living conditions are still difficult, so it is difficult to attract labor, especially skilled labor.

The simultaneous deployment of many construction projects at the same time also makes the labor force even scarcer. In addition, seasonal changes and frequent rains in the afternoon are affecting the construction progress of completion items and technical infrastructure, affecting the overtime plans of contractors.

Mr. Nguyen Hoang Giang acknowledged the efforts of the construction units in the past time, and at the same time requested the Department of Education and Training to coordinate with localities to review learning needs, arrange a suitable teaching staff; organize and mobilize students to study at new inter-level schools, avoiding surplus and waste.

Ông Nguyễn Hoàng Giang - Chủ tịch UBND tỉnh Quảng Ngãi tặng quà, động viên các đơn vị thi công. Ảnh: HƠ JAN
Mr. Nguyen Hoang Giang - Chairman of Quang Ngai Provincial People's Committee presents gifts and encourages construction units. Photo: HO JAN

The Western Quang Ngai Investment Project Management Board reports on progress weekly to promptly remove arising difficulties and obstacles; supervise and urge construction units to ensure progress; urgently accelerate bidding for equipment procurement according to regulations.

On this occasion, Chairman of the Provincial People's Committee Nguyen Hoang Giang visited, presented gifts, and encouraged construction units to continue to strive to complete their tasks.

ĐÔNG GIANG
RELATED NEWS

Reviewing and removing difficulties for 111 projects in Quang Ngai

|

Quang Ngai is focusing on removing obstacles for 111 backlog and prolonged projects, of which 61 projects are expected to apply special mechanisms.

Quang Ngai accelerates land auctions, creating budget revenue

|

Quang Ngai is accelerating to complete procedures to auction 6 land plots in July, creating additional revenue for the budget.

Quang Ngai urgently rearranges and reorganizes villages and residential groups

|

Quang Ngai - Through review, the province identified 700 villages and residential groups that did not meet household scale standards and implemented a relocation plan throughout the province.

Modern space of Lao Dong Newspaper creates highlights at the 2026 National Press Festival

|

Hai Phong - The exhibition booth of Lao Dong Newspaper attracted a large number of delegates and visitors on the opening day of the 2026 National Press Festival.

Top 10 schools with the highest grade 10 benchmarks in Hanoi in 2026

|

Yen Hoa, Kim Lien, Le Quy Don - Ha Dong 3 high schools have the highest 10th grade benchmark scores in Hanoi this year with 26 points (on a 30-point scale).

The current condition of Vo Chi Cong street is being restored to its road surface

|

Hanoi - Vo Chi Cong Street is being restored to its road surface after a long period of partial barricades to serve the construction of the flood control system.

Forest fire in Quang Tri, hundreds of people put out the fire

|

Quang Tri - A forest fire broke out in Ninh Chau commune, hundreds of people were mobilized to fight the fire but by late afternoon it had not been completely extinguished.

Official answers for all high school graduation exam subjects in 2026

|

Official answers for all high school graduation exam subjects in 2026 have just been announced by the Ministry of Education and Training.

Reviewing and removing difficulties for 111 projects in Quang Ngai

ĐÔNG GIANG |

Quang Ngai is focusing on removing obstacles for 111 backlog and prolonged projects, of which 61 projects are expected to apply special mechanisms.

Quang Ngai accelerates land auctions, creating budget revenue

ĐÔNG GIANG |

Quang Ngai is accelerating to complete procedures to auction 6 land plots in July, creating additional revenue for the budget.

Quang Ngai urgently rearranges and reorganizes villages and residential groups

ĐÔNG GIANG |

Quang Ngai - Through review, the province identified 700 villages and residential groups that did not meet household scale standards and implemented a relocation plan throughout the province.