Minister of Construction inspects the progress of the expressway section through Khanh Hoa

Hữu Long |

Khanh Hoa - The Minister of Construction inspected a number of expressways passing through the area.

On the morning of April 3, Mr. Tran Hong Minh - Minister of Construction inspected the progress of the Khanh Hoa - Buon Ma Thuot Expressway Component 1 Project, Phase 1 (section through Khanh Hoa province).

According to the report of the Khanh Hoa Province Traffic and Agricultural Construction Investment Project Management Board (project investor), up to now, Ninh Hoa town has handed over 30.5km of site (reaching 96.83%).

For the Ha Thanh Resettlement Area Project, up to now, the Town Land Fund Development Center has handed over 7.05ha of the site to the management board (reaching 98.2%).

Bo truong Tran Hong Minh tang qua dong vien doi ngu ky su, cong nhan thi cong tai cong trinh duong bo cao toc Khanh Hoa - Buon Ma Thuot. Anh: Huu Long
Minister Tran Hong Minh presented gifts to encourage the team of engineers and construction workers at the Khanh Hoa - Buon Ma Thuot expressway project. Photo: Huu Long

Regarding the construction progress, the total completed output reached nearly 1,409 billion VND (38.91% of the total contract value).

The Head of the Ministry of Construction has inspected 2 locations, which are the intersection between the Van Phong - Nha Trang expressway and the Khanh Hoa - Buon Ma Thuot expressway; east of the Phuong Hoang tunnel.

Minister Tran Hong Minh encouraged a team of engineers and workers to directly execute at the construction site at the same time, requesting the investor of the project to coordinate with the local authorities to remove difficulties in terms of premises; The contractor promotes the mobilization of human resources, machinery and equipment to organize 3 shifts and 4 crews to accelerate the progress, ensuring the quality of the project.

The Khanh Hoa - Buon Ma Thuot Expressway is nearly 118km long with a total investment of nearly VND22,000 billion, divided into 3 component projects. Of which, component project 1 is 31.5km long with a total investment of VND 5,333 billion, located in Khanh Hoa province.

This project is invested by the Khanh Hoa Provincial Project Management Board for Investment in Construction of Agricultural and Transport Works and is connected to component project 2 (invested by Project Management Board 6) and component project 3 (managed by the Dak Lak Provincial People's Committee).

Hữu Long
TIN LIÊN QUAN

Reviewing and handling contractors behind schedule on Bien Hoa - Vung Tau Expressway

|

The Bien Hoa - Vung Tau Expressway section through Ba Ria - Vung Tau is expected to open to traffic on April 30. Meanwhile, the section through Dong Nai has not yet completed site clearance. The province is currently racing to complete the embankment before June 30 according to the schedule assigned by the Government.

Bottleneck at 2 expressway projects through Lang Son and Cao Bang

|

Lang Son - The Huu Nghi - Chi Lang and Dong Dang - Tra Linh expressway projects are racing to make efforts to open the route in 2025.

Tightening 4-wheeled motor vehicles for passenger vehicles in Khanh Hoa

|

Khanh Hoa - The locality will organize the placement of signs of maximum operating speed, signs prohibiting or restricting the operation of 4-wheeled vehicles with engines.

HCMC plans to clear 2,452 households to expand 4 gateway roads

|

Ho Chi Minh City plans to reclaim land from 4,730 households for 4 projects to upgrade and expand National Highways 1, 13, 22, and the North-South axis road. Of which, 2,452 households were cleared.

Intentionally violating legal regulations in 2 hospital projects in Ha Nam

|

The Government Inspectorate pointed out intentional violations of legal regulations in the implementation of 2 hospital projects in Ha Nam.

At the end of this morning's stock market trading session, VN-Index decreased by 47.77 points

|

bottom-fishing demand has appeared but could not help the stock market have a better trading session.

Mr. Trump unexpectedly sets negotiation conditions to reduce counterpart taxes

|

President Donald Trump has said he is ready to negotiate counterpart tax reductions if there is an attractive enough proposal.

A project abandoned for many years in Long Bien has resumed operations

|

Hanoi - The wastewater treatment plant of Viet Hung Urban Area (Viet Hung, Long Bien) has resumed operations after many years of "lying still".

Reviewing and handling contractors behind schedule on Bien Hoa - Vung Tau Expressway

HÀ ANH CHIẾN |

The Bien Hoa - Vung Tau Expressway section through Ba Ria - Vung Tau is expected to open to traffic on April 30. Meanwhile, the section through Dong Nai has not yet completed site clearance. The province is currently racing to complete the embankment before June 30 according to the schedule assigned by the Government.

Bottleneck at 2 expressway projects through Lang Son and Cao Bang

Khánh Linh |

Lang Son - The Huu Nghi - Chi Lang and Dong Dang - Tra Linh expressway projects are racing to make efforts to open the route in 2025.

Tightening 4-wheeled motor vehicles for passenger vehicles in Khanh Hoa

Bình Quý |

Khanh Hoa - The locality will organize the placement of signs of maximum operating speed, signs prohibiting or restricting the operation of 4-wheeled vehicles with engines.