Wastewater treatment plant in Long Bien is about to be handed over and put into operation

HỮU CHÁNH |

Hanoi - The wastewater treatment plant in Long Bien with a capacity of 7,600 m3/day and night is about to be handed over and put into operation after many years of abandonment.

In 2014, after submitting for approval the planning and organizing a construction bidding, the Viet Hung Urban Area Wastewater Treatment Plant (Long Bien District, Hanoi) was started.

The wastewater treatment plant is a project under the Ngo Gia Tu Street renovation and renovation project and investment in infrastructure construction of Viet Hung Urban Area invested by the Housing and Urban Development Investment Corporation (HUD).

s
The wastewater treatment plant of Viet Hung Urban Area is built next to Long Bien Park (Hanoi). Photo: Huu Chanh
Cong trinh hoan thanh xay dung tu nam 2017. Anh: Huu Chanh
The project was completed in 2017 and has been abandoned since then. Photo: Huu Chanh

In terms of scale, the Wastewater Treatment Station has a capacity of 7,600 m3/day and night, applying AO treatment technology (Anoxic - Oxic), after treatment, the wastewater is discharged into the Viet Hung ditch, then flowing into the Cau Bai River.

The project was completed in 2017, but has not yet been handed over to the management unit. Meanwhile, domestic wastewater of more than 20,000 people living in Viet Hung Urban Area still flows directly into Viet Hung ditch every day, causing environmental pollution.

Hang rao hoen gi theo thoi gian. Anh: Huu Chanh
The fence has rusted over time. Photo: Huu Chanh
Nhieu hang muc trong Tram xu ly nuoc thai thoi gian dai chua duoc dua vao su dung. Anh: Huu Chanh
Many items in the Wastewater Treatment Plant have not been put into use for a long time. Photo: Huu Chanh
Nhieu s
Some items have just been repaired and maintained by the authorities after a long period of deterioration. Photo: Huu Chanh

According to the Hanoi Department of Construction, the Viet Hung Urban Area Wastewater Treatment Plant has been put into trial operation since January 2017 and continues to complete the procedures for project acceptance, installing an additional automatic monitoring system in the project to meet current regulations, and carrying out the handover work after investment.

The management and operation of the Viet Hung Urban Area Wastewater Treatment Plant before handover will be carried out by the investor - HUD.

By May 2022, based on the request of HUD, the Department of Construction had organized a review and received the handover of Viet Hung Wastewater Treatment Plant.

During the completion of procedures for receiving the handover to organize the selection of contractors for management and operation, according to the commitment to the city, HUD will continue to operate and maintain the wastewater treatment plant using the unit's funding and overcome the shortcomings during the counting process, including: Automatic monitoring system and equipment and chemicals of the laboratory are damaged and not working; the station is rusty, some construction items are peeling; overgrown weeds encroach on the grass carpet area; the discharge license expires in January 2023.

Mot hang muc cong trinh trong du an dang duoc don vi gap rut thi cong. Anh: Huu Chanh
A construction item is being urgently constructed by the unit. Photo: Huu Chanh
Cong vao Tram xu ly nuoc thai tren duong Doan Khue. Anh: Huu Chanh
Entrance to Viet Hung Wastewater Treatment Plant on Doan Khue Street. Photo: Huu Chanh
Du kien, Tram xu ly nuoc thai se duoc ban giao trong thang 4.2025. Anh: Huu Chanh
It is expected that the wastewater treatment plant of Viet Hung Urban Area will be handed over in April 2025. Photo: Huu Chanh

Up to now, the Department of Construction has completed the selection of contractors to receive the official management and operation of Viet Hung Wastewater Treatment Plant.

The degraded items inside the Wastewater Treatment Plant are currently being renovated and repaired by HUD to ensure requirements. It is expected that the unit will officially hand over to the Hanoi Department of Construction, the contractor for management and operation in April 2025.

HỮU CHÁNH
TIN LIÊN QUAN

Wastewater treatment plant in Hanoi has been shelved for many years

|

Son Dong wastewater treatment plant (Hanoi) was invested with hundreds of billions of dong but has been "shelved" for a long time.

Vietnamese tourists are required to declare online when traveling to Thailand

|

From May 1, all international tourists traveling to Thailand must fill in their digital entry cards before entering the country. This is something Vietnamese tourists need to pay attention to.

The Ministry of Construction has many violations when adjusting the planning of the capital area

|

The Government Inspectorate has just pointed out many violations in adjusting the Construction Planning of the Capital Region.

The Inspection Committee proposes to discipline the former Vice Chairman of the Dong Nai Provincial People's Committee

|

The Provincial Party Committee's Inspection Committee proposed to discipline former Vice Chairman of Dong Nai Provincial People's Committee Vo Van Chanh for related land violations.

Ho Chi Minh City sidewalks "transformed", people are excited about clean and beautiful walking paths

|

HCMC - After the renovation process, many sidewalks in the city center have taken on a new look, people are excited because they have a clean and beautiful walking space.

Hanoi Police lost the first leg of the Southeast Asian Cup C1 semi-final

|

Hanoi Police lost 0-1 to PSM Makassar in the first leg of the 2024-2025 Southeast Asian Cup C1 semi-final on the evening of April 2.

A principal was accused of failing to meet standards with teachers

|

Thanh Hoa - The principal of a kindergarten in a mountainous district of Thanh Hoa was accused of committing many violations and lacking standards in behavior towards teachers.

Bad debt is likely to lose capital at Sacombank of nearly VND 8,870 billion

|

Bad debt at Sacombank increased by 18% in 2024, to VND 12,957 billion. Of which, debt is likely to lose nearly VND 8,870 billion, up 81% over the beginning of the year.

Bất cập hệ thống xử lý nước thải khu công nghiệp ở Quảng Trị

HƯNG THƠ - HOÀI LUÂN |

Quảng Trị - Phần lớn các khu công nghiệp, cụm công nghiệp ở tỉnh Quảng Trị chưa được đầu tư hệ thống xử lý nước thải.

Wastewater treatment plant in Hanoi has been shelved for many years

NGỌC THÙY |

Son Dong wastewater treatment plant (Hanoi) was invested with hundreds of billions of dong but has been "shelved" for a long time.

Vận hành thử Nhà máy xử lý nước thải Yên Xá

Minh Hạnh |

Hà Nội - Nhà máy xử lý nước thải Yên Xá bắt đầu vận hành thử nghiệm 6 tháng sau 8 năm khởi công xây dựng.