CC1 Company is behind schedule in construction of expressway project in Dak Lak

BẢO TRUNG |

Dak Lak - Despite being reminded by the investor many times, Construction Corporation No. 1 is still behind schedule on the Khanh Hoa - Buon Ma Thuot expressway.

To prolong the progress

According to the investigation, package 3, component project 3, on the Khanh Hoa - Buon Ma Thuot expressway is being constructed by contractor Construction Corporation No. 1 - JSC (abbreviated as CC1).

CC1 is under construction behind schedule with a workload of up to 25.45%, equivalent to VND122.92 billion. Especially the 2km road section, part of package No. 3, the first area of the route from Km112+740 - Km114+740.

In the past, the contractor has been very slow and lacked initiative in the construction and implementation of input materials. The unit also does not have specific measures to speed up the construction progress.

Du treo khau hieu ngay o cong truong nhung CC1 van thi cong i ach, khong hoan thanh tien do de ra. Anh: Bao Trung
Despite hanging a slogan right at the construction site, CC1 is still slow to construct, failing to complete the set progress. Photo: Bao Trung

Mr. Nguyen Tai Minh, Deputy Director of the Dak Lak Province Traffic Construction Investment and Rural Development Project Management Board (abbreviated as Dak Lak Province Project Management Board, investor) informed that the unit has repeatedly urged CC1 to remind at meetings and made recordings to inspect the site.

However, the unit has not yet fixed the problem, the construction is very slow, and the human resources on the project are not arranged to meet the progress requirements. Even the machinery, equipment, and materials arranged by the contractor at the construction site have not been guaranteed according to the committed mobilization schedule.

According to Mr. Minh, after checking at the site, the contractor organized the construction teams that were not serious. The contractor also almost did not take overtime or work overtime as committed.

Due to the CC1's prolonged delay in construction progress and lack of initiative in preparing materials... it is easy to increase the risk of overall delay in the expressway project.

Considering changing contractors

In the face of the above situation, the Dak Lak Provincial Project Management Board held a meeting to invite CC1's leaders to a meeting to review the progress and consider transferring the volume as committed.

CC1 has issued a commitment document (2nd time) on speeding up the construction progress. However, the contractor is still behind schedule according to the committed contents.

Cac phuong tien cua nha thau CC1 thi cong cham chap tai du an (chup ngay 8.3.2025). Anh: Bao Trung
The vehicles of CC1 contractor are slow to construct at the project (taken on March 8, 2025). Photo: Bao Trung

Through on-site inspection, the implementation value in the last 2 weeks was very low, not guaranteed as committed. Of which, the third week of February 2025 reached 1.5 billion VND (total 7.3 billion VND); the fourth week of February 2025 reached 2.1 billion VND (total 7.3 billion VND).

If CC1 continues to be behind schedule, the investor will consider and propose to transfer the volume according to the commitment. In particular, it is proposed to relocate the entire remaining volume of the 2 km section (belonging to package No. 3 of the first section of the route from Km112+740 - Km114+740).

Mr. Nguyen Tai Minh, Deputy Director of the Dak Lak Provincial Project Management Board, said: "If CC1 continues to be behind schedule, we will report to the Provincial People's Committee for instructions to replace the contractor. Thereby, ensuring the Khanh Hoa - Buon Ma Thuot expressway reaches the finish line according to the set plan".

BẢO TRUNG
TIN LIÊN QUAN

HCMC builds 2 major intersections connecting Ben Luc - Long Thanh Expressway

|

HCMC - The two intersections connecting Ben Luc - Long Thanh Expressway with Rung Sac Road and National Highway 50 will be approved for investment in the second quarter of 2025, starting construction in 2026.

Tuyen Quang proposes to add VND 7,237 billion to expressway project

|

Tuyen Quang province proposed that the Government provide additional support of VND 7,237 billion to complete both phases of the Tuyen Quang - Ha Giang expressway project.

Allocate capital to soon start construction of Ninh Binh - Hai Phong expressway

|

Ninh Binh - Ninh Binh province is determined to speed up the progress of site clearance, select contractors, and focus capital to start the Ninh Binh - Hai Phong expressway project.

Heavy rain worries affecting the progress of the North - South expressway

|

Ha Tinh In Ha Tinh, it has been raining for the past 4 days, affecting the construction of the North-South expressway, causing great pressure when the main route must be completed and opened to traffic on April 30.

Thousand-billion-dong expressways are about to be deployed in mountainous areas

|

Expressway projects with a total investment of thousands of billions of VND are expected to synchronize transport infrastructure, promote socio-economic development of mountainous provinces.

What did the President of the Cambodian King contest say about the controversy

|

In recent days, the contestants of a male pageant in Cambodia have suddenly caused a stir and attracted attention on social networks.

Measles epidemic is not over yet, special attention to prevent diseases for children

|

The measles epidemic is forecast to decrease in general but not stop. Therefore, people should not be subjective or negligent in preventing epidemics.

General Luong Tam Quang receives new assignment

|

General Luong Tam Quang - Politburo member, Minister of Public Security - was elected to hold the position of Chairman of the National Data Society.

HCMC builds 2 major intersections connecting Ben Luc - Long Thanh Expressway

MINH QUÂN |

HCMC - The two intersections connecting Ben Luc - Long Thanh Expressway with Rung Sac Road and National Highway 50 will be approved for investment in the second quarter of 2025, starting construction in 2026.

Tuyen Quang proposes to add VND 7,237 billion to expressway project

Việt Bắc |

Tuyen Quang province proposed that the Government provide additional support of VND 7,237 billion to complete both phases of the Tuyen Quang - Ha Giang expressway project.

Allocate capital to soon start construction of Ninh Binh - Hai Phong expressway

NGUYỄN TRƯỜNG |

Ninh Binh - Ninh Binh province is determined to speed up the progress of site clearance, select contractors, and focus capital to start the Ninh Binh - Hai Phong expressway project.

Heavy rain worries affecting the progress of the North - South expressway

TRẦN TUẤN |

Ha Tinh In Ha Tinh, it has been raining for the past 4 days, affecting the construction of the North-South expressway, causing great pressure when the main route must be completed and opened to traffic on April 30.

Thousand-billion-dong expressways are about to be deployed in mountainous areas

Lam Thanh |

Expressway projects with a total investment of thousands of billions of VND are expected to synchronize transport infrastructure, promote socio-economic development of mountainous provinces.