Heavy rain worries affecting the progress of the North - South expressway

TRẦN TUẤN |

Ha Tinh In Ha Tinh, it has been raining for the past 4 days, affecting the construction of the North-South expressway, causing great pressure when the main route must be completed and opened to traffic on April 30.

According to a reporter from Lao Dong Newspaper, on March 8, in Ha Tinh, it was still raining and cold. Therefore, the construction site of the North - South expressway, Bai Vot - Ham Nghi section; Ham Nghi - Vung Ang in this locality is quite deserted, many machines such as excavators and road rollers are lying still around the construction workshop without operation.

Mr. Dang Dinh Duyen - Construction Commander of Xuan Truong Construction Private Enterprise for the Ham Nghi - Vung Ang section - shared that currently, package 11 under his command (22km long) has 50% of the C16 asphalt paving.

The main work at present is to continue paving asphalt. However, due to the rainy weather, they had to stop and could not be paved.

"If the rain cannot be done, the sun will rise and we will have to make up for the volume. It was sunny, so we had to work overtime, work in shifts, work through the day and work all night, said Mr. Duyen.

Cong truong cao toc kha yen ang do troi mua. Anh: Tran Tuan.
The expressway construction site is quite quiet due to the rain. Photo: Tran Tuan.

Mr. Tran Dinh Ngan - Construction Commander of Corporation 319 - Ministry of National Defense (the construction unit of nearly 13km of the North - South expressway, Bai Vot - Ham Nghi section) - said that since the Lunar New Year, in Ha Tinh, the heavy rain has affected the construction of the unit, especially at the time when the current asphalt paving construction is being focused on.

Up to now, the construction volume of the package that Corporation 319 - Ministry of National Defense has implemented has reached 80% of the plan, of which the roadbed construction has reached 95%, the road foundation has reached 85%, and asphalt concrete pavement of all kinds has reached 50-60%.

Mr. Hoang Chien Thang - Executive Director of the Thang Long Project Management Board (investor of the North - South expressway project, Bai Vot - Ham Nghi section) - said that due to the rainy weather, contractors could only construct the crushed stone aggregate but the asphalt concrete pavement could not be constructed.

"From now until April 30, there is not much time left. Therefore, if the rain continues, it will be very worrying. Hopefully the weather will improve so that contractors can focus on construction, work overtime, and increase teams to speed up the progress to complete the opening of the main route before April 30 as directed by the Government, Mr. Thang shared.

Nhung chiec may lu dang nam im do thoi tiet xau khong the thi cong. Anh: Tran Tuan.
The rollers are lying idle due to bad weather and cannot be constructed. Photo: Tran Tuan.

According to Mr. Thang, the North - South Eastern Expressway phase 2021 - 2025, Bai Vot - Ham Nghi section, has currently completed about 82% of the construction volume.

It is known that the Ham Nghi - Vung Ang section has reached about 88% of the construction volume.

The North - South Expressway Project in the East phase 2021 - 2025 through Ha Tinh province with a length of 102.38km, including 3 component projects: Bai Vot - Ham Nghi with a length of 35.28km, Ham Nghi - Vung Ang with a length of 54.2km and Vung Ang - Bung with a length of 12.9km.

TRẦN TUẤN
TIN LIÊN QUAN

Speeding up the construction progress of the North-South expressway through Quang Binh

|

Quang Binh - The North-South Expressway construction unit through the area is mobilizing maximum human resources and equipment, working 3 consecutive shifts to ensure the project's progress.

Prime Minister requests "just work" to complete North-South Expressway

|

The Prime Minister requested units to concentrate human and material resources to soon complete the North-South expressway.

Workers work through Tet on the North-South Expressway

|

Quang Binh - Even though it was the days before and during Lunar New Year, workers still stayed at the construction site, working through the holiday to ensure the progress of the expressway project.

A major fire collapsed part of a factory in Ho Chi Minh City

|

HCMC - On March 17, HCMC Police are investigating and clarifying the cause of the fire at an iron workshop in Hoc Mon district that caused many workers to flee.

Lack of seafaring workers, many fishing boats in Quang Tri are stranded

|

At the end of the Northern fish crop and preparing to enter the Southern fish fishing season, in many coastal localities of Quang Tri province, many boats are still ashore due to lack of workers.

Social networks are becoming potential forces

|

According to the Standing Committee of the Secretariat Tran Cam Tu, social networks are becoming a potential power force for the ideological life of millions of people.

What is the status of the first gold enterprise on the stock exchange

|

Lao Cai - Due to the failure to extend the mining license at Minh Luong gold mine, the stock price of Lao Cai Gold Joint Stock Company decreased sharply.

Always consider lifelong learning as the key to keeping up with the trend

|

In the era of industrialization and modernization, the country is transforming, requiring party members and union members to learn more to keep up with the trend.

Speeding up the construction progress of the North-South expressway through Quang Binh

CÔNG SÁNG |

Quang Binh - The North-South Expressway construction unit through the area is mobilizing maximum human resources and equipment, working 3 consecutive shifts to ensure the project's progress.

Prime Minister requests "just work" to complete North-South Expressway

Khánh Linh |

The Prime Minister requested units to concentrate human and material resources to soon complete the North-South expressway.

Workers work through Tet on the North-South Expressway

CÔNG SÁNG |

Quang Binh - Even though it was the days before and during Lunar New Year, workers still stayed at the construction site, working through the holiday to ensure the progress of the expressway project.