Tuyen Quang province proposed that the Government provide additional support of VND 7,237 billion to complete both phases of the Tuyen Quang - Ha Giang expressway project.

On March 8, the Government Inspection Team led by Deputy Prime Minister Bui Thanh Son worked in Tuyen Quang, reviewing and removing difficulties and obstacles related to key transport projects planned to be completed in 2025.

For the Tuyen Quang - Ha Giang expressway project (phase 1) through Tuyen Quang province, there is currently 5.7 km of land that has not been handed over, lacking 0.35 million m3 of stone, lacking 1.97 million m3 of land. Construction output reached 28%, 7% behind schedule compared to the contract.

Tuyen Quang province proposed that the Government consider additional support of VND1,800 billion from the central budget in 2025 to complete phase 1 in 2025 and add VND5,437 billion to implement phase 2.

Pho Thu tuong Bui Thanh Son kiem tra tien do cao toc Tuyen Quang - Ha Giang. Anh: Ngoc Hung.
Deputy Prime Minister Bui Thanh Son inspects the progress of the Tuyen Quang - Ha Giang expressway. Photo: Ngoc Hung.

Deputy Prime Minister Bui Thanh Son requested that the site clearance for the Tuyen Quang - Ha Giang expressway project should be completely completed, and the telecommunications technical infrastructure should be relocated to hand over the entire site to the contractors for construction in March 2025. At the same time, urge the completion of items before December 31, 2025.

Regarding the capital source as proposed by the province, the Deputy Prime Minister requested the Ministry of Finance to study and consider the proposal to supplement funding in Tuyen Quang province to promptly meet the capital demand in project implementation.

Việt Bắc
RELATED NEWS

Allocate capital to soon start construction of Ninh Binh - Hai Phong expressway

|

Ninh Binh - Ninh Binh province is determined to speed up the progress of site clearance, select contractors, and focus capital to start the Ninh Binh - Hai Phong expressway project.

Heavy rain worries affecting the progress of the North - South expressway

|

Ha Tinh In Ha Tinh, it has been raining for the past 4 days, affecting the construction of the North-South expressway, causing great pressure when the main route must be completed and opened to traffic on April 30.

The large construction site of the 6,800 billion VND expressway in Tuyen Quang

|

Tuyen Quang - The expressway project through Tuyen Quang province is 77km long, with a total investment of VND6,800 billion.

Gasoline and oil prices today 21.1: Simultaneously sharply decrease

|

Gasoline prices today 21.1: World gasoline prices today simultaneously decreased sharply. WTI oil and Brent oil are recording a decrease of more than 1%.

Do not leave any gaps or dark areas that inspection and supervision work cannot reach

|

Speaking at the 14th National Congress, Mr. Tran Van Ron mentioned not leaving "battlerooms", "dark areas" that the Party's inspection and supervision work cannot reach.

The 3 driving forces to bring Vietnam to break through and escape the middle-income trap

|

At the 14th Congress, according to Minister Nguyen Manh Hung, Vietnam must rely on science and technology, innovation and digital transformation to escape the middle-income trap.

1 million social housing units will be completed 2 years early, with over 1.6 million units by 2030

|

The Minister of Construction said that he will strive to complete the goal of having 1 million social housing units by 2 years and over 1.6 million units by 2030.

University rankings: 11 Vietnamese universities with industry in the top of the world

|

11 Vietnamese universities have majors in the top world rankings. Business and Economics, Engineering, Computer Science,... are groups of majors ranked high.

Allocate capital to soon start construction of Ninh Binh - Hai Phong expressway

NGUYỄN TRƯỜNG |

Ninh Binh - Ninh Binh province is determined to speed up the progress of site clearance, select contractors, and focus capital to start the Ninh Binh - Hai Phong expressway project.

Heavy rain worries affecting the progress of the North - South expressway

TRẦN TUẤN |

Ha Tinh In Ha Tinh, it has been raining for the past 4 days, affecting the construction of the North-South expressway, causing great pressure when the main route must be completed and opened to traffic on April 30.

The large construction site of the 6,800 billion VND expressway in Tuyen Quang

Lam Thanh |

Tuyen Quang - The expressway project through Tuyen Quang province is 77km long, with a total investment of VND6,800 billion.