Tuyen Quang proposes to add VND 7,237 billion to expressway project

Việt Bắc |

Tuyen Quang province proposed that the Government provide additional support of VND 7,237 billion to complete both phases of the Tuyen Quang - Ha Giang expressway project.

On March 8, the Government Inspection Team led by Deputy Prime Minister Bui Thanh Son worked in Tuyen Quang, reviewing and removing difficulties and obstacles related to key transport projects planned to be completed in 2025.

For the Tuyen Quang - Ha Giang expressway project (phase 1) through Tuyen Quang province, there is currently 5.7 km of land that has not been handed over, lacking 0.35 million m3 of stone, lacking 1.97 million m3 of land. Construction output reached 28%, 7% behind schedule compared to the contract.

Tuyen Quang province proposed that the Government consider additional support of VND1,800 billion from the central budget in 2025 to complete phase 1 in 2025 and add VND5,437 billion to implement phase 2.

Pho Thu tuong Bui Thanh Son kiem tra tien do cao toc Tuyen Quang - Ha Giang. Anh: Ngoc Hung.
Deputy Prime Minister Bui Thanh Son inspects the progress of the Tuyen Quang - Ha Giang expressway. Photo: Ngoc Hung.

Deputy Prime Minister Bui Thanh Son requested that the site clearance for the Tuyen Quang - Ha Giang expressway project should be completely completed, and the telecommunications technical infrastructure should be relocated to hand over the entire site to the contractors for construction in March 2025. At the same time, urge the completion of items before December 31, 2025.

Regarding the capital source as proposed by the province, the Deputy Prime Minister requested the Ministry of Finance to study and consider the proposal to supplement funding in Tuyen Quang province to promptly meet the capital demand in project implementation.

Việt Bắc
TIN LIÊN QUAN

Allocate capital to soon start construction of Ninh Binh - Hai Phong expressway

|

Ninh Binh - Ninh Binh province is determined to speed up the progress of site clearance, select contractors, and focus capital to start the Ninh Binh - Hai Phong expressway project.

Heavy rain worries affecting the progress of the North - South expressway

|

Ha Tinh In Ha Tinh, it has been raining for the past 4 days, affecting the construction of the North-South expressway, causing great pressure when the main route must be completed and opened to traffic on April 30.

The large construction site of the 6,800 billion VND expressway in Tuyen Quang

|

Tuyen Quang - The expressway project through Tuyen Quang province is 77km long, with a total investment of VND6,800 billion.

Hot mountain, illegal exploitation of ornamental stones in Yen Bai

|

Yen Bai - Illegal exploitation of ornamental stones is happening everywhere, despite reminders and penalties from authorities.

Investors respond to the Kim Van - Kim Lu connection road

|

Lao Dong Newspaper has just published a series of articles, Kim Van - Kim Lu people hope for a connecting road. The investor has responded in writing.

Gold ring price may reach 100 million VND/tael

|

The domestic gold ring price is increasing sharply. Experts predict that the price of gold rings may reach 100 million VND/tael in the near future.

A major fire collapsed part of a factory in Ho Chi Minh City

|

HCMC - On March 17, HCMC Police are investigating and clarifying the cause of the fire at an iron workshop in Hoc Mon district that caused many workers to flee.

Lack of seafaring workers, many fishing boats in Quang Tri are stranded

|

At the end of the Northern fish crop and preparing to enter the Southern fish fishing season, in many coastal localities of Quang Tri province, many boats are still ashore due to lack of workers.

Allocate capital to soon start construction of Ninh Binh - Hai Phong expressway

NGUYỄN TRƯỜNG |

Ninh Binh - Ninh Binh province is determined to speed up the progress of site clearance, select contractors, and focus capital to start the Ninh Binh - Hai Phong expressway project.

Heavy rain worries affecting the progress of the North - South expressway

TRẦN TUẤN |

Ha Tinh In Ha Tinh, it has been raining for the past 4 days, affecting the construction of the North-South expressway, causing great pressure when the main route must be completed and opened to traffic on April 30.

The large construction site of the 6,800 billion VND expressway in Tuyen Quang

Lam Thanh |

Tuyen Quang - The expressway project through Tuyen Quang province is 77km long, with a total investment of VND6,800 billion.