The multi-billion-dong road project in Hanoi is about to resume construction

HỮU CHÁNH |

Hanoi - The Ring Road 2.5 project from Dam Hong to National Highway 1A is about to resume construction after many years of "shelving" due to problems.

The project to build the Ring Road 2.5, Dam Hong - National Highway 1A section (Hoang Mai district, Hanoi) is invested in the form of a BT (build - transfer) contract with a length of 2.06km, with a total investment of more than 1,300 billion VND.

The project started in 2014 and was expected to be completed in 2017 but was behind schedule.

In 2020, the project was temporarily suspended when it had only reached about 40% of the workload. The reason is that the contract implementation period has not been extended, and the adjusted feasibility study report has not been approved.

Hon 10 nam xay dung, duong Vanh dai 2,5 doan Dam Hong - Quoc lo 1A van dang do. Anh: Huu Chanh
After more than 10 years of construction, the Ring Road 2.5 section Dam Hong - National Highway 1A (Hanoi) is still unfinished. Photo: Huu Chanh
Nhieu doan tro thanh noi tap ket rac thai, gay mat mi quan, o nhiem moi truong. Anh: Huu Chanh
Many sections have become garbage collection places, causing loss of aesthetics and environmental pollution. Photo: Huu Chanh

According to Lao Dong, after more than 10 years since the groundbreaking date, the project is still in disarray and unfinished. Many sections of the road have become garbage dumps, construction material storage areas, and dusty, causing great frustration for people.

According to the investor's report, up to now, package No. 1 (section 1, Km0+00 to Km1+381.7) has been organized with a volume of about 1,270m/1,381.7m. Since 2020, this package has been suspended due to the extension of the BT contract.

For package No. 2 (construction of L3 bridge across Lu river, route Km1+394) has organized the construction of 20 bored piles, the entire bridge piers and cast the entire girders. The bridge abutment and remaining items of the bridge cannot be constructed due to lack of land and the BT contract has not been extended.

As for package No. 3 (section 3, Km1+405.85 - Km1+600), although the site has been handed over, construction cannot be carried out because the site is still encroached by some households, the adjusted construction drawing design has not been approved, the BT contract has not been extended.

Cau L3 qua song Lu da bo hoang nhieu nam. Anh: Huu Chanh
The L3 bridge over the Lu River has been abandoned for many years. Photo: Huu Chanh
s
The L3 bridge has completed 20 bored piles, all bridge piers and cast all girders. Photo: Huu Chanh

On 9.5.2025, under the authorization of the Chairman of the Hanoi People's Committee, Director of the Management Board of the Investment Project Construction of Hanoi Transport Project Ngo Ngoc Van signed the Appendix of BT 02.2025 Investment Project on construction of Ring Road 2.5 (section from Dam Hong to National Highway 1A) with investors of Hanoi Housing and Urban Development Joint Stock Company - Hoang Ha Construction Company Limited, Hoang Ha Construction Company Limited - Hanoi, extension of BT project contract until the end of the first quarter of 2026 due to the main problems in the site clearance.

Diem dau du an tai Dam Hong. Anh: Huu Chanh
The starting point of the project is at Dam Hong. Photo: Huu Chanh
s
The end point of the route will connect with the Kim Dong - Giai Phong underpass. Photo: Huu Chanh

The Chairman of the Hanoi People's Committee has chaired meetings with relevant departments and branches twice to resolve the problems of this project.

The Hanoi People's Committee has directed the restart of the project on May 27, to complete it in sync with the progress of opening the Kim Dong - Giai Phong underpass.

HỮU CHÁNH
TIN LIÊN QUAN

Tomorrow, Hanoi will start construction of a bridge worth more than 20,000 billion VND connecting Tay Ho with Dong Anh

|

Hanoi - The Tu Lien Bridge project and the approach roads at both ends of the Tay Ho bridge connecting Dong Anh, with an investment capital of more than 20,000 billion VND, will start construction tomorrow (May 19).

Hanoi will build 7 more bridges across the Red River

|

Hanoi - In addition to closing the belt roads, national highways in the center..., the city will invest in 7 large bridges across the Red River to reduce traffic congestion.

7 students in Quang Ninh were swept away by floodwaters, 2 children died, 2 children are still missing

|

Quang Ninh - 7 students in Hai Ha district, Quang Ninh province went swimming in a stream when they were suddenly swept away by the flood.

Rumors of fake eggs surrounding livestock farmers are in trouble

|

The information about "fake eggs" not only makes consumers confused but also directly affects farmers' livestock production.

A series of streets in Hanoi were flooded after the rain on the afternoon of May 21

|

Hanoi - After the rain on the afternoon of May 21, many streets in Hanoi were flooded and had water stagnant.

Hanoi Police lost the Southeast Asian Championship after losing in penalty shootout

|

On the evening of May 21, Hanoi Police lost to Buriram United after a penalty shootout in the second leg of the 2024-2025 Southeast Asian Cup C1 final.

Strengthening regulations related to the Fatherland Front in the 2013 Draft Amendment to the Constitution

|

HCMC - The Vietnam Fatherland Front Committee of HCMC solicited opinions on amending the 2013 Constitution. Lawyers commented and proposed to clarify many regulations on government and social organizations.

Checking DJ Ngan 98's weight loss product in Ho Chi Minh City, the company closed

|

HCMC - The Department of Food Safety of HCMC inspects the weight loss product of DJ Ngan 98. However, at the time of inspection, the company's office was closed and no samples had been taken.

Tomorrow, Hanoi will start construction of a bridge worth more than 20,000 billion VND connecting Tay Ho with Dong Anh

HỮU CHÁNH - KHÁNH AN |

Hanoi - The Tu Lien Bridge project and the approach roads at both ends of the Tay Ho bridge connecting Dong Anh, with an investment capital of more than 20,000 billion VND, will start construction tomorrow (May 19).

Loạt công trình xây dựng trái phép ở Hà Nội bị yêu cầu tháo dỡ

NHÓM PV |

Hà Nội - Những ngày gần đây, lực lượng chức năng các quận, huyện trên địa bàn thành phố đồng loạt ra quân, xử lý vi phạm về đất đai, trật tự xây dựng.

Hanoi will build 7 more bridges across the Red River

Hữu Chánh |

Hanoi - In addition to closing the belt roads, national highways in the center..., the city will invest in 7 large bridges across the Red River to reduce traffic congestion.